Work remains as 63.2% of all commuter railroads’ cumulative required route miles were PTC-governed as of March 31, an 8.5% increase since last quarter.
The Federal Railroad Administration (FRA) released a quarterly status update on railroads’ self-reported progress, as of March 31, toward fully implementing positive train control (PTC) systems by Dec. 31, 2020, as required by Congress. Based on railroads’ First Quarter 2020 PTC Progress Reports and current PTC Implementation Plans, nearly all railroads subject to the statutory mandate are operating their systems in revenue service or in advanced field testing, known as revenue service demonstration (RSD), with PTC technology remaining to be activated on only approximately 1,100 required route miles.
“We continue to work directly with all ‘to be compliant’ railroads — providing technical support and guidance as requested — to enable them to satisfactorily meet the Congressional deadline,” FRA Administrator Ronald L. Batory said.
Ad Loading...
As of March 31, PTC systems were in RSD or in operation on 56,541 route miles — 98% of the nearly 58,000 route miles subject to the mandate. Specifically, at the end of the first quarter of 2020, PTC systems were governing operations on all PTC-mandated main lines owned or controlled by Class I freight railroads and other freight host railroads subject to the mandate.
While most commuter railroads’ PTC systems are in RSD on their entire mandated networks, work remains as 63.2% of all commuter railroads’ cumulative required route miles were PTC-governed as of March 31, an 8.5% increase since last quarter. In addition, interoperability has reportedly been achieved in 48.5% of the 229 applicable, host-tenant railroad relationships as of March 31, a 10% increase since the fourth quarter of 2019.
Recognizing that 33 weeks remain until the final implementation deadline set forth by Congress, FRA continues to direct additional staff resources to railroads at risk of not fully implementing an FRA-certified and interoperable PTC system on their required main lines by Dec. 31. To evaluate the risk of noncompliance, FRA is primarily considering the following factors: (1) the percentage of mandated route miles currently governed by a PTC system, including RSD; (2) any unresolved technical issue in implementing a compliant PTC system; (3) the percentage of a host railroad’s tenant railroads that have achieved required interoperability; and (4) a host railroad’s expected date to submit its PTC Safety Plan to FRA, necessary to obtain PTC System Certification.
Based on railroads’ self-reported progress on these factors as of March 31, FRA currently considers the following four host railroads at risk of not fully implementing a PTC system on all required main lines by December 2020: New Jersey Transit, TEXRail, Northeast Illinois Regional Commuter Railroad Corporation (Metra), and New Mexico Rail Runner Express (Rio Metro).
“We strongly urge the collaborating railroads to work in a safe, focused and aggressive manner to meet this end-of-year deadline,” Batory said. “FRA has provided nearly $2.6 billion in grants and loans and thousands of hours of technical assistance to help railroads fully implement PTC systems.”
The Plan is CTA's formal response to an FTA Special Directive issued in December and details how the agency will significantly expand the law enforcement surge it launched.
On a recent episode of METROspectives, METRO Magazine’s Executive Editor Alex Roman sat down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the CSA Group, to explore a bold initiative aimed at addressing those challenges: the development of a National Code for Transit and Passenger Rail Systems in Canada.
During a safety blitz, Metra employees will visit one of the railroad’s 243 stations during the morning rush hour, distributing educational materials on train and grade-crossing safety, answering questions, and listening to riders’ safety concerns.
Operated in partnership with Tech Valley Security, trained CDTA Ambassadors will be on select routes and will rotate throughout CDTA’s route network. Their presence is intended to provide customers with an approachable, visible resource focused on assistance and engagement.
Customers have always been able to report concerns through the CATS Customer Service line or the “Report a Problem to CATS” feature in the CATS-Pass mobile app; however, CATS has also integrated a Text-a-Tip line, giving riders multiple, easy-to-use channels to get support.