CTA awards another Red Line contract
The project, which begins in spring 2013, will completely rebuild the 43-year-old Red Line South — including all track, ties, ballast and drainage systems — from Cermak-Chinatown to 95th Street.
The Chicago Transit Board approved the award of a contract for station improvement work related to the Red Line South reconstruction project, one of the largest reconstruction projects in the Chicago Transit Authority’s (CTA) history and a multimillion-dollar investment in both Chicago’s South Side and the backbone of the CTA rail system.
The project, which begins in spring 2013, will completely rebuild the 43-year-old Red Line South — including all track, ties, ballast and drainage systems — from Cermak-Chinatown to 95th Street. The station work will renew and improve the eight stations along the project footprint, including painting and lighting, bus bridge improvements, and new roofs and canopies at some stations.
F. H. Paschen, S.N. Nielsen and Associates LLC submitted the lowest bid for the station work component of the project at $43.875 million.
Paschen met the CTA’s target of 40% Disadvantaged Business Enterprise (DBE) participation by engaging the services of 13 DBE subcontractors.
The total DBE contract dollar amount is just over $17.5 million with 92.2% going to African-American firms, 7.8% to Hispanic firms and six percent to women-owned firms.
Since announcing the project in June, the CTA has worked diligently to make sure DBE subcontractors were aware of the Red Line South project—hosting seven meet-and-greet sessions pairing potential prime contractors with more than 160 companies to ensure that prime contractors engaged with DBE firms that may qualify for and be interested in the work.
The overall estimated budget for the project, including design, construction and additional CTA service, is $425 million. The project is part of more than $1 billion in federal, state and local funds being invested in the Red Line, the system’s busiest.
More Rail

New York MTA Leverages Zoning Program to Advance Station Accessibility
Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.
Read More →
Virginia's $28.5B Transportation Plan Targets Transit and Rail
Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.
Read More →
DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades
Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.
Read More →
D Line Expansion Fuels Growth Across LA Metro's Rail System
Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.
Read More →
Southern California's Metrolink Debuts Contactless Fare Payment Pilot
Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.
Read More →
California's BART Approves FY27 Budget While Maintaining Service Levels
The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.
Read More →
Penn Station Transformation Advances with Design Unveiling
The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.
Read More →
Second Avenue Subway Phase 2 Advances into Major Construction Stage
New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.
Read More →
The Invisible Infrastructure of Passenger Flow
What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.
Read More →
Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures
The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.
Read More →