Denver's RTD gets Fed approval for next phase of G Line testing
Testing will soon simulate the full daily service schedule of nearly 21 consecutive hours each day.

The authorization given to RTD and its contractor, Denver Transit Partners (DTP), represents another significant step forward in the process to open the commuter rail line for passenger service.
Denver RTD

Denver’s Regional Transportation District (RTD) received approval from the Federal Railroad Administration (FRA) to begin the next phase of testing on the G Line. Beginning late last week, testing is ramping up and will soon simulate the full daily service schedule of nearly 21 consecutive hours each day.
The authorization given to RTD and its contractor, Denver Transit Partners (DTP), represents another significant step forward in the process to open the commuter rail line for passenger service.
Limited testing along the forthcoming 11.2-mile line between Union Station and Wheat Ridge began last fall and has been underway between on weekdays since the start of this year. That process has examined the communication signaling along the line, as well as the effectiveness of the communication technology in place at each of the G Line’s 16 at-grade railroad crossings. The gate-crossing technology is the same as that used along two additional lines originating in downtown Denver: the University of Colorado A Line to Denver International Airport, and the B Line to Westminster.
“We are pleased to have arrived at this phase in the testing schedule, and we continue to appreciate the patience of the public, businesses and leaders in the communities along the G Line as we work through all of the necessary details,” said RTD CEO/GM Dave Genova. An opening date for the G Line has not yet been announced.
As many as three trains will be running on the alignment every day, for an initial period intended to help train operators become familiar with the line. During this time frame, trains will operate every half hour starting as early as 3:30 a.m. and extending through 1 a.m. the following day. With more trains running for longer periods of time throughout the day, the RTD is urging the public to exercise caution as they move and drive through the area.
The official start to the next phase of G Line testing — simulating full passenger service — will follow this initial period. A date for the start of that phase has not been determined.
When the G Line officially opens — which also has yet to be determined — trains will run from 4 a.m. to 12:30 a.m., with 15-minute frequency between 6 a.m. and 6:30 p.m. and every 30 minutes during off-peak hours.
The line is a segment of RTD’s FasTracks program, a voter-approved transit expansion initiative to build new commuter rail and light rail, bus rapid transit service and new parking spaces; redevelop Denver Union Station; and redirect bus service to better connect the eight-county district.
More Rail

New York MTA Leverages Zoning Program to Advance Station Accessibility
Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.
Read More →
Virginia's $28.5B Transportation Plan Targets Transit and Rail
Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.
Read More →
DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades
Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.
Read More →
D Line Expansion Fuels Growth Across LA Metro's Rail System
Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.
Read More →
Southern California's Metrolink Debuts Contactless Fare Payment Pilot
Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.
Read More →
California's BART Approves FY27 Budget While Maintaining Service Levels
The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.
Read More →
Penn Station Transformation Advances with Design Unveiling
The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.
Read More →
Second Avenue Subway Phase 2 Advances into Major Construction Stage
New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.
Read More →
The Invisible Infrastructure of Passenger Flow
What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.
Read More →
Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures
The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.
Read More →