Crews work on sections of rail for the Hilltop Tacoma Link extension.
Sound Transit
2 min to read
Crews work on sections of rail for the Hilltop Tacoma Link extension.
Sound Transit
Crews on Sound Transit’s Hilltop Tacoma Link Extension project installed the first 300-foot rail segments for the 2.4-mile extension through the Stadium District and Hilltop neighborhood. The new rails were placed on Stadium Way south of Division Street. Once the rail installation is complete, there is two-week test and inspection period to ensure the rails meet design specifications.
The Hilltop Tacoma Link Extension is being built by Walsh Construction Company II LLC.
Ad Loading...
Since last fall, construction has concentrated on relocating underground utilities, building foundations for Link power poles, building traction power substations, and expanding the Link Operations and Maintenance facility near Freighthouse Square.
Initial work on the Hilltop Tacoma Link Extension includes relocating nearly 10,000 feet of underground utility lines and built the foundations for 60 of the more that 300 Link power poles that will be built as part of the project. At the Operations and Maintenance facility expansion nearly 200 piles have been installed and 50% of the utility work is complete. Crews will erect structural steel beams at the facility this July.
When finished, the project extends the existing Tacoma Link system up Stadium Way, N. E St., 1st Street, Division Avenue, and down Martin Luther King Jr. Way to South 19th Street. This includes relocating the existing Theatre District station and building seven new stations along the Link system.
Sound Transit is simultaneously working to extend regional light rail north, south, east and west, opening new stations every few years to form a 116-mile regional system by 2041. Northgate Link will open in 2021, to be followed in 2023 by the opening of service to Mercer Island, Bellevue and Redmond’s Overlake community.
Additional extensions to Shoreline, Mountlake Terrace, Lynnwood, Kent/Des Moines, Federal Way and downtown Redmond are planned in 2024. Further light rail extensions are scheduled to reach West Seattle, Fife and Tacoma in 2030; Ballard in 2035; Paine Field and Everett in 2036; and South Kirkland and Issaquah in 2041.
Amtrak will open grant applications March 23 for community projects near the Frederick Douglass Tunnel alignment in Baltimore as part of a $50 million investment tied to the B&P Tunnel Replacement Program.
The Denmark Station $2.3 million construction investment project includes a new 280-foot concrete boarding platform, built eight inches above the top of rail, for improved accessibility for passengers with disabilities and families with small children and much more.
Caltrain and its partners have implemented safety improvements at specific locations in response to known risk conditions, operational needs, and available funding since the agency’s founding.
On a recent episode of METROspectives, METRO Magazine’s Executive Editor Alex Roman sat down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the CSA Group, to explore a bold initiative aimed at addressing those challenges: the development of a National Code for Transit and Passenger Rail Systems in Canada.
Competitive FTA grants will support accessibility upgrades, family-friendly improvements, and cost-efficient capital projects at some of the nation’s oldest and busiest transit hubs.
The 3.92-mile addition will soon take riders west beyond its current Wilshire and Western station in Koreatown, continuing under Wilshire Boulevard through neighborhoods and communities including Hancock Park, Windsor Square, the Fairfax District, and Carthay Circle into Beverly Hills.
Under the plan, all long-distance routes will transition to a universal single-level fleet, replacing today’s mix of bi-level and single-level equipment.