MBTA's Red Line Now Slow Zone-Free for First Time in 20 Years

As a result of unencumbered access to track areas, crews accomplished important work to lift two speed restrictions along over 2,000 feet of track as part of the Track Improvement Program.

November 26, 2024
MBTA's Red Line Now Slow Zone-Free for First Time in 20 Years

Critical track and tamping work was performed at MBTA's Red Line stations.

3 min to read


Boston’s MBTA announced the successful completion of critical track work on the Red Line while service was suspended between Harvard and Broadway the evening of November 17 through November 23 and between Harvard and JFK/UMass on November 24. 

The Red Line is now completely free of all slow zones for the first time in at least 20 years, joining both the Blue and Orange lines as speed restriction-free. 

Ad Loading...

The Green Line will be free of its final speed restrictions following upcoming track work in December, making the entire subway system free of speed restrictions. 

“I’m proud of the tremendous amount of work we’re accomplishing. The track in these areas of the Red Line is very challenging for crews to be able to access, but our workforce was given the unencumbered time on the track that they needed to finally do the work to completely remove these slow zones,” said MBTA GM/CEO Phillip Eng. “There’s more work to do on the Green Line next month to make the entire subway system slow zone-free, but we’re now well-positioned to efficiently maintain our system for years to come with the goal of providing the safe, reliable service our riders can be proud of.” 

Crews worked in critical track areas during the MBTA's Red Line service suspension.

Work Completed

As a result of unencumbered access to track areas, crews accomplished important work to lift two speed restrictions along over 2,000 feet of track as part of the Track Improvement Program. Workers also maximized the outage by performing signal upgrades, security enhancements, station amenity upgrades, and more.

With unencumbered access to Red Line stations, crews accomplished the following work: 

  • Replaced 2,230 feet of rail. 

  • Performed approximately 970 feet of full depth track replacement. 

  • Replaced 177 ties and 3,350 plates.  

  • Resurfaced and tamped 13,800 feet of track.

Ad Loading...

A variety of other work also took place along the Red Line to further enhance the rider experience, including: 

  • Stairway repairs at Kendall/MIT, Park Street, and Downtown Crossing. 

  • Repairs to a tunnel construction joint in four locations at Kendall/MIT. 

  • Electrical room repairs at Kendall/MIT. 

  • Signal modernization work, including the installation of wires and cable at Central’s signal room, the removal and replacement of 15 WeeZee bonds, repairs and upgrades to additional bonds, switch and track circuit upgrades, and the installation of new switch infrastructure at the complicated area of crossover track at Park Street. 

  • Electrical work on the outbound Kendall/MIT headhouse. 

  • Security enhancements at Charles/MGH and Park Street. 

  • The completion of door surveys and inspections at stations throughout the shutdown area. 

  • Removed over 1,200 Pandrol Panguard plates with the installation of over 1,200 new resilient RF-A fastener plates between Park Street and Charles/MGH, which will improve noise/vibration mitigation and provide better maintainability. 

  • Power modernization work, including replacing third rail at South Station, as well as power and cable replacement at Kendall/MIT. 

  • Plumbing and drainage improvements, concrete repairs, painting, bench repairs, brick replacement, and power washing within stations throughout the shutdown area.

More Rail

A New York MTA subway car with an open gangway
Railby Staff and News ReportsSeptember 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →
A San Diego MTS Copper Line vehicle
Railby Staff and News ReportsSeptember 15, 2026

San Diego MTS Breaks Monthly Trolley Ridership Record

Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.

Read More →
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Railby Alex RomanSeptember 14, 2026

Report Examines NJ TRANSIT Reliability, Funding Challenges

The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.

Read More →
Ad Loading...
A CapMetro commuter rail train provided by Stadler
Railby Staff and News ReportsSeptember 11, 2026

Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement

Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.

Read More →
Rendering of an Alstom train in a VIA Rail Station
Technologyby Alex RomanSeptember 10, 2026

Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More

In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.

Read More →
The CATS Gold Line in service with the city skyline in the background.
Railby Staff and News ReportsSeptember 3, 2026

CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips

With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Amtrak Sunnyside Groundbreaking
Railby Staff and News ReportsSeptember 2, 2026

Amtrak Begins Major Construction at New York’s Sunnyside Yard

The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.

Read More →
O'Hare Flyer Rendering
Railby Staff and News ReportsAugust 27, 2026

Chicago Leaders Unveil Plans for O’Hare Airport Express Train

The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.

Read More →
Ad Loading...
An OCTA coastal rail line train.
Railby Staff and News ReportsAugust 27, 2026

OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor

The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.

Read More →