Denver RTD to open FasTracks line early

Currently 93% complete, the West Rail line is slated for April 26, 2013, eight months ahead of the originally scheduled opening date. It is the first FasTracks project to be completed.

May 23, 2012
2 min to read


Denver’s Regional Transportation District (RTD) will open the FasTracks West Rail Line to the public on April 26, 2013, eight months ahead of the originally scheduled opening date.

The West Rail Line is the first FasTracks project to be completed and part of the current $4.2 billion investment in the region. Presently, 50 miles of new rail line are in construction or under contract to begin construction.

“The way we managed our first major FasTracks project is indicative of our success in managing projects in the past and what we anticipate for the future,” said Phil Washington, GM, RTD. “But, this doesn’t happen without teamwork between RTD and our partners, namely the Federal Transit Administration and all of our regional stakeholders.”

The new light rail line will travel for 12.1 miles from Denver Union Station and head west through parts of Denver, Lakewood and terminate in the foothills at the Jefferson County Government Center in Golden. The line will serve an estimated 19,300 riders per weekday and will run every five minutes along most of the line during peak hours.

Currently, the West Rail Line is 93% complete. Major construction of the light rail line will be finalized later this summer, followed by completion of the signals and communications system in late 2012. Construction on the Wadsworth and Sheridan parking structures will continue through early March 2013, and RTD light rail operations will conduct final testing and operator training through the spring of 2013.

Final construction of the $707 million project will include 5,600 parking spaces and 12 new stations.

Events leading up to the opening of the West Rail Line include the Sheridan park-n-Ride groundbreaking on June 29 and a bike event this fall in which community members will be able to ride the newly constructed bike path along various locations of the line. Construction on the parking garage at Wadsworth and 13th Avenue began last month.

RTD’s FasTracks transit expansion program will build 122 miles of commuter rail and light rail, 18 miles of bus rapid transit service, add 21,000 new parking spaces, redevelop Denver Union Station and redirect bus service to better connect the eight-county District.

More Rail

A photo of an Amtrak train with a logo
Railby Staff and News ReportsSeptember 17, 2026

Amtrak, CN Reach Agreements to Strengthen Passenger Rail Service, Safety

The agreement resolves a more than decade-long proceeding before the Surface Transportation Board concerning the terms and conditions for Amtrak services, such as the City of New Orleans, Illini/Saluki, and Wolverine.

Read More →
A New York MTA subway car with an open gangway
Railby Staff and News ReportsSeptember 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →
A San Diego MTS Copper Line vehicle
Railby Staff and News ReportsSeptember 15, 2026

San Diego MTS Breaks Monthly Trolley Ridership Record

Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.

Read More →
Ad Loading...
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Railby Alex RomanSeptember 14, 2026

Report Examines NJ TRANSIT Reliability, Funding Challenges

The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.

Read More →
A CapMetro commuter rail train provided by Stadler
Railby Staff and News ReportsSeptember 11, 2026

Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement

Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.

Read More →
Rendering of an Alstom train in a VIA Rail Station
Technologyby Alex RomanSeptember 10, 2026

Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More

In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.

Read More →
Ad Loading...
The CATS Gold Line in service with the city skyline in the background.
Railby Staff and News ReportsSeptember 3, 2026

CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips

With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.

Read More →
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Amtrak Sunnyside Groundbreaking
Railby Staff and News ReportsSeptember 2, 2026

Amtrak Begins Major Construction at New York’s Sunnyside Yard

The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.

Read More →
Ad Loading...
O'Hare Flyer Rendering
Railby Staff and News ReportsAugust 27, 2026

Chicago Leaders Unveil Plans for O’Hare Airport Express Train

The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.

Read More →