High-Speed Rail: At a Crossroads

Major corridor programs — such as California High-Speed Rail and the Northeast Corridor — are actively advancing visionary futures for public transportation. Yet, future federal funding for HSR remains clouded in the complexities of the federal appropriations process.

by David J. Carol
September 27, 2017
High-Speed Rail: At a Crossroads

In July 2017, the FRA released the Record of Decision for NEC FUTURE, its planning platform for defining the expansion of the Northeast Corridor over the next 25 to 50 years. Rendering via Amtrak

8 min to read


It is the best of times and . . . perhaps the most unclear of times for high-speed rail (HSR) in the U.S. Major corridor programs — such as California High-Speed Rail and the Northeast Corridor — are actively advancing visionary futures for public transportation. Privately funded projects — All Aboard Florida’s Brightline project and Texas Central’s Houston-Dallas HSR program — have achieved major and exciting milestones. Other programs — from the Chicago-St. Louis HSR program to the Southeast High Speed Rail Corridor to the Hartford Line program in New England— continue to progress.

Yet, future federal funding for HSR remains clouded in the complexities of the federal appropriations process. While states such as California have, and will continue to step in with significant, and often creative, funding initiatives, such as the use of cap-and-trade taxes on greenhouse gas emissions to partially fund the California High-Speed Rail Program, it is the long-term availability of federal funding that ultimately will define the scale and pace of HSR implementation in this country.

Ad Loading...
The California High-Speed Rail project, which will eventually connect San Diego, Los Angeles, San Francisco, and Sacramento, will be implemented in phases. Rendering via CHSRA

For the first time ever, as a direct outcome of the $10 billion investment in HSR made in 2009 and 2010, states across the country have developed and now completed the environmental and planning processes for a myriad of new HSR systems and for expansion of existing ones. The Federal Railroad Administration (FRA) has overseen dozens of environmental and engineering projects that make the nation truly “shovel ready” for passenger rail investment. This includes the California High-Speed Train Project; the Eugene-Portland-Seattle-Vancouver Cascades program; various Midwest corridors connecting to Chicago; the Atlanta, Charlotte, Raleigh, Richmond and Washington Southeast HSR Corridor; the Northeast Corridor; the Boston and Montreal Northern New England Intercity Rail Initiative; the Tucson-Phoenix corridor; Tulsa-Oklahoma City HSR; the Minneapolis-Rochester ZIP Rail project; among other rail corridor initiatives.

With federal funding, these programs could accelerate design and construction, ushering in a new era of transportation in this country. Yet, legislative efforts to define a long-term investment program and to provide a long-term funding vehicle for investment remain stalled in Washington, D.C. Funding for FY 2018, and congressional priorities for that funding, will not be resolved until some time this fall. Until a sustained funding program is implemented, many plans will remain on the shelf. Nonetheless, real progress is being made in a number of major corridors.

For the first time ever, as a direct outcome of the $10 billion investment in HSR made in 2009 and 2010, states across the country have developed and now completed the environmental and planning processes for a myriad of new HSR systems and for expansion of existing ones.

California                                                                                                                 The California High-Speed Rail Program, the largest single rail transportation project in U.S. history, is making significant construction progress as it seeks to implement the first 119-mile segment of world-class HSR infrastructure in the U.S. The project, which will eventually connect San Diego, Los Angeles, San Francisco, and Sacramento, will be implemented in phases, with many related upgrades to the state’s extensive commuter rail system. Work currently is focused in the Central Valley, with the first phase of service linking San Jose to Bakersfield expected around 2025. Some 13 active construction projects are underway, ranging from construction of new rail infrastructure to new bridges and viaducts to convey vehicular traffic over the railroad. Some major recent milestones include:

Completion of the Tuolumne Street Bridge in downtown Fresno, a large structure that carries vehicular traffic over the Union Pacific and future HSR tracks. Beginning in 2015, the project involved placement of 42 massive steel-and-concrete girders, each some 149 feet long and weighing more than 83 tons. The bridge reopened to traffic on Aug. 3, 2017.

Ad Loading...

New spans on the 3,700-foot Cedar Viaduct in Fresno, which will carry high-speed trains over State Route 99, North Avenue, Cedar Avenue, and Golden State Boulevard. Crews are installing reinforcing steel bars in preparation for the next concrete pours. The massive structure is expected to be completed in 2018.
Near completion of the Fresno River Viaduct, a 1,600-foot structure that will carry high-speed trains over the Fresno River and State Route 145 outside of the town of Madera. The viaduct was the first project to start construction.

Northeast Corridor                                                                                                The FRA has achieved two major milestones related to enabling the Washington-New York-Boston corridor to accommodate growing demand for intercity and commuter rail services. In July 2017, the FRA released the Record of Decision for NEC FUTURE, its planning platform for defining the expansion of the Northeast Corridor (NEC) over the next 25 to 50 years. The alternative adopted by the FRA would accommodate as many as five times as many intercity trains on the NEC as operate today, significantly reduce travel time, enable commuter railroads to meet projected growth, and upgrade the NEC to a state of good repair. The program foresees addition of some 200 miles of new track and alignments, replacement of most of the aging bridges across the 465-mile corridor, and elimination of numerous chokepoints that result in delays and restrict operations. The expansion would support a near doubling of ridership across the NEC, as well as transforming the NEC into an integrated network for commuter, regional, and intercity rail services. In all, some $135 billion in investments would be required over a 25- to 50-year period, creating a reliable, fast, and safe rail corridor that for many would be the predominant means of transportation across the region.

In addition to NEC FUTURE, the FRA released the draft Environmental Impact Statement for the Gateway Tunnel Project, the critical effort to build two new tunnels under the Hudson River from New Jersey to Penn Station in Manhattan, and to rehabilitate the existing 115-year-old Hudson River tunnels, heavily damaged in Superstorm Sandy. The current tunnels under the Hudson River, along with aging infrastructure and capacity constraints at Penn Station, represent the single worst bottleneck on the NEC. Expanding service to and from Penn Station is the cornerstone for expanding NEC service and ensuring a vibrant and competitive regional economy. Amtrak, New Jersey Transit, the Port Authority of New York and New Jersey, and the FRA are leading the effort to address this critical deficiency. Future work will focus on expansion of Penn Station to add platforms and tracks and to incorporate new train operations at the Farley Post Office adjacent to Penn Station. Meanwhile, Amtrak has ordered new high-speed trainsets to initially supplement and then replace the existing Acela fleet.

Brightline will serve some of Florida’s most populated cities and tourist destinations with frequent and fast rail service. Rendering via All Aboard Florida/Brightline

Brightline
Brightline is the privately-funded passenger rail initiative to create a new train corridor connecting Miami, Fort Lauderdale, West Palm Beach, and Orlando. Owned by All Aboard Florida, a subsidiary of Florida East Coast Industries, the rail service will be built in two phases — from Miami to West Palm Beach on upgraded existing right-of-way and then to Orlando on new alignment capable of 110 mph operations. Travel time will be approximately three hours end-to-end. Work is currently focused on upgrades between Miami and West Palm Beach, with three major stations and track upgrades under construction, and on trainset acquisition and commissioning. While not the 90-minute HSR service many want for the Miami-Orlando market, Brightline will serve some of Florida’s most populated cities and tourist destinations with frequent and fast rail service. Moreover, it will be the first privately funded U.S. rail corridor program in decades, presenting a new model for rail corridor implementation at a time when public funding for new rail infrastructure is so challenging. Brightline anticipates start-up of its first phase later this year.

Related: Florida's Brightline to Boost Intercity Train Travel

Texas Central HSR
Texas Central is another privately developed passenger rail initiative that could dramatically expand travel options between the state’s two economic powerhouses — Dallas/Fort Worth and Houston. The $12 billion initiative, which will utilize N700 Shinkansen train technology developed and operated by Central Japan Railways, will support 90-minute service between the two cities, with an additional mid-line stop near the state’s largest university, Texas A&M. The project is attracting a myriad of institutional investors and Texas Central Railroad recently awarded a contract for construction of the civil infrastructure. The final environmental impact statement is anticipated later this year.

Ad Loading...

The success of the Texas Central initiative — a HSR corridor serving two large business markets supported by Japanese rail interests and requiring no federal and state funding — may well define the future of HSR in the U.S. Its success will provide a powerful model for implementation of new passenger initiatives in corridors where premium fares from the business travel market can support capital and operating costs without significant public funding.

In July 2017, the FRA released the Record of Decision for NEC FUTURE, its planning platform for defining the expansion of the Northeast Corridor over the next 25 to 50 years. Rendering via Amtrak

In addition to these major initiatives, work continues on other important HSR projects. Between St. Louis and Chicago, completion of track and crossing improvements this year will reduce travel times by as much as an hour. In Connecticut, Hartford Line service connecting New Haven, Hartford, and Springfield, Mass. will begin service in 2018, with some 16 new daily round-trip trains connecting central New England to the NEC. Amtrak’s Downeaster service from Boston has been extended to Brunswick, Maine, including completion of a new maintenance facility in Brunswick. Major improvements are under way between Richmond, Va. and Washington, D.C. to improve travel times and expand the capacity of the rail corridor to support additional frequencies, while the North Carolina Department of Transportation is completing several grade separation and capacity expansion projects to support additional Piedmont and Southeast HSR corridor service. In the Pacific Northwest, the State of Washington recently announced a new initiative, supported by Microsoft and other major companies, to implement HSR for the Portland-Seattle-Vancouver corridor.

The success of these initiatives, and the willingness of state governments to finance improved passenger rail service, underscores the public support for passenger rail and the strong economic and environmental benefits it can provide. Elsewhere in the world —notably France, the UK, Singapore, and China — national governments continue to use HSR investment to achieve broad economic, environmental and social policy objectives. Whether, and to what extent, the U.S. government follows suit is an open question.

David J. Carol serves as deputy project director on the Tel Aviv Red Line light rail project for WSP.

Subscribe to Our Newsletter

More Rail

Operation Lifesaver Rail Safety Education logo over railroad tracks background, representing rail safety awareness initiatives.
Railby News/Media ReleaseMay 4, 2026

Operation Lifesaver Awards Rail Safety Outreach Funds in 12 States

Operation Lifesaver awarded $220,200 in grants to 12 states to support rail safety campaigns focused on grade crossing awareness and trespass prevention.

Read More →
Caltrain trains on tracks
Railby StaffMay 1, 2026

Caltrain Survey Shows Record-High Rider Approval

The survey showed that commute trips still make up the majority of ridership, with most riders boarding 2 to 3 days a week, reflecting hybrid work schedules. Two-thirds of Caltrain riders have access to a car, while 37% of Caltrain riders are considered low-income.

Read More →
A person working on a bus
ManagementMay 1, 2026

Data-Driven Maintenance: Focusing Effort Where It Matters Most

Advances in data and analytics are giving transit agencies new opportunities to refine maintenance practices, improve efficiency and make more informed decisions about asset performance.

Read More →
Ad Loading...
Carmen C. Cham of HNTB
Managementby Alex RomanApril 29, 2026

How Transit Architecture Is Reshaping the Rider Journey

In this Consultant Roundtable, Carmen C. Cham shares insights on how agencies can create spaces that are intuitive, connected and built for long-term impact.

Read More →
A Red Line Rendering
Railby StaffApril 27, 2026

Chicago Kicks Off Historic Red Line Extension at Michigan Avenue Station Site

The Red Line Extension Project will provide the Far South Side of Chicago with rapid rail transit for the first time by extending the Red Line by 5.5 miles from 95th Street to 130th Street, including the construction of four new Red Line stations at 103rd, 111th, Michigan, and 130th streets.

Read More →
Trains at railroad crossings
Security and Safetyby StaffApril 27, 2026

USDOT Invests $1.1B to Enhance Safety Infrastructure at Railroad Crossings

Every year, more than 2,000 incidents and 300 fatalities occur at railroad crossings nationwide. 

Read More →
Ad Loading...
Siemens and LK Comstock photo for Fulton-Liberty Lines
Security and Safetyby StaffApril 27, 2026

NYC’s Fulton–Liberty Lines Get Digital Signal Upgrade from Siemens and L.K. Comstock

The Siemens CBTC System, Trainguard MT, in compliance with New York Subway Interoperability Interface Specifications, enables trains to run as close as 90 seconds apart, using next-generation signaling and continuous communication to keep operations moving seamlessly.

Read More →
WMATA 7000-series railcars at Navy Yard
Managementby StaffApril 24, 2026

WMATA Adopts FY2027 Budget, Boosts Service Without Raising Fares

While recognizing regional economic constraints and continuing to improve service, the budget increases the jurisdictional subsidy to less than 1.8%, significantly below the inflation rate and the 3% regional target, said agency officials.

Read More →
Denver RTD's A Line with passengers
Railby StaffApril 23, 2026

Denver's RTD Celebrates 10th Anniversary of the A Line

With more than 59,400,000 boardings since the service’s debut, the A Line’s utilization surpassed that of all other RTD rail services in 2025, the agency reported.

Read More →
Ad Loading...
Passengers on a public transit vehicle.
Railby StaffApril 21, 2026

Virginia DRPT Releases Draft Six-Year Program for Transit, Rail Investments

The plan outlines funding for transit operations, capital projects, and freight and passenger rail initiatives, as state officials seek public input on priorities shaping mobility and infrastructure across the Commonwealth.

Read More →