Test Track and Vehicle Testing Facility to Be Used for New MBTA Red Line Cars

The dedicated track and facility will give the MBTA flexibility and control over the testing process and will allow a faster rollout of the new fleet.

by Staff
January 5, 2022
Test Track and Vehicle Testing Facility to Be Used for New MBTA Red Line Cars

Aerial view of the completed Red Line Test Track and Vehicle Testing Facility

Photo: MBTA

1 min to read


New Red Line cars shipped from Springfield to Boston will be commissioned using the recently completed $22 million Red Line Test Track and Vehicle Testing Facility, built as part of the Red Line Transformation Program, according to the Massachusetts Bay Transportation Authority's (MBTA) press release.

The dedicated track and facility will give the MBTA flexibility and control over the testing process and will allow a faster rollout of the new fleet.

Ad Loading...

The new test track and testing facility will soon be used to commission the first production vehicles before the end of the Winter and an increase of deliveries is expected throughout 2022. At the same time, deliveries continue for Orange Line trains.

“The installation of the new test track and testing facility enables the timely commissioning of new Red Line vehicles as part of the MBTA’s plan to increase capacity and improve reliability on the Red Line,” said Steve Poftak, MBTA GM.

The new test track is adjacent to Cabot Yard (near Broadway Station), allowing easy access for vehicle deliveries and testing without interfering with regular maintenance or competing for access on the mainline with regular service.

“The completion of this project brings our team one step closer to delivering state-of-the-art, more reliable vehicles to our Red Line ridership,” said Angel Peña, chief of Capital Transformation.

More Rail

A New York MTA subway car with an open gangway
Railby Staff and News ReportsSeptember 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →
A San Diego MTS Copper Line vehicle
Railby Staff and News ReportsSeptember 15, 2026

San Diego MTS Breaks Monthly Trolley Ridership Record

Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.

Read More →
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Railby Alex RomanSeptember 14, 2026

Report Examines NJ TRANSIT Reliability, Funding Challenges

The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.

Read More →
Ad Loading...
A CapMetro commuter rail train provided by Stadler
Railby Staff and News ReportsSeptember 11, 2026

Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement

Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.

Read More →
Rendering of an Alstom train in a VIA Rail Station
Technologyby Alex RomanSeptember 10, 2026

Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More

In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.

Read More →
The CATS Gold Line in service with the city skyline in the background.
Railby Staff and News ReportsSeptember 3, 2026

CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips

With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Amtrak Sunnyside Groundbreaking
Railby Staff and News ReportsSeptember 2, 2026

Amtrak Begins Major Construction at New York’s Sunnyside Yard

The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.

Read More →
O'Hare Flyer Rendering
Railby Staff and News ReportsAugust 27, 2026

Chicago Leaders Unveil Plans for O’Hare Airport Express Train

The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.

Read More →
Ad Loading...
An OCTA coastal rail line train.
Railby Staff and News ReportsAugust 27, 2026

OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor

The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.

Read More →