MBTA's Red Line Now Slow Zone-Free for First Time in 20 Years

As a result of unencumbered access to track areas, crews accomplished important work to lift two speed restrictions along over 2,000 feet of track as part of the Track Improvement Program.

November 26, 2024
MBTA's Red Line Now Slow Zone-Free for First Time in 20 Years

Critical track and tamping work was performed at MBTA's Red Line stations.

3 min to read


Boston’s MBTA announced the successful completion of critical track work on the Red Line while service was suspended between Harvard and Broadway the evening of November 17 through November 23 and between Harvard and JFK/UMass on November 24. 

The Red Line is now completely free of all slow zones for the first time in at least 20 years, joining both the Blue and Orange lines as speed restriction-free. 

Ad Loading...

The Green Line will be free of its final speed restrictions following upcoming track work in December, making the entire subway system free of speed restrictions. 

“I’m proud of the tremendous amount of work we’re accomplishing. The track in these areas of the Red Line is very challenging for crews to be able to access, but our workforce was given the unencumbered time on the track that they needed to finally do the work to completely remove these slow zones,” said MBTA GM/CEO Phillip Eng. “There’s more work to do on the Green Line next month to make the entire subway system slow zone-free, but we’re now well-positioned to efficiently maintain our system for years to come with the goal of providing the safe, reliable service our riders can be proud of.” 

Crews worked in critical track areas during the MBTA's Red Line service suspension.

Work Completed

As a result of unencumbered access to track areas, crews accomplished important work to lift two speed restrictions along over 2,000 feet of track as part of the Track Improvement Program. Workers also maximized the outage by performing signal upgrades, security enhancements, station amenity upgrades, and more.

With unencumbered access to Red Line stations, crews accomplished the following work: 

  • Replaced 2,230 feet of rail. 

  • Performed approximately 970 feet of full depth track replacement. 

  • Replaced 177 ties and 3,350 plates.  

  • Resurfaced and tamped 13,800 feet of track.

Ad Loading...

A variety of other work also took place along the Red Line to further enhance the rider experience, including: 

  • Stairway repairs at Kendall/MIT, Park Street, and Downtown Crossing. 

  • Repairs to a tunnel construction joint in four locations at Kendall/MIT. 

  • Electrical room repairs at Kendall/MIT. 

  • Signal modernization work, including the installation of wires and cable at Central’s signal room, the removal and replacement of 15 WeeZee bonds, repairs and upgrades to additional bonds, switch and track circuit upgrades, and the installation of new switch infrastructure at the complicated area of crossover track at Park Street. 

  • Electrical work on the outbound Kendall/MIT headhouse. 

  • Security enhancements at Charles/MGH and Park Street. 

  • The completion of door surveys and inspections at stations throughout the shutdown area. 

  • Removed over 1,200 Pandrol Panguard plates with the installation of over 1,200 new resilient RF-A fastener plates between Park Street and Charles/MGH, which will improve noise/vibration mitigation and provide better maintainability. 

  • Power modernization work, including replacing third rail at South Station, as well as power and cable replacement at Kendall/MIT. 

  • Plumbing and drainage improvements, concrete repairs, painting, bench repairs, brick replacement, and power washing within stations throughout the shutdown area.

More Rail

PATCO's New Control Center
Managementby StaffMay 7, 2026

PATCO Opens New Operations Control Center

The new center serves as the central hub for monitoring and managing PATCO train operations, communications, customer service coordination, incident response, and overall operational oversight across the transit system.

Read More →
VIA Rail Canada logo
Railby StaffMay 7, 2026

VIA Rail reports Stable Ridership, Rising Revenue Amid Ongoing Challenges

Despite these pressures, VIA Rail is reporting that total revenues increased to $514.8 million as more travelers took advantage of the wide range of options available through the corporation’s new reservation system.

Read More →
SEPTA's advertisement for multi-rider feature.
Technologyby StaffMay 7, 2026

Philadelphia's SEPTA Introduces Multi-Rider Feature for Contactless Payments

Up until now, this feature was only available when using a SEPTA Key card.

Read More →
Ad Loading...
A Waev Gem vehicle with a ramp deployed.

ABC Teams with Waev, Knorr-Bremse in Boston Top Biz Briefs

Stay informed with these quick takes on the projects and companies driving progress across the transportation landscape.

Read More →
Books with graduation mortar board
Managementby StaffMay 6, 2026

New Chicago Scholarship Program Targets Student Pathways to Construction Careers

Created in partnership with Walsh-VINCI Transit Community Partners, the contractor for CTA’s historic $5.7 billion RLE project, the new $250,000 scholarship program will provide three students a year from 2026 to 2030 with $3,000 scholarships.

Read More →
Steve Goodreau
Technologyby Alex RomanMay 6, 2026

Trackless Rapid Transit: Hype or Viable Option?

Steve Goodreau of WSP explores the technology’s promise, limitations and where it may fit in the evolving transit landscape.

Read More →
Ad Loading...
Operation Lifesaver Rail Safety Education logo over railroad tracks background, representing rail safety awareness initiatives.
Railby News/Media ReleaseMay 4, 2026

Operation Lifesaver Awards Rail Safety Outreach Funds in 12 States

Operation Lifesaver awarded $220,200 in grants to 12 states to support rail safety campaigns focused on grade crossing awareness and trespass prevention.

Read More →
Caltrain trains on tracks
Railby StaffMay 1, 2026

Caltrain Survey Shows Record-High Rider Approval

The survey showed that commute trips still make up the majority of ridership, with most riders boarding 2 to 3 days a week, reflecting hybrid work schedules. Two-thirds of Caltrain riders have access to a car, while 37% of Caltrain riders are considered low-income.

Read More →
A person working on a bus
ManagementMay 1, 2026

Data-Driven Maintenance: Focusing Effort Where It Matters Most

Advances in data and analytics are giving transit agencies new opportunities to refine maintenance practices, improve efficiency and make more informed decisions about asset performance.

Read More →
Ad Loading...
Carmen C. Cham of HNTB
Managementby Alex RomanApril 29, 2026

How Transit Architecture Is Reshaping the Rider Journey

In this Consultant Roundtable, Carmen C. Cham shares insights on how agencies can create spaces that are intuitive, connected and built for long-term impact.

Read More →