METRO Magazine Logo
MenuMENU
SearchSEARCH

The Expertise Behind Constructing the San Diego Mid-Coast Trolley

WSP USA representatives discuss the behind-the-scenes of The Mid-Coast Trolley Project’s completion, the role of a consultant, and the overall benefits of the project itself.

by Louis Prejean
February 3, 2022
The Expertise Behind Constructing the San Diego Mid-Coast Trolley

The UC San Diego Blue Line now provides a one-seat connection from UTC to downtown San Diego, and south to the U.S.-Mexico border.

Photos courtesy WSP USA

5 min to read


The Mid-Coast Trolley Project, an 11-mile light rail extension of the University of California (UC) San Diego Trolley Blue Line, celebrated its official opening in November 2021.

The extension provides a critical new connection for San Diego, extending the light rail line from the Old Town Transit Center north to the University Towne Center (UTC) Transit Center in University City.

Ad Loading...

The UC San Diego Blue Line now provides a one-seat connection from UTC to downtown San Diego, and south to the U.S.-Mexico border.

What Makes This Project Unique

In addition to 11 miles of new double tracks, the project included the design and construction of eight bridge crossings, nearly seven miles of at-grade alignment in or near existing railroad right- of-way, more than four miles of aerial viaduct structures, and nine stations — five at-grade and four aerial.

WSP representatives, including Project Managers Kristin Carlson and Kimberly Jaskot, Area Manager/VP Patti Boekamp, and Sr. Manager Vladimir Kanevskiy discuss just how much went into completing this extension.

“The Mid-Coast project is one of very few major rail transit projects successfully delivered via alternative delivery methods, such as construction manager/general contractor (CM/GC),” say WSP representatives. “The project had numerous technical challenges associated with difficult geologic conditions.”

Ad Loading...

According to WSP, there were challenges of active fault lines; major utility relocations involving local and federal owners such as the U.S. Navy aviation fuel line; and construction along the Los Angeles-San Diego-San Luis Obispo (LOSSAN) rail corridor.

Other challenges included construction on the University of California, (UC) San Diego campus with a student and faculty population of over 35,000 and bringing an electrified transit system in close proximity to major health care facilities with sensitive medical equipment.

The Impact Of COVID-19

The COVID-19 pandemic provided another challenge for The Mid-Coast project.

“The project has been a major boost to the local economy since construction began in the fall of 2016, employing over 5,200 on-site workers,” say WSP representatives. “There were some shortages or extended procurement times associated with certain materials as a result of the COVID-19 pandemic, but these challenges did not effect on-time opening of the project.”

Ad Loading...

The firm managed a safe construction process and was able to provide employment during the pandemic, benefiting the local economy.

Now open for service, the trolley extension will offer alternatives to commuters while also improving public transportation services and further enhancing access to jobs, schools, and hospitals.

The extension provides a critical new connection for San Diego, extending the light rail line from the Old Town Transit Center north to the University Towne Center Transit Center in University City.

Behind the Funding

WSP USA was responsible for environmental, planning, preliminary, and final engineering; New Starts funding advisory services; and design services during construction of the light rail extension operated by the San Diego Metropolitan Transit System.

“The Mid-Coast project is particularly complex and required a wide range of planning and design capability, as well as flexibility, to address the needs of two rail operators and various stakeholders including the City of San Diego, UC San Diego, Caltrans, Veterans Affairs San Diego Healthcare System, and several private property owners,” says WSP representatives.

Ad Loading...

As the designer of record, WSP was charged with advancing the $2.1 billion project from environmental clearance and conceptual engineering through construction, including track and systems design and operations analysis, station design, traffic engineering, civil and utilities design, and structures design.

WSP also provided grant procurement services that led to a $1 billion Federal Transit Administration Full Funding Grant Agreement in 2016, clearing the way for construction to begin. The project was completed on time and on budget.

“WSP played a key role on the project starting as the environmental and preliminary engineering consultant by getting the project environmentally cleared in late 2014 from the San Diego Association of Governments (SANDAG) board of directors and the Federal Transit Administration (FTA), while simultaneously proceeding with advanced preliminary engineering,” WSP representatives say.

This allowed SANDAG to proceed with selection of the CM/GC, bringing the entity early in the final design phase, and allowing for a collaboration between the design team and CM/GC contractor. It also optimizes the design and reduces risk of change orders during construction.

The Importance of a Consultant

Ad Loading...

The Mid-Coast project was the largest program undertaken in the region’s history, according to WSP USA.

WSP brought together and managed a team of sub-consultants, closely coordinating with SANDAG’s team and consultant partners to advance and deliver this project.

The team included TYLin International in partnership with HDR, program management; Jacobs and PGH Wong, construction management; and the Mid-Coast Transit Constructors CM/GC team, a joint venture of Stacy and Witbeck, Herzog, and Skanska.

“The ability to ramp up and down and utilize technical specialists was also critical during construction when responding to Requests for Information and working with the contractor,” says WSP representatives. “WSP and the rest of the consultant team on the project management consultant and construction manager side were key in supporting SANDAG with on time and on budget delivery of the project.”

The firm says it required expertise and resources to deliver over 30,000 pages of the environmental documentation and nearly 7,000 pages of drawings in a short period of time.

Ad Loading...

Mid-Coast Trolley Project Benefits

In addition to the 1,170 new parking spaces at five of the new stations, the Mid-Coast Trolley Project’s benefits have a bigger impact within the community.

“Transportation capacity expansion was needed along the corridor to accommodate existing and future travel demand resulting from the expected growth in population and job opportunities,” says WSP representatives. “Additionally, there was increasing residential development in the university community, considered to be San Diego’s second downtown.”

The Mid-Coast Light Rail Transit (LRT) Extension has connected the densely populated University City community of San Diego with the rest of the LRT system, while also providing direct access to the UC San Diego campus and major medical facilities serving the broader county population, according to WSP USA.

The project also provides a connection with the City’s “Golden Triangle” situated between three freeways, I-5 on the West, I-805 on the West, and SR-52 on the South.

Ad Loading...

“This trolley extension will transform regional transit connectivity and enhance cross-border opportunities,” WSP representatives say. “The main need for the project was to help address the increase in regional growth by providing improved access to growing employment, education, and residential areas.”

Subscribe to Our Newsletter

More Rail

Operation Lifesaver Rail Safety Education logo over railroad tracks background, representing rail safety awareness initiatives.
Railby News/Media ReleaseMay 4, 2026

Operation Lifesaver Awards Rail Safety Outreach Funds in 12 States

Operation Lifesaver awarded $220,200 in grants to 12 states to support rail safety campaigns focused on grade crossing awareness and trespass prevention.

Read More →
Caltrain trains on tracks
Railby StaffMay 1, 2026

Caltrain Survey Shows Record-High Rider Approval

The survey showed that commute trips still make up the majority of ridership, with most riders boarding 2 to 3 days a week, reflecting hybrid work schedules. Two-thirds of Caltrain riders have access to a car, while 37% of Caltrain riders are considered low-income.

Read More →
A person working on a bus
ManagementMay 1, 2026

Data-Driven Maintenance: Focusing Effort Where It Matters Most

Advances in data and analytics are giving transit agencies new opportunities to refine maintenance practices, improve efficiency and make more informed decisions about asset performance.

Read More →
Ad Loading...
Carmen C. Cham of HNTB
Managementby Alex RomanApril 29, 2026

How Transit Architecture Is Reshaping the Rider Journey

In this Consultant Roundtable, Carmen C. Cham shares insights on how agencies can create spaces that are intuitive, connected and built for long-term impact.

Read More →
A Red Line Rendering
Railby StaffApril 27, 2026

Chicago Kicks Off Historic Red Line Extension at Michigan Avenue Station Site

The Red Line Extension Project will provide the Far South Side of Chicago with rapid rail transit for the first time by extending the Red Line by 5.5 miles from 95th Street to 130th Street, including the construction of four new Red Line stations at 103rd, 111th, Michigan, and 130th streets.

Read More →
Trains at railroad crossings
Security and Safetyby StaffApril 27, 2026

USDOT Invests $1.1B to Enhance Safety Infrastructure at Railroad Crossings

Every year, more than 2,000 incidents and 300 fatalities occur at railroad crossings nationwide. 

Read More →
Ad Loading...
Siemens and LK Comstock photo for Fulton-Liberty Lines
Security and Safetyby StaffApril 27, 2026

NYC’s Fulton–Liberty Lines Get Digital Signal Upgrade from Siemens and L.K. Comstock

The Siemens CBTC System, Trainguard MT, in compliance with New York Subway Interoperability Interface Specifications, enables trains to run as close as 90 seconds apart, using next-generation signaling and continuous communication to keep operations moving seamlessly.

Read More →
WMATA 7000-series railcars at Navy Yard
Managementby StaffApril 24, 2026

WMATA Adopts FY2027 Budget, Boosts Service Without Raising Fares

While recognizing regional economic constraints and continuing to improve service, the budget increases the jurisdictional subsidy to less than 1.8%, significantly below the inflation rate and the 3% regional target, said agency officials.

Read More →
Denver RTD's A Line with passengers
Railby StaffApril 23, 2026

Denver's RTD Celebrates 10th Anniversary of the A Line

With more than 59,400,000 boardings since the service’s debut, the A Line’s utilization surpassed that of all other RTD rail services in 2025, the agency reported.

Read More →
Ad Loading...
Passengers on a public transit vehicle.
Railby StaffApril 21, 2026

Virginia DRPT Releases Draft Six-Year Program for Transit, Rail Investments

The plan outlines funding for transit operations, capital projects, and freight and passenger rail initiatives, as state officials seek public input on priorities shaping mobility and infrastructure across the Commonwealth.

Read More →