Amtrak, NJ TRANSIT Highlight Recent Infrastructure, Reliability Improvements

After issuing a report in August, which included details of joint efforts and progress to date, Amtrak and NJ TRANSIT released a new progress report today and discussed the recently-awarded grants for nearly $300 million in federal funding to modernize critical rail infrastructure in New Jersey.

November 21, 2024
Amtrak logo

The execution of the joint action plan followed several major service disruptions in May and June, together with a variety of smaller incidents that reduced service reliability on the NEC between Trenton and New York City. 

Photo: Amtrak

4 min to read


Amtrak and NJ TRANSIT joined Gov. Phil Murphy to share the positive progress on their joint inspection, maintenance, and improvement program for Amtrak’s Northeast Corridor (NEC) infrastructure and NJ TRANSIT’s trains, which has increased the service reliability for customers on the NEC over the last several months.

The meeting follows a June 27 convening led by Gov. Murphy to determine a joint action plan designed to address several major service disruptions that occurred throughout the summer. 

Ad Loading...

After issuing a report in August, which included details of joint efforts and progress to date, Amtrak and NJ TRANSIT released a new progress report today and discussed the recently-awarded grants for nearly $300 million in federal funding to modernize critical rail infrastructure in New Jersey.

“While we are pleased with the progress that has improved reliability for tens of thousands of NJ TRANSIT rail customers, our joint efforts will continue,” said NJ TRANSIT President/CEO Kevin S. Corbett. “It’s essential that we sustain the same level of attention we have demonstrated over the past five months. In addition to the work we are doing to add fiberglass protectors on our pantographs to protect them from impact damage on the NEC catenary, NJ TRANSIT will continue to support Amtrak’s efforts to accelerate the work to upgrade the most vulnerable infrastructure along the NEC.”

Recent for the Joint Action

The execution of the joint action plan followed several major service disruptions in May and June, together with a variety of smaller incidents that reduced service reliability on the NEC between Trenton and New York City. 

Following June’s public meeting with Gov. Murphy, Amtrak, and NJ TRANSIT outlined immediate actions, investigations, inspections, and repairs that both companies undertook together to address these issues. 

The comprehensive actions taken since June have greatly contributed to a noticeable decline in similar occurrences over the past several months and service quality has returned to typical levels.

Ad Loading...

Improvements Made

Over the course of the past five months, Amtrak and NJ TRANSIT made the following improvements executing on their joint plan:

  • Amtrak performed 240 Track Miles of catenary system inspection on the Northeast Corridor between Trenton and NYC and renewed approximately 2,000 hardware components within the area.

  • Amtrak conducted helicopter inspections of the entire NEC overhead catenary system between Trenton and the North River Tunnel, right outside New York Penn Station and made 839 hardware replacements from the defects identified from the 2,000-plus catenary structures captured from the photographs taken during the inspections.

  • Amtrak performed photo inspections via special hi-rail vehicle of tunnels and tracks within New York Penn Station.

  • Amtrak identified and remediated electric traction components and replaced overhead wire to ensure reliability.

  • NJ TRANSIT and Amtrak increased equipment inspections and used high-definition video on top of locomotives to document the interaction of NJ TRANSIT equipment with Amtrak wires.

  • NJ TRANSIT also completed visual and hands-on inspections of approximately 82 route-miles of overhead catenary system on its territory.

Additional Improvements

In addition to the above improvements, Amtrak recently received nearly $300 million in grants applied for with NJ TRANSIT support and matching funds, from the FRA for several projects that will modernize the area’s infrastructure. 

This includes funds to advance further planning, development, or construction activities as follows:

  • The Amtrak Sawtooth Bridges Replacement Project obtained $187.5 million for final design and preconstruction services, which includes updated track, signals, catenary, and other infrastructure in that 2.5-mile territory for the replacement of the 115-year-old NEC bridges in Kearny.

  • The Amtrak Substation 41 Renewal Project, which will replace and protect from the potential of flooding, a key point on Amtrak’s NEC electric traction system, received $80.2 million to construct a new substation in Kearny.

  • Amtrak signal system upgrades between New Brunswick and Elizabeth received $18.6 million for project development and design of modernizing the existing signal system along 26 miles of the NEC for increased train throughput and improved speeds.

  • Amtrak NEC catenary upgrades from New Brunswick to Newark secured $13.4 million to fund the completion of the design and environmental review of the project, which will result in the replacement of the almost 90-year-old catenary structures along 23 miles.

More Rail

Railby StaffFebruary 2, 2026

Chicago Region Transit Ridership Grows in 2025

The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.

Read More →
Managementby StaffJanuary 29, 2026

Valley Metro Sees Strong Ridership Growth in 2025

The agency ranked top five among mid-sized U.S. transit systems, defined as agencies with 15 million to 50 million annual trips.

Read More →
Busby StaffJanuary 29, 2026

Subway Customer Satisfaction Reaches Record High, New York MTA Says

The subway system saw increases across all key metrics, with 62% of subway riders reporting they feel satisfied with the system overall.

Read More →
Ad Loading...
Managementby StaffJanuary 27, 2026

Keolis Retains Virginia Railway Express Contract

The new contract for Keolis and VRE will commence in July 2026, with the potential to expand to 15 years.

Read More →
Busby StaffJanuary 27, 2026

California's OCTA Advances 2026 Initiatives Centered on Balance and Sustainability

The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.

Read More →
Railby Staff and News ReportsJanuary 26, 2026

People Movement: Virginia's DRPT Names New Director and More

In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
Ad Loading...
ManagementJanuary 23, 2026

Seattle Sound Transit Sets Launch Date for Crosslake Connection

This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.

Read More →
A blue and white graphic with a map of the proposed study area for the Sepulveda Transit Corridor and text reading "LA Metro Approves Underground Rail for Sepulveda Transit Corridor."
RailJanuary 23, 2026

LA Metro Approves Underground Rail for Sepulveda Transit Corridor

The agency’s selection aims to slash travel times from the San Fernando Valley to the Westside to under 20 minutes.

Read More →
TechnologyJanuary 21, 2026

Florida's Tri-Rail Taps Siemens Mobility for Modern Locomotive Procurement

Expected to enter service in 2029, these locomotives support the agency’s commitment to offer reliable and efficient rail transportation across South Florida.

Read More →
Ad Loading...
Rendering of an Austin Light Rail station.
RailJanuary 20, 2026

Austin Transit Partnership Advances Federal Funding Process for Light Rail Project

See how the agency’s transit project completed a Final Environmental Impact Statement within the federal two-year guideline.

Read More →