All speed restrictions that were in place prior to the shutdown have been alleviated in this area, improving travel times by over 10 minutes for Ashmont Branch and Mattapan Line riders.
Crews performing in-station work on the stairway areas at JFK/UMass station.
Photo: MBTA
2 min to read
Boston’s MBTA completed critical track work on the Red Line’s Ashmont Branch between JFK/UMass and Ashmont Stations and the Mattapan Line.
Shuttle buses replaced service on the Ashmont Branch and Mattapan Line for 16 days from October 14 to 29, with regular service resuming at the start of service on Monday, Oct. 30.
Ad Loading...
“The MBTA is proud to have successfully completed this critical work on an expedited timeline. As a result, Red Line and Mattapan Line riders are now experiencing safer, faster, and more reliable service. I want to thank the public for their patience as we completed critical infrastructure work along the Ashmont Branch and Mattapan Line over the last 16 days,” said MBTA GM/CEO Phillip Eng. “I thank the MBTA team for their tireless efforts. As we move toward delivering essential work to restore service levels across our entire system, lessons learned will be incorporated and enable us to continue to streamline efforts and better serve the public.”
Completed Red Line Work
The diversion allowed crews to replace nearly 5,000 feet of rail and 1,174 ties on the Ashmont Branch and nearly 4,700 feet of rail and 1,380 ties on the Mattapan Line, improving reliability and reducing maintenance needs.
Following this work, all speed restrictions that were in place prior to the shutdown have been alleviated in this area, improving travel times by over 10 minutes for Ashmont Branch and Mattapan Line riders. The MBTA expedited this important work by working around the clock for 16 days with unencumbered access, which would have otherwise taken six months to complete if crews only worked during nights and weekends.
The MBTA also maximized these full-access closures by performing a variety of in-station work along both lines to improve the rider experience, including new floor tiling, ceiling and platform canopy repairs, new paint, new tactile edging on platforms, stairway repairs, new lighting, vegetation removal, and power washing.
The Ashmont Branch serves approximately 40,000 riders per day, and the Mattapan Line serves approximately 3,700 riders daily.
Amtrak will open grant applications March 23 for community projects near the Frederick Douglass Tunnel alignment in Baltimore as part of a $50 million investment tied to the B&P Tunnel Replacement Program.
The Denmark Station $2.3 million construction investment project includes a new 280-foot concrete boarding platform, built eight inches above the top of rail, for improved accessibility for passengers with disabilities and families with small children and much more.
Caltrain and its partners have implemented safety improvements at specific locations in response to known risk conditions, operational needs, and available funding since the agency’s founding.
On a recent episode of METROspectives, METRO Magazine’s Executive Editor Alex Roman sat down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the CSA Group, to explore a bold initiative aimed at addressing those challenges: the development of a National Code for Transit and Passenger Rail Systems in Canada.
Competitive FTA grants will support accessibility upgrades, family-friendly improvements, and cost-efficient capital projects at some of the nation’s oldest and busiest transit hubs.
The 3.92-mile addition will soon take riders west beyond its current Wilshire and Western station in Koreatown, continuing under Wilshire Boulevard through neighborhoods and communities including Hancock Park, Windsor Square, the Fairfax District, and Carthay Circle into Beverly Hills.
Under the plan, all long-distance routes will transition to a universal single-level fleet, replacing today’s mix of bi-level and single-level equipment.