FRA approves MBTA's PTC program extension to 2020
Work to install PTC infrastructure on the MBTA Commuter Rail network is in various stages of completion and testing on each line.

Additional next steps for the MBTA’s PTC Program include testing completion and placement of the remaining South Side Commuter Rail lines in Extended RSD.
Keolis
Boston’s MBTA received federal approval for its alternative schedule and sequence for implementation of its positive train control (PTC) program. The approval, which was granted by the Federal Railroad Administration (FRA), extends the deadline for the full PTC system deployment to December 2020.
Work to install PTC infrastructure on the MBTA Commuter Rail network is in various stages of completion and testing on each line.
The MBTA formally submitted to the FRA its Request for Extension in September 2018 with a revised PTC Implementation Plan submitted to the FRA in November 2018. To formally submit a Request for Extension from the FRA, major work was required to be completed, including the completion of wayside equipment installation (equipment totals include 194 wayside interface units, 181 wayside radios, 181 antennas, 3,097 transponders, and 223 miles of fiber optic cable), onboard equipment installation on the commuter rail fleet’s locomotives and control cars, Field Qualification Testing on the Stoughton Pilot Line, PTC training of Keolis personnel, and implementation of the PTC Configuration Management System.
Additionally, in October the FRA approved the MBTA’s Revenue Service Demonstration (RSD) Application to place the Stoughton Line in RSD. Eighty-five consecutive trips are required to be completed with the PTC system engaged during the RSD phase, which also allows real-world operations to take place, ensuring the training, processes, and system configurations are sufficient to support safe and regularly scheduled revenue service operations. The Stoughton Line’s RSD operation began in November, with 85 consecutive successful trips completed in mid-December.
On the North Side, Field Qualification Testing, which confirms all wayside and on-board units are operating as intended, on the Lowell Line is complete. An RSD Application for the North Side Commuter Rail lines starting with the Lowell Line will be submitted to the FRA in January 2019 with an anticipated FRA approval in February 2019.
Additional next steps for the MBTA’s PTC Program include testing completion and placement of the remaining South Side Commuter Rail lines in Extended RSD. Middleborough Line testing is currently underway with continued Automatic Train Control implementation upcoming on the Worcester, Needham, and Franklin Lines. Coordination with Amtrak, CSX, and Pan Am Railways will also continue for interoperability testing.
The MBTA, together with its contractors, continues to achieve its goals in executing PTC Program Plans to deploy PTC across the entire Commuter Rail System in compliance with FRA regulations, which requires complete PTC deployment by the end of December 2020.
More Security and Safety

New York MTA Launches Historic $1.9B Signal, Track Modernization Project
Funded in part by congestion pricing revenue, the project will replace nearly century-old signals along the A and C lines in Brooklyn and Queens.
Read More →
CSA Group Releases Climate Resilience Standard for Transit, Passenger Rail
Developed with support from the Standards Council of Canada, CSA D700 guides assessing climate-related risks and planning adaptation measures for transit and passenger rail systems.
Read More →
San Diego MTS Approves New Fare Evasion Penalty Program
The new administrative process will move eligible violations out of the criminal court system, cap penalties at $125, and provide flexible payment options for riders.
Read More →
RTC of Southern Nevada Reports 29% Drop in Transit Operator Assaults
The agency credits expanded security measures, employee training, and technology investments for improvements in transit safety, while security officers have responded to 19 suspected overdoses since July.
Read More →
Public Transit Conference Returning to GFX in 2027, Call for Papers Now Open
The Call for Papers is now open, allowing transit agency professionals and industry experts to help shape the PTC educational program by submitting session ideas for consideration.
Read More →
Safe Transit Act Proposes New Security Requirements for Federal Transit Funding
Proposed legislation would link federal transit dollars to safety measures while requiring security investments, onboard cameras, and new fare collection standards.
Read More →
FTA Ends Direct Oversight of MBTA Safety Actions
The federal agency closed its remaining special directive to the Massachusetts Department of Public Utilities following a safety review that began in 2022.
Read More →
Transit Agencies Highlight Safety Gains at National Summit
Leaders from 15 major transit systems shared crime-reduction results and safety initiatives while discussing the role of continued federal support.
Read More →
DART Launches Major Security, Fare Enforcement Initiative
The 90-day demonstration will deploy coordinated security teams at five light rail stations while testing controlled access and gathering data to guide future investments.
Read More →
RTD Launches NextRide App to Consolidate Trip Planning, Fares, Security Reporting
The app expands on RTD’s existing NextRide web application and allows customers to view real-time vehicle locations and service alerts, purchase and store digital fares, and access customer support.
Read More →