CTA to Begin Final Stage of North Belmont Red-Purple Reconstruction Project

The final stage will mark the next major milestone for the RPM project, completing the new elevated track structure north of Belmont station and reaching the two-thirds completion point for this section of the project.

CTA to Begin Final Stage of North Belmont Red-Purple Reconstruction Project

The bypass, along with the new Red and Purple line tracks being finished this fall, allow trains to travel more efficiently with fewer delays, and provide CTA with additional capacity to add trains to meet ridership demand.

Photo: Canva

3 min to read


The Chicago Transit Authority (CTA) announced the agency will begin this fall the final major stage of the North Belmont Red-Purple Reconstruction project as part of CTA’s Red and Purple Modernization (RPM) Phase One Project.

The final stage will mark the next major milestone for the RPM project, completing the new elevated track structure north of Belmont station and reaching the two-thirds completion point for this section of the project.

Ad Loading...

The North Belmont Red-Purple Reconstruction project includes two major components: the new Red-Purple Bypass, which opened in November 2021, and the full reconstruction of the 0.3 miles of southbound track structure north of Belmont station to approximately Newport/Cornelia avenues south of Addison Red Line station.

The bypass, along with the new Red and Purple line tracks being finished this fall, allow trains to travel more efficiently with fewer delays, and provide CTA with additional capacity to add trains to meet ridership demand.

“As CTA ridership returns in record numbers nearing pre-pandemic levels, we are pleased to deliver modern track infrastructure to our customers,” said CTA President Dorval R. Carter, Jr. “Combined with the new tracks recently opened between Lawrence and Bryn Mawr earlier this year, we have now built nearly two miles of new tracks under the RPM project. We look forward to continuing to deliver on our promises to modernize the Red Line from north to south.”

Final Major Stage of North Belmont Red-Purple Reconstruction

With the completion of the bypass and the new southbound Red and Purple line tracks, CTA can move on to the next phase of work.

CTA’s RPM project contractor, Walsh-Fluor, will rebuild 0.3 miles of northbound Red and Purple Line elevated track structures between Belmont station on the south to the stretch of track between Newport and Cornelia avenues on the north.

Ad Loading...

Reconstruction of southbound tracks began in late 2021 and will be completed in late 2023.

Reconstruction of northbound tracks will start in late 2023 and is expected to be completed in 2025.

Minor Rail Service Impacts Expected in Fall 2023

Red, Purple, and Brown Line service will be maintained through the end of the project in 2025, with minor interruptions at the time of the new tracks being put into service this fall.

During the weekends when rail service is interrupted, CTA will provide free shuttle buses between stations for customers.

Upcoming scheduled service* interruptions:

Ad Loading...
  • Brown Line: Belmont to Southport interrupted Oct. 14-16

  • Red and Purple Line: Belmont to Addison interrupted Oct. 27-30 and Nov. 10-13

Community Meeting: North Belmont Red-Purple Reconstruction

CTA and Walsh-Fluor hold an in-person public meeting which will also be recorded and posted on the agency's website.

RPM Phase One Overview

RPM Phase One Project includes three major components:

  • Reconstruction of the Lawrence, Argyle, Berwyn, and Bryn Mawr Red Line stations into larger, 100% accessible stations; and replacement of track structure totaling six track miles (ongoing)

  • New Red-Purple Bypass construction (completed in 2021) and the reconstruction of the Red and Purple Line track structure between Belmont and Newport/Cornelia (ongoing)

  • Installation of a new signal system on 23 track miles between Howard and Belmont that, similar to roadway traffic signals, will improve train flow and service reliability (ongoing)

More Rail

MTA Advances Accessibility Improvements in Brooklyn
Paratransitby StaffJune 17, 2026

New York MTA Leverages Zoning Program to Advance Station Accessibility

Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.

Read More →
Six-Year Plan Boosts Virginia Transit, Rail Investments
Managementby StaffJune 17, 2026

Virginia's $28.5B Transportation Plan Targets Transit and Rail

Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.

Read More →
Security and Safetyby StaffJune 16, 2026

DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades

Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.

Read More →
Ad Loading...
An LA Metro D Line train in Union Station
Managementby StaffJune 16, 2026

D Line Expansion Fuels Growth Across LA Metro's Rail System

Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.

Read More →
A user demonstrating Metrolink's contactless fare payment pilot.
Technologyby StaffJune 12, 2026

Southern California's Metrolink Debuts Contactless Fare Payment Pilot

Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.

Read More →
A BART train on the tracks.
Managementby StaffJune 12, 2026

California's BART Approves FY27 Budget While Maintaining Service Levels

The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.

Read More →
Ad Loading...
A rendering of the Amtrak New York Penn Station renovation
Railby StaffJune 9, 2026

Penn Station Transformation Advances with Design Unveiling

The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.

Read More →
Groundbreaking event for Second Avenue Subway Phase 2 TBM construction.
Railby StaffJune 9, 2026

Second Avenue Subway Phase 2 Advances into Major Construction Stage

New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.

Read More →
A man sits in a passenger rail seat and looks at his phone.
Railby Elora HaynesJune 8, 2026

The Invisible Infrastructure of Passenger Flow

What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.

Read More →
Ad Loading...
Aerial view of Caltrain's electric service.
Railby StaffJune 5, 2026

Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures

The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.

Read More →