Design-Build Facilitates Completion of L.A.'s Expo Line Phase 2

The 6.6-mile Expo Line will improve transportation mobility along the corridor, provide an alternative to the heavily-congested I-10 freeway and east-west arterials, and increase the capacity of the transportation system in Los Angeles County.

by Bruce Ross
September 1, 2015
Design-Build Facilitates Completion of L.A.'s Expo Line Phase 2

The Exposition/Bundy aerial station will feature a center platform, which will be accessible via stairs and elevator, on a bridge structure over Bundy Dr., just north of Exposition Blvd. Nearby destinations include business centers and the West Los Angeles and Mar Vista neighborhoods. The station’s park-and-ride facility is a surface lot with approximately 250 spaces. Passengers can make connections to Santa Monica Big Blue Bus lines.

6 min to read


The Exposition/Bundy aerial station will feature a center platform, which will be accessible via stairs and elevator, on a bridge structure over Bundy Dr., just north of Exposition Blvd. Nearby destinations include business centers and the West Los Angeles and Mar Vista neighborhoods. The station’s park-and-ride facility is a surface lot with approximately 250 spaces. Passengers can make connections to Santa Monica Big Blue Bus lines.

What does it take to get Angelenos off the freeway, out of their cars and onto a light rail transit (LRT) line for the 15.2-mile trip between downtown Los Angeles and Santa Monica, L.A.’s beachside neighbor? With the ability to allow riders to make the journey from downtown to the beach in approximately 45 minutes — even during rush hour — the Exposition (Expo) Line may hold the key.

Expo Line Phase 1, an 8.6-mile LRT line with 12 stations between downtown Los Angeles and Culver City, opened in April 2012. Expo Line Phase 2 — the 6.6-mile extension under construction between Culver City and Santa Monica, comprising seven new stations, seven major bridges, and three park-and-ride lots with approximately 570 spaces — is due to open in 2016.

Improve mobility
By 2030, the completed Expo Line is expected to attract a ridership of approximately 64,000 per day. The Expo Line will improve transportation mobility for residents and visitors along the corridor; provide an alternative to the heavily congested I-10 freeway and east-west arterials; increase the capacity of the transportation system in Los Angeles County; and improve access to employment, education and recreation in downtown L.A., Culver City, Santa Monica and other destinations along the corridor.

Ad Loading...

The state legislature established the Exposition Construction Authority (Expo Authority) to plan, design and construct the Expo Line from downtown to Santa Monica. When Phase 2 is completed, the entire Expo Line will be owned and operated by Los Angeles County Metropolitan Transportation Authority (Metro), the regional transportation planning agency for Los Angeles County.  

The Palms elevated station will feature a center platform, which will be accessible via stairs and elevators, on the northwest corner of National Blvd. and Palms Blvd. Nearby destinations include the Palms neighborhood, schools, a shopping center and a public park. Passengers can make connections to Santa Monica Big Blue Bus and Culver City Bus lines.

The total project cost of Phase 2, at $1.5 billion, includes costs for design, construction, utility relocation, light rail vehicles and real estate. The Phase 2 funding agreement between Metro and the Expo Authority provided the guidelines by which Metro is funding the project through a half-cent sales tax revenue as well as state and local funds.

Expo Authority awarded a design-build contract to a joint venture of Skanska USA and Rados Construction Inc. for Expo Phase 2. As lead designer for the Skanska-Rados joint venture, Parsons Brinckerhoff provided track design and station design, incorporating bikeway facilities and pedestrian links; design of the track guideway, structures, traction power system, overhead catenary system (OCS) and communication ductwork; design for 24 at-grade and above-grade street crossings; three park-and-ride lots; drainage and road improvements for at-grade crossings; and relocation of utilities.

Streamlined approach
Under the design-build project delivery method, the design-build team works under a single contract with the project owner to provide integrated design and construction services. A streamlined approach with a single point of responsibility, design-build is an alternative to the traditional design-bid-build delivery method in which design and construction services are split between separate entities and contracts.

A proven team approach for efficient construction of highways and buildings, the design-build method is gaining momentum in the transit industry. The Gold Line light rail line from Los Angeles to Pasadena was among the earliest transit design-build projects completed in the U.S. Following this success, Expo Phase 1 and Phase 2 were also built utilizing the design-build method.  

Ad Loading...

“Design-build provides an integrated contracting vehicle for the design and construction of a project,” says Eric Olson, chief project officer, Exposition Construction Authority. “When done successfully, it results in a collaborative effort between the construction contractor, designer and the owner. This facilitates a cost-effective and constructible design that is consistent with the vision of the owner.”

The 26th Street/Bergamot at-grade station will feature two side platforms located adjacent to Bergamot Station, on the southeast corner of Olympic Blvd. and 26th St. Nearby destinations include an arts center, a hospital, an office complex and public parks. Passengers can make connections to a Santa Monica Big Blue Bus line.

As a team approach, design-build takes experience, strong relationships and commitment to a common goal. For Expo Line Phase 2, every discipline lead for design and construction, and a full-time quality assurance manager, were co-located in one project office, meeting weekly, performing interdisciplinary design reviews, constructability reviews, and working from a central document control system and central CADD database to facilitate communication and coordination.

“Most of the design was critical path, so delivering on the design schedule was crucial for the overall success of the project,” says Brett E. Jones, P.E., VP, Parsons Brinckerhoff. “We broke the design into 26 packages that were sequenced according to the approval and construction processes. Authority and Metro were involved early, providing feedback on the trains, operations, and the location and geometry of the turnouts and providing early approval on design deviations. Our design teams completed 90 percent of the design within the first 15 months, which facilitated the construction schedule.”

Collaboration key, resolve challenges
Skanska Project Executive Brian Freund says, “Collaboration between the owner, designer and construction team from the very beginning was a key to success. Decisions made early in the process about proper phasing of project elements could not be made in a vacuum and they had to be handled quickly in order to keep to schedule.”

Discipline leads collaborated in the field to quickly resolve design-build challenges and save project dollars; for example, determining that a mile-long, 10-foot-diameter arched brick storm water pipe 20 feet under Colorado Avenue in Santa Monica would support the LRT load and could be left in place with offset manholes.

The Expo Line was designed as a multimodal transit parkway with parking facilities, bike facilities and transit connections. Stations are generally located at major north/south arterials for increased access and mobility. Station parking is provided at some locations, and all stations feature bike facilities, including bike racks and lockers. Local public transit providers conducted studies to determine how to best serve the new stations.

Ad Loading...

Landscaping is primarily comprised of native, drought-tolerant plants. The stations feature signature palm and ginko trees, which line the corridor.


Community, stakeholder involvement
Community involvement in station design, native landscaping and public art was an important component of the project. The Expo Authority appointed an urban design committee comprised of members representing communities and stakeholders along the entire Expo alignment to provide input into design, landscaping and art; and a community-stakeholder bikeway advisory committee provided input on the bikeway project built in conjunction with and adjacent to the Phase 2 project.

Metro’s public art program dedicates 0.5% of rail construction project costs to creating original artwork at each station. Of nearly 400 artists who submitted qualifications for consideration for the Expo Phase 2 stations, eight were selected by stakeholders and the community to provide artworks.

Landscaping is primarily comprised of native, drought-tolerant plants. The stations feature signature palm trees and ginkgo trees, which line the corridor, tying into the landscaping on Phase 1.

Community-wide outreach for the project kept the community in the loop with quarterly construction update meetings; presentations to neighborhood councils, homeowner associations, block clubs, business associations and school groups; information tables at community events; and construction notices distributed in affected areas prior to the start of new construction and fieldwork activities.

Construction is slated for substantial completion in late September, when the line will be turned over to Metro for pre-revenue testing. It is anticipated that Expo 2 will be open to the public by early 2016.

Ad Loading...

The Expo Line is a key component of a regional plan to provide cost-effective, environmentally friendly mass transit options and increase mobility in southern California. By providing an efficient alternative to driving for Angelenos and visitors, the Expo Line also will contribute to reduced levels of air pollutants and greenhouse gases, improving the overall quality of life in this region.

Bruce Ross, founder of New York City-based Bruce Ross Associates Inc., writes frequently about transit.

Subscribe to Our Newsletter

More Rail

Coastal railroad tracks run between a steep bluff and the Pacific Ocean in San Clemente, California, with rock barriers protecting portions of the shoreline.
Rail•by Elora Haynes•October 1, 2026

OCTA Declares Emergency to Protect Rail Corridor From Coastal Erosion

The California agency is accelerating shoreline protection and plans to place approximately 690,000 cubic yards of sand along the San Clemente coast to protect a key passenger and freight rail link.

Read More →
DRPA interns with program swag.
Management•by Alex Roman•October 1, 2026

More Than a Summer Job: Building the Next Generation of Transit Talent

The Delaware River Port Authority and PATCO have transformed their internship program into a hands-on professional development experience that introduces students to the breadth of transportation careers — and creates a pipeline for future employees.

Read More →
An Amtrak Airo trainset on the Cascades line
Rail•by Alex Roman•September 30, 2026

Airo Trains Make Their Amtrak Cascades Debut in the Pacific Northwest

Effective immediately, two cutting-edge Airo trainsets will join the Amtrak Cascades route, operating four daily trips between Vancouver, B.C., Seattle, Portland, and Eugene, Oregon, marking the first introduction of Airo trains into passenger service anywhere in the country.

Read More →
Ad Loading...
Rail•by Alex Roman•September 29, 2026

Florida's Brightline Announces Financial Restructuring

Brightline Florida says train operations will continue as normal as certain parent entities enter Chapter 11 and financial stakeholders provide $490 million in new long-term capital.

Read More →
Bus manufacturing image from ENC
Technology•by Alex Roman•September 25, 2026

ENC Lands MATA Contract and More in Biz Briefs

In this edition of Biz Briefs, we spotlight the latest developments shaping the future of mobility.

Read More →
Turning transit data into better decisions
Management•by Alex Roman•September 23, 2026

Strada360’s Steve Lassey on Turning Transit Data Into Better Decisions

From breaking down data silos to preparing for AI, Strada360 CEO Steve Lassey discusses how transit agencies can use technology to improve operations, customer information, and long-term decision-making.

Read More →
Ad Loading...
SEPTA Accelerate press conference
Management•by Staff and News Reports•September 23, 2026

SEPTA Details Accelerate Vision for Transit System

The plan outlines investments in trolley modernization, new Metro and Regional Rail vehicles, accessible stations, and more frequent bus and rail service.

Read More →
Two MBTA railcars in station.

FTA Ends Direct Oversight of MBTA Safety Actions

The federal agency closed its remaining special directive to the Massachusetts Department of Public Utilities following a safety review that began in 2022.

Read More →
A photo of an Amtrak train with a logo
Rail•by Staff and News Reports•September 17, 2026

Amtrak, CN Reach Agreements to Strengthen Passenger Rail Service, Safety

The agreement resolves a more than decade-long proceeding before the Surface Transportation Board concerning the terms and conditions for Amtrak services, such as the City of New Orleans, Illini/Saluki, and Wolverine.

Read More →
Ad Loading...
A New York MTA subway car with an open gangway
Rail•by Staff and News Reports•September 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →