Sound Transit 1 Line Returns to Service
Crews began working on Jan. 13 on several projects to improve service for riders.

During the service interruption, work crews replaced 500 feet of northbound track between University Street and Westlake at the sharpest curve in the entire Link system.
Photo: Sound Transit
Sound Transit announced that the 1 Line returned to normal operations on Feb. 5 as platform work in the downtown tunnel wraps up on schedule.
Crews began working on Jan. 13 on several projects to improve service for riders.
During this period, trains ran on a single track approximately every 26-30 minutes between UW and Stadium stations on weekdays, while shuttle buses between Capitol Hill and SODO stations replaced light rail service on weekends.
“I want to thank all of our passengers for their patience during this extended maintenance interruption,” said Sound Transit Deputy CEO Russ Arnold. “We know that this hasn’t been easy for them, but the end result is a smoother ride and a more reliable system.”
What Sound Transit Worked on During Service Interruption
During the service interruption, work crews replaced 500 feet of northbound track between University Street and Westlake at the sharpest curve in the entire Link system. These rails were worn and made for a bumpy ride for passengers for years. Without replacement, the worn rails would eventually have become a safety hazard, according to the agency.
Crews also replaced 58 “bond boxes,” which provide signal connections to the tracks. These bond boxes were progressively damaged by buses between 2009 and 2019, leading to occasional signal failures and train delays.
In addition to the two major projects, the agency took advantage of the service disruption to do five other projects as well, including repairing some sections of southbound rail and cleaning artwork. Scheduling these projects during this period meant that the work could be completed sooner than originally planned.
More Rail

New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Read More →
San Diego MTS Breaks Monthly Trolley Ridership Record
Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.
Read More →
Report Examines NJ TRANSIT Reliability, Funding Challenges
The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.
Read More →
Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement
Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.
Read More →
Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More
In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.
Read More →
CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips
With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.
Read More →
Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations
Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.
Read More →
Amtrak Begins Major Construction at New York’s Sunnyside Yard
The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.
Read More →
Chicago Leaders Unveil Plans for O’Hare Airport Express Train
The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.
Read More →
OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor
The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.
Read More →