Gillig launches new 600K-square-foot facility in Livermore, Calif.
The move from nearby Hayward, Calif., took three years of meticulous planning and was completed losing less than two days of production, with each employee receiving an individualized move plan.

Gillig's longest-tenured employee did the ribbon cutting honors.

Gillig's longest-tenured employee did the ribbon cutting honors.
On Friday, Gillig LLC launched its new manufacturing plant in Livermore, Calif., with a ribbon cutting ceremony that included several local dignitaries.
During the ceremony, Derrick Maunus, president of Gillig, said the three-year transition overcame several hurdles, including the wettest winter in the region’s history, before calling it a great day for America and American manufacturing.
While surrounded by both current and former Gillig employees, Maunus credited them for the company’s long-term success.

Gillig's new facility.
"These 900 men and women have made the company successful,” said Maunus, adding that the move to Livermore from nearby Hayward keeps stable, skilled jobs in the U.S., setting the company apart from other companies who have chosen to leave the state or country to take advantage of cheaper labor.
In Livermore, Gillig built a 600,000-square-foot main facility, as well as a 50,000-square-foot building used for fabrication and assembly and a 27,000 square-foot facility to prepare the buses for delivery. The move, which took three years of meticulous planning, was completed losing less than two days of production, with each employee receiving an individualized move plan.

Gillig's first electric bus, which is currently in operation by the County Connection, formerly CCCTA.
In addition, VP, Sales and Marketing, Joe Policarpio said about 95% of employees stayed on with the company after the move, with the large influx of employees in the area having a minimal impact on traffic, due to the company’s hours of operations.
Policarpio added that Gillig plans on being able to ramp up production in the near future, as well as continuing to develop an electric bus, with the first having recently been delivered to Concord, Calif.’s The County Connection.
More Management

METRO Opens Submissions for 2026 Motorcoach Awards
Nominations are now being accepted for METRO Magazine’s Operator of the Year and Innovative Operator of the Year awards.
Read More →
New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Read More →
Transit Agencies Highlight Safety Gains at National Summit
Leaders from 15 major transit systems shared crime-reduction results and safety initiatives while discussing the role of continued federal support.
Read More →
NITA Names New Leadership, Expands Reduced-Fare Program at First Board Meeting
The new regional transit authority appointed its first board chair and interim executive director while extending reduced fares across CTA, Metra, and Pace for eligible riders.
Read More →
Beyond the Checklist: A Structured Approach to Transit Maintenance
Reliability-Centered Maintenance helps transit agencies move beyond routine checklists to focus limited resources on the assets and failures that have the greatest impact on safety, reliability, and service.
Read More →
APTA 2026 Nominating Committee Selects Leadership Slate, Names Chair and Vice Chair Nominees
Leadership changes will help shape the association’s priorities and its representation of the transportation industry during the 2026–2027 term.
Read More →
DART Launches Major Security, Fare Enforcement Initiative
The 90-day demonstration will deploy coordinated security teams at five light rail stations while testing controlled access and gathering data to guide future investments.
Read More →Advancing Fare Collection Through Technology and Innovation
Learn about delivering 1300 gates at 91 stations while managing fare evasion. Explore the large scale deployment, solution customization and real-world results that affect the region. Prepare for deployment in your region now.
Read More →
Game Day in Motion: Moving Millions During the 2026 World Cup
Between packed transit stations and team motorcoaches, see how agencies and operators across North America tackled the transportation demands of the 2026 FIFA World Cup.
Read More →
Surface Transportation Extension Averts Shutdown, Leaves Transit Funding Gap
The stopgap keeps federal transportation programs moving, but missing advance funding could complicate the transit and rail projects agencies are planning next.
Read More →