Capital Metro approves PTC contract, freight service expansion

The approved contract allows Modern Railway Systems to complete a portion of the work within 15 months, which will make the agency eligible to apply for a two-year extension to the December 2018 deadline to complete the rest of the system.

August 29, 2017
Capital Metro approves PTC contract, freight service expansion

 

2 min to read


Austin, Texas’ Capital Metro board of directors approved a contract with Modern Railway Systems Inc. to design, build, and commission Positive Train Control (PTC). The board also approved an amendment to Capital Metro’s contract with freight operator WATCO, which would allow the company to utilize a currently dormant Capital Metro-owned segment of track between Elgin and Giddings.

Capital Metro’s commuter rail system is regulated by the Federal Railroad Administration (FRA) which, in response to Congress, mandated that all commuter rail systems install a PTC system by Dec. 31, 2018. PTC systems are designed to prevent derailments or train-to-train collisions, and to ensure trains are not guided onto the wrong track due to a switch being left in the wrong position.

Ad Loading...

The approved contract allows Modern Railway Systems to complete a portion of the work within 15 months, which will make the agency eligible to apply for a two-year extension to the December 2018 PTC deadline to complete the rest of the system.

The board also approved today a contract modification with the agency’s freight operator, WATCO, to expand freight service along a currently dormant 23-mile stretch of Capital Metro’s track between Elgin and Giddings. WATCO will operate and maintain the new segment and provide Capital Metro with a portion of the gross revenue generated, projected to bring the agency $13M over the contract period.

Capital Metro will conduct community outreach to area residents, businesses, and other stakeholders prior to the opening of the line, including providing information to schoolchildren from the Operation Lifesaver national train safety program.

Freight trains are expected to run once a day, with service estimated to start during the first quarter of 2018. The WATCO proposal states that small rocks, known as aggregate, would be the primary product transported. Capital Metro owns 162 miles of railroad track between Llano and Giddings.

More Security and Safety

Houston METRO substation
Security and Safetyby StaffJune 5, 2026

New Public Safety Hub Opens in Downtown Houston

The substation strengthens METRO Police presence in an area where transit activity, pedestrian movement, and visitor flow converge.

Read More →
SamTrans planning for ballot measure
Managementby StaffJune 4, 2026

SamTrans Sets Priorities for Potential Connect Bay Area Revenue

The board-approved framework allocates future funding to maintaining service, rider improvements, equity initiatives, and infrastructure repairs.

Read More →
Riders in MARTA bus station
Security and Safetyby StaffJune 4, 2026

Federal Transit Officials Launch MARTA Safety Probe

FTA has given MARTA 15 days to provide records on crime prevention, fare evasion enforcement, and security funding as part of a broader safety investigation.

Read More →
Ad Loading...
Security and Safetyby StaffJune 1, 2026

Strategic Safety Measures at CATS Lead to Drop in Transit Crime

Under the leadership of the CATS Chief Safety and Security Officer, the organization has marked a pivotal transformation.

Read More →
Managementby StaffJune 1, 2026

Chicago's NITA Act Moves Into Next Phase as Service Improvements Begin

Rider-focused improvements will begin rolling out across the system immediately as CTA, Metra, and Pace increase service this summer in the six-county region.

Read More →
Image of two Los Angeles Metro employees speaking to a person in a wheelchair. Text reads: "Transit Safety Through Care-Based Strategies."
Security and Safetyby Elora HaynesJune 1, 2026

How Transit Agencies Are Evolving Enforcement-Only Models With Care-Based Safety Strategies

Transit agencies are redefining safety with care-based response models. See how leaders are improving trust and operations.

Read More →
Ad Loading...
frontrunner bus image
SponsoredJune 1, 2026

A True Low-Floor Minibus Design Delivers Better Accessibility and Efficiency for Everyone

As transit demands evolve, so should your fleet. Download the whitepaper to see how the Low-Floor Frontrunner Minibus compares to traditional options.

Read More →
A New Flyer 60-foot articulated bus
Busby StaffMay 29, 2026

WMATA Debuts 'Fares Pay for Service' Awareness Campaign

The campaign was highlighted during a media event at the Paul S. Sarbanes Transit Center in Silver Spring, where WMATA’s GM/CEO Randy Clarke joined Metro Transit Police officers, WMATA management team, board members, and staff to expand fare enforcement and customer education efforts on Metro Bus routes throughout the region.

Read More →
HDR's Brian Buchanan
Managementby Alex RomanMay 27, 2026

The Evolving Role of Program Management in Transit Delivery

Brian Buchanan, HDR’s transit program management lead, discusses how agencies can strengthen governance, anticipate risk and deliver large-scale projects more effectively.

Read More →
Ad Loading...
Riders boarding at a Toronto rail station.
Security and Safetyby StaffMay 27, 2026

TTC Enhances Security Efforts With More Checks, Track Intrusion Focus

The actions, and more, are part of the new and enhanced measures outlined in the “Advancing Safety on the TTC: 2026 Focus Areas Plan” report, which is going to the TTC Board on June 3.

Read More →