MBTA's Red Line Now Slow Zone-Free for First Time in 20 Years
As a result of unencumbered access to track areas, crews accomplished important work to lift two speed restrictions along over 2,000 feet of track as part of the Track Improvement Program.
Critical track and tamping work was performed at MBTA's Red Line stations.
3 min to read
Boston’s MBTA announced the successful completion of critical track work on the Red Line while service was suspended between Harvard and Broadway the evening of November 17 through November 23 and between Harvard and JFK/UMass on November 24.
The Red Line is now completely free of all slow zones for the first time in at least 20 years, joining both the Blue and Orange lines as speed restriction-free.
Ad Loading...
The Green Line will be free of its final speed restrictions following upcoming track work in December, making the entire subway system free of speed restrictions.
“I’m proud of the tremendous amount of work we’re accomplishing. The track in these areas of the Red Line is very challenging for crews to be able to access, but our workforce was given the unencumbered time on the track that they needed to finally do the work to completely remove these slow zones,” said MBTA GM/CEO Phillip Eng. “There’s more work to do on the Green Line next month to make the entire subway system slow zone-free, but we’re now well-positioned to efficiently maintain our system for years to come with the goal of providing the safe, reliable service our riders can be proud of.”
Crews worked in critical track areas during the MBTA's Red Line service suspension.
Work Completed
As a result of unencumbered access to track areas, crews accomplished important work to lift two speed restrictions along over 2,000 feet of track as part of the Track Improvement Program. Workers also maximized the outage by performing signal upgrades, security enhancements, station amenity upgrades, and more.
With unencumbered access to Red Line stations, crews accomplished the following work:
Replaced 2,230 feet of rail.
Performed approximately 970 feet of full depth track replacement.
Replaced 177 ties and 3,350 plates.
Resurfaced and tamped 13,800 feet of track.
Ad Loading...
A variety of other work also took place along the Red Line to further enhance the rider experience, including:
Stairway repairs at Kendall/MIT, Park Street, and Downtown Crossing.
Repairs to a tunnel construction joint in four locations at Kendall/MIT.
Electrical room repairs at Kendall/MIT.
Signal modernization work, including the installation of wires and cable at Central’s signal room, the removal and replacement of 15 WeeZee bonds, repairs and upgrades to additional bonds, switch and track circuit upgrades, and the installation of new switch infrastructure at the complicated area of crossover track at Park Street.
Electrical work on the outbound Kendall/MIT headhouse.
Security enhancements at Charles/MGH and Park Street.
The completion of door surveys and inspections at stations throughout the shutdown area.
Removed over 1,200 Pandrol Panguard plates with the installation of over 1,200 new resilient RF-A fastener plates between Park Street and Charles/MGH, which will improve noise/vibration mitigation and provide better maintainability.
Power modernization work, including replacing third rail at South Station, as well as power and cable replacement at Kendall/MIT.
Plumbing and drainage improvements, concrete repairs, painting, bench repairs, brick replacement, and power washing within stations throughout the shutdown area.
Amtrak will open grant applications March 23 for community projects near the Frederick Douglass Tunnel alignment in Baltimore as part of a $50 million investment tied to the B&P Tunnel Replacement Program.
The Denmark Station $2.3 million construction investment project includes a new 280-foot concrete boarding platform, built eight inches above the top of rail, for improved accessibility for passengers with disabilities and families with small children and much more.
Caltrain and its partners have implemented safety improvements at specific locations in response to known risk conditions, operational needs, and available funding since the agency’s founding.
On a recent episode of METROspectives, METRO Magazine’s Executive Editor Alex Roman sat down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the CSA Group, to explore a bold initiative aimed at addressing those challenges: the development of a National Code for Transit and Passenger Rail Systems in Canada.
Competitive FTA grants will support accessibility upgrades, family-friendly improvements, and cost-efficient capital projects at some of the nation’s oldest and busiest transit hubs.
The 3.92-mile addition will soon take riders west beyond its current Wilshire and Western station in Koreatown, continuing under Wilshire Boulevard through neighborhoods and communities including Hancock Park, Windsor Square, the Fairfax District, and Carthay Circle into Beverly Hills.
Under the plan, all long-distance routes will transition to a universal single-level fleet, replacing today’s mix of bi-level and single-level equipment.