Amtrak, NJ TRANSIT Highlight Recent Infrastructure, Reliability Improvements

After issuing a report in August, which included details of joint efforts and progress to date, Amtrak and NJ TRANSIT released a new progress report today and discussed the recently-awarded grants for nearly $300 million in federal funding to modernize critical rail infrastructure in New Jersey.

November 21, 2024
Amtrak logo

The execution of the joint action plan followed several major service disruptions in May and June, together with a variety of smaller incidents that reduced service reliability on the NEC between Trenton and New York City. 

Photo: Amtrak

4 min to read


Amtrak and NJ TRANSIT joined Gov. Phil Murphy to share the positive progress on their joint inspection, maintenance, and improvement program for Amtrak’s Northeast Corridor (NEC) infrastructure and NJ TRANSIT’s trains, which has increased the service reliability for customers on the NEC over the last several months.

The meeting follows a June 27 convening led by Gov. Murphy to determine a joint action plan designed to address several major service disruptions that occurred throughout the summer. 

Ad Loading...

After issuing a report in August, which included details of joint efforts and progress to date, Amtrak and NJ TRANSIT released a new progress report today and discussed the recently-awarded grants for nearly $300 million in federal funding to modernize critical rail infrastructure in New Jersey.

“While we are pleased with the progress that has improved reliability for tens of thousands of NJ TRANSIT rail customers, our joint efforts will continue,” said NJ TRANSIT President/CEO Kevin S. Corbett. “It’s essential that we sustain the same level of attention we have demonstrated over the past five months. In addition to the work we are doing to add fiberglass protectors on our pantographs to protect them from impact damage on the NEC catenary, NJ TRANSIT will continue to support Amtrak’s efforts to accelerate the work to upgrade the most vulnerable infrastructure along the NEC.”

Recent for the Joint Action

The execution of the joint action plan followed several major service disruptions in May and June, together with a variety of smaller incidents that reduced service reliability on the NEC between Trenton and New York City. 

Following June’s public meeting with Gov. Murphy, Amtrak, and NJ TRANSIT outlined immediate actions, investigations, inspections, and repairs that both companies undertook together to address these issues. 

The comprehensive actions taken since June have greatly contributed to a noticeable decline in similar occurrences over the past several months and service quality has returned to typical levels.

Ad Loading...

Improvements Made

Over the course of the past five months, Amtrak and NJ TRANSIT made the following improvements executing on their joint plan:

  • Amtrak performed 240 Track Miles of catenary system inspection on the Northeast Corridor between Trenton and NYC and renewed approximately 2,000 hardware components within the area.

  • Amtrak conducted helicopter inspections of the entire NEC overhead catenary system between Trenton and the North River Tunnel, right outside New York Penn Station and made 839 hardware replacements from the defects identified from the 2,000-plus catenary structures captured from the photographs taken during the inspections.

  • Amtrak performed photo inspections via special hi-rail vehicle of tunnels and tracks within New York Penn Station.

  • Amtrak identified and remediated electric traction components and replaced overhead wire to ensure reliability.

  • NJ TRANSIT and Amtrak increased equipment inspections and used high-definition video on top of locomotives to document the interaction of NJ TRANSIT equipment with Amtrak wires.

  • NJ TRANSIT also completed visual and hands-on inspections of approximately 82 route-miles of overhead catenary system on its territory.

Additional Improvements

In addition to the above improvements, Amtrak recently received nearly $300 million in grants applied for with NJ TRANSIT support and matching funds, from the FRA for several projects that will modernize the area’s infrastructure. 

This includes funds to advance further planning, development, or construction activities as follows:

  • The Amtrak Sawtooth Bridges Replacement Project obtained $187.5 million for final design and preconstruction services, which includes updated track, signals, catenary, and other infrastructure in that 2.5-mile territory for the replacement of the 115-year-old NEC bridges in Kearny.

  • The Amtrak Substation 41 Renewal Project, which will replace and protect from the potential of flooding, a key point on Amtrak’s NEC electric traction system, received $80.2 million to construct a new substation in Kearny.

  • Amtrak signal system upgrades between New Brunswick and Elizabeth received $18.6 million for project development and design of modernizing the existing signal system along 26 miles of the NEC for increased train throughput and improved speeds.

  • Amtrak NEC catenary upgrades from New Brunswick to Newark secured $13.4 million to fund the completion of the design and environmental review of the project, which will result in the replacement of the almost 90-year-old catenary structures along 23 miles.

More Rail

Graphic from Amtrak promoting the B&P Tunnel Replacement and Frederick Douglass Tunnel project, featuring the Amtrak logo, project title and an illustration of a high-speed train near the West Baltimore MARC Station.
Railby News/Media ReleaseMarch 17, 2026

Amtrak Announces Community Grants for Projects Near Baltimore’s New Frederick Douglass Tunnel

Amtrak will open grant applications March 23 for community projects near the Frederick Douglass Tunnel alignment in Baltimore as part of a $50 million investment tied to the B&P Tunnel Replacement Program.

Read More →
Amtrak train with logo
Railby StaffMarch 16, 2026

Amtrak Marks Restoration of Two South Carolina Stations

The Denmark Station $2.3 million construction investment project includes a new 280-foot concrete boarding platform, built eight inches above the top of rail, for improved accessibility for passengers with disabilities and families with small children and much more.

Read More →
A view looking down the rail across the new Portal North Bridge.
Railby Staff and News ReportsMarch 13, 2026

NJ Transit, Amtrak Prepare to Open First Track on New Portal North Bridge

The new bridge will begin carrying passenger trains on March 16, replacing a 116-year-old swing bridge that has long caused delays.

Read More →
Ad Loading...
Caltrain trains on tracks
Railby StaffMarch 6, 2026

Caltrain Adopts Corridor-Wide Right-of-Way Safety Strategy

Caltrain and its partners have implemented safety improvements at specific locations in response to known risk conditions, operational needs, and available funding since the agency’s founding.

Read More →
A photo of rail tracks in Ottawa, Canada

Building a National Framework for Transit Safety and Consistency

On a recent episode of METROspectives, METRO Magazine’s Executive Editor Alex Roman sat down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the CSA Group, to explore a bold initiative aimed at addressing those challenges: the development of a National Code for Transit and Passenger Rail Systems in Canada.

Read More →
Stairs in a New York rail station with text reading "USDOT Invests $686 Million to Modernize Aging Rail Stations."
Railby StaffMarch 2, 2026

FTA Invests $686M to Modernize Aging Rail Stations

Competitive FTA grants will support accessibility upgrades, family-friendly improvements, and cost-efficient capital projects at some of the nation’s oldest and busiest transit hubs.

Read More →
Ad Loading...
A purple MBTA train at a Mansfield Station platform.
Railby StaffFebruary 27, 2026

MBTA Updates Rail Modernization Plan to Expand Reliability and Accessibility

The strategy outlines near- and long-term upgrades to ease congestion, support housing growth, and advance statewide climate goals.

Read More →
LA Metro underground station with vehicle
Railby StaffFebruary 27, 2026

LA Metro Sets D Line Subway Extension Launch Date

The 3.92-mile addition will soon take riders west beyond its current Wilshire and Western station in Koreatown, continuing under Wilshire Boulevard through neighborhoods and communities including Hancock Park, Windsor Square, the Fairfax District, and Carthay Circle into Beverly Hills.

Read More →
MBTA railcars
Railby StaffFebruary 26, 2026

Boston's MBTA Marks Progress in Regional Rail Modernization

The procurement advances the agency's broader efforts to modernize its rail fleet and position Regional Rail for long-term improvement.

Read More →
Ad Loading...
An Amtrak Acela
Railby StaffFebruary 26, 2026

Amtrak Sets New Course for Long-Distance Fleet Renewal

Under the plan, all long-distance routes will transition to a universal single-level fleet, replacing today’s mix of bi-level and single-level equipment.

Read More →