Caltrain Awards Mountain View Transit Center Construction Contract
The cost of the first phase, referred to as pre-construction services, is $1.49 million. The project is funded by the Santa Clara Valley Transportation Authority Measure B Program and the City of Mountain View.

The contract award by the Caltrain board follows an earlier action to authorize the use of CM/GC for the project, as opposed to conventional design-bid-build project delivery.
Caltrain
The Caltrain board of directors voted to award a Construction Manager/General Contractor (CM/GC) contract for the Mountain View Transit Center Grade Separation and Access Project to Stacy & Witbeck Inc. and Myers & Sons Construction, a joint venture headquartered in Alameda, Calif.
The cost of the first phase, referred to as pre-construction services, is $1.49 million. The project is funded by the Santa Clara Valley Transportation Authority Measure B Program and the City of Mountain View.
The project will improve safety and multimodal access to the transit center and Downtown Mountain View. The project is focused on the Castro Street/Moffett Boulevard/Central Expressway intersection and will close the Castro Street crossing of the railroad tracks. A shared use pathway that allows pedestrians and cyclists to pass under the tracks and Central Expressway will offer safe and easy access to residents and office workers to Mountain View’s vibrant downtown.
The City of Mountain View identified this project as Phase I of the 2017 Transit Master Plan. Determinations will be made this year regarding the architectural design and public art that will be featured, with the Final Design scheduled to be completed in Summer 2024. Construction is expected to begin that summer, with a completion date in late 2026.
Caltrain Project Delivery
The contract award by the Caltrain board follows an earlier action to authorize the use of CM/GC for the project, as opposed to conventional design-bid-build project delivery. There are advantages to the CM/GC delivery which engages the contractor earlier in the project.
The project is Caltrain’s first use of CM/GC project delivery and is a key strategy being deployed by Caltrain’s Design & Construction team in expanding the pallet of project delivery methods being utilized to increased schedule and cost certainty, particularly on large, complex projects.
Creating a grade separation at Castro Street so people and vehicles will no longer be required to cross the tracks will improve safety for pedestrians and bicyclists; reduce train gate down-time and horn noise; reduce conflicts between trains, vehicles, pedestrians, and bicyclists; and improve traffic flow.
More Rail

New York MTA Leverages Zoning Program to Advance Station Accessibility
Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.
Read More →
Virginia's $28.5B Transportation Plan Targets Transit and Rail
Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.
Read More →
DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades
Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.
Read More →
D Line Expansion Fuels Growth Across LA Metro's Rail System
Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.
Read More →
Southern California's Metrolink Debuts Contactless Fare Payment Pilot
Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.
Read More →
California's BART Approves FY27 Budget While Maintaining Service Levels
The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.
Read More →
Penn Station Transformation Advances with Design Unveiling
The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.
Read More →
Second Avenue Subway Phase 2 Advances into Major Construction Stage
New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.
Read More →
The Invisible Infrastructure of Passenger Flow
What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.
Read More →
Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures
The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.
Read More →