METRO Magazine Logo
MenuMENU
SearchSEARCH

Caltrain Awards Mountain View Transit Center Construction Contract

The cost of the first phase, referred to as pre-construction services, is $1.49 million. The project is funded by the Santa Clara Valley Transportation Authority Measure B Program and the City of Mountain View.

Caltrain Awards Mountain View Transit Center Construction Contract

The contract award by the Caltrain board follows an earlier action to authorize the use of CM/GC for the project, as opposed to conventional design-bid-build project delivery.

Credit:

Caltrain

2 min to read


The Caltrain board of directors voted to award a Construction Manager/General Contractor (CM/GC) contract for the Mountain View Transit Center Grade Separation and Access Project to Stacy & Witbeck Inc. and Myers & Sons Construction, a joint venture headquartered in Alameda, Calif.

The cost of the first phase, referred to as pre-construction services, is $1.49 million. The project is funded by the Santa Clara Valley Transportation Authority Measure B Program and the City of Mountain View.

Ad Loading...

The project will improve safety and multimodal access to the transit center and Downtown Mountain View. The project is focused on the Castro Street/Moffett Boulevard/Central Expressway intersection and will close the Castro Street crossing of the railroad tracks. A shared use pathway that allows pedestrians and cyclists to pass under the tracks and Central Expressway will offer safe and easy access to residents and office workers to Mountain View’s vibrant downtown.

The City of Mountain View identified this project as Phase I of the 2017 Transit Master Plan. Determinations will be made this year regarding the architectural design and public art that will be featured, with the Final Design scheduled to be completed in Summer 2024. Construction is expected to begin that summer, with a completion date in late 2026.

Caltrain Project Delivery

The contract award by the Caltrain board follows an earlier action to authorize the use of CM/GC for the project, as opposed to conventional design-bid-build project delivery. There are advantages to the CM/GC delivery which engages the contractor earlier in the project.

The project is Caltrain’s first use of CM/GC project delivery and is a key strategy being deployed by Caltrain’s Design & Construction team in expanding the pallet of project delivery methods being utilized to increased schedule and cost certainty, particularly on large, complex projects.

Creating a grade separation at Castro Street so people and vehicles will no longer be required to cross the tracks will improve safety for pedestrians and bicyclists; reduce train gate down-time and horn noise; reduce conflicts between trains, vehicles, pedestrians, and bicyclists; and improve traffic flow.

More Rail

A CapMetro commuter rail train provided by Stadler
Railby Staff and News ReportsSeptember 11, 2026

Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement

Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.

Read More →
Rendering of an Alstom train in a VIA Rail Station
Technologyby Alex RomanSeptember 10, 2026

Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More

In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.

Read More →
The CATS Gold Line in service with the city skyline in the background.
Railby Staff and News ReportsSeptember 3, 2026

CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips

With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Amtrak Sunnyside Groundbreaking
Railby Staff and News ReportsSeptember 2, 2026

Amtrak Begins Major Construction at New York’s Sunnyside Yard

The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.

Read More →
O'Hare Flyer Rendering
Railby Staff and News ReportsAugust 27, 2026

Chicago Leaders Unveil Plans for O’Hare Airport Express Train

The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.

Read More →
Ad Loading...
An OCTA coastal rail line train.
Railby Staff and News ReportsAugust 27, 2026

OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor

The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.

Read More →
Ray Melleady and industry leaders on Capitol Hill
Managementby Alex RomanAugust 24, 2026

The Business Voice Behind Public Transportation

As chair of APTA’s Business Members Board of Governors, Ray Melleady explains how more than 850 business members are partnering with transit agencies to advance funding, innovation, and industry-wide collaboration.

Read More →
An Amtrak Cascades Airo Trainset at a station.
Railby Alex RomanAugust 14, 2026

FRA Announces $5.3B in Rail Investments, Including $2B for Amtrak

Funding will support grade-crossing improvements, infrastructure upgrades, and new Amtrak equipment in 23 states.

Read More →
Ad Loading...
Finding the Right Balance: Optimizing Transit Maintenance
ManagementAugust 14, 2026

Finding the ‘Happy Medium’: Optimizing Maintenance Without Sacrificing Reliability

The key to maintenance optimization isn’t doing less work—it’s doing the right work at the right time on the right assets.

Read More →