The Los Angeles County Metropolitan Transportation Authority (Metro) Gold Line Foothill Extension Construction Authority’s (Construction Authority) 11.5-mile Metro Gold Line Foothill Extension light rail project from Pasadena to Azusa is now more than halfway to project completion.
When completed, the nearly $1 billion Measure R project will include six new light rail stations with intermodal parking facilities in the cities of Arcadia, Monrovia, Duarte, Irwindale and Azusa; two dozen new and rebuilt bridge structures; 14 at-grade street crossings; 3.6-miles of relocated freight track within a shared corridor with Burlington Northern Santa Fe Corp. Railway; and a 24-acre, $265 million Operations Campus to house up to 84 light rail vehicles.
“We were the first Measure R rail project to break ground, and we have stayed on schedule and on budget since we began work in 2010,” said Construction Authority CEO Habib F. Balian. “We still have a significant way to go to substantial completion, but the progress already made provides the confidence that we will be able to meet our schedule and deliver this regionally significant project on time and on budget.”
All three design-build project contracts have been awarded for the project: the $18.6 million Gold Line Bridge to Skanska USA; the $486 million Pasadena to Azusa Alignment to Foothill Transit Constructors — a Kiewit-Parsons Joint Venture (FTC); and the $48.7 million Intermodal Parking and Enhancements to Webcor. The Gold Line Bridge was completed on time and on budget in late 2012 and recognized in 2013 with five industry awards for its design and construction.
The largest contract — the $486 million Pasadena to Azusa Alignment — is being designed and built by FTC and is on schedule and on budget. Since work began in early 2012, FTC has utilized nearly 500,000 work hours on the project and has now surpassed 50% completion.
To date, eight at-grade street crossings, 15 bridge structures, 40% of the Operations Campus and 70% of the utility work has been completed. The freight track between San Gabriel Ave. in Azusa and the Glendora city border has been fully realigned to its new position south of the future light rail tracks, more than half of the overhead catenary system foundations have been put in place, and light rail track is starting to be installed. Of the nearly half million work hours completed, none have been lost due to injury.
The Alignment and Parking contracts will be completed in 18 months. The Construction Authority anticipates having the Operations Campus ready for Metro in March 2015 and the remainder of the project turned over to Metro in September 2015 for testing and pre-revenue service. Metro will decide when the project opens for passenger service.
Calif.’s $1B Metro Gold Line more than halfway complete
Finished eight at-grade street crossings, 15 bridge structures, 40% of the Operations Campus and 70% of the utility work. When fully complete, the project will include six new light rail stations with intermodal parking facilities.

More Rail

Operation Lifesaver Awards Rail Safety Outreach Funds in 12 States
Operation Lifesaver awarded $220,200 in grants to 12 states to support rail safety campaigns focused on grade crossing awareness and trespass prevention.
Read More →
Caltrain Survey Shows Record-High Rider Approval
The survey showed that commute trips still make up the majority of ridership, with most riders boarding 2 to 3 days a week, reflecting hybrid work schedules. Two-thirds of Caltrain riders have access to a car, while 37% of Caltrain riders are considered low-income.
Read More →
Data-Driven Maintenance: Focusing Effort Where It Matters Most
Advances in data and analytics are giving transit agencies new opportunities to refine maintenance practices, improve efficiency and make more informed decisions about asset performance.
Read More →
How Transit Architecture Is Reshaping the Rider Journey
In this Consultant Roundtable, Carmen C. Cham shares insights on how agencies can create spaces that are intuitive, connected and built for long-term impact.
Read More →
Chicago Kicks Off Historic Red Line Extension at Michigan Avenue Station Site
The Red Line Extension Project will provide the Far South Side of Chicago with rapid rail transit for the first time by extending the Red Line by 5.5 miles from 95th Street to 130th Street, including the construction of four new Red Line stations at 103rd, 111th, Michigan, and 130th streets.
Read More →
USDOT Invests $1.1B to Enhance Safety Infrastructure at Railroad Crossings
Every year, more than 2,000 incidents and 300 fatalities occur at railroad crossings nationwide.
Read More →
NYC’s Fulton–Liberty Lines Get Digital Signal Upgrade from Siemens and L.K. Comstock
The Siemens CBTC System, Trainguard MT, in compliance with New York Subway Interoperability Interface Specifications, enables trains to run as close as 90 seconds apart, using next-generation signaling and continuous communication to keep operations moving seamlessly.
Read More →
WMATA Adopts FY2027 Budget, Boosts Service Without Raising Fares
While recognizing regional economic constraints and continuing to improve service, the budget increases the jurisdictional subsidy to less than 1.8%, significantly below the inflation rate and the 3% regional target, said agency officials.
Read More →
Denver's RTD Celebrates 10th Anniversary of the A Line
With more than 59,400,000 boardings since the service’s debut, the A Line’s utilization surpassed that of all other RTD rail services in 2025, the agency reported.
Read More →
Virginia DRPT Releases Draft Six-Year Program for Transit, Rail Investments
The plan outlines funding for transit operations, capital projects, and freight and passenger rail initiatives, as state officials seek public input on priorities shaping mobility and infrastructure across the Commonwealth.
Read More →