Amtrak announces summer New York infrastructure renewal work

The total cost of the projects is estimated between $45 and $50 million, which will keep this important infrastructure in a state of good repair for Amtrak and benefit New York State with an upgraded, state-of-the art railroad.

April 11, 2018
Amtrak announces summer New York infrastructure renewal work

 

2 min to read


Amtrak will continue its Infrastructure Renewal program at New York Penn Station during Summer 2018 by performing critical reconstruction of three major railroad infrastructure assets in New York City: The Empire Tunnel and the Spuyten Duyvil Bridge, which provides train access between Upstate New York and New York Penn Station, as well as renewal work on Track 19 in New York Penn Station that will help provide commuters with more reliable service. The total cost of the projects is estimated between $45 and $50 million, which will keep this important infrastructure in a state of good repair for Amtrak and benefit New York State with an upgraded, state-of-the art railroad.

Due to the work on the Empire Connection and Spuyten Duyvil Bridge, Empire Service, Ethan Allen Express, Adirondack, and Maple Leaf trains will all be rerouted from New York Penn Station to Grand Central Terminal between May 26 to Sept. 4. The Lake Shore Limited will only operate between Boston and Chicago, with New York City and Hudson Valley customers connecting from Empire Service trains at Albany-Rensselaer.

Ad Loading...

While the schedules have yet to be finalized, there will be fewer service impacts and schedule changes compared to summer 2017. The work on Track 19 will occur between June 8 to July 20. The modified schedule Amtrak announced in January 2018 will continue until the work on Track 19 is complete.

“Amtrak is continuing to prioritize updating the infrastructure in and around New York Penn Station to improve our service reliability,” said Amtrak Executive VP/COO Scot Naparstek. “We thank our partners for their coordination and flexibility as we continue this important and necessary work.”

Specifics of the work include:

  • Empire Connection – Amtrak will be replacing track in the Empire Tunnel, as well as replacing cross ties, grade crossings and 8,000 feet of continuous rail, including the track between the tunnel and the Spuyten Duyvil Bridge.

  • Spuyten Duyvil Bridge – Amtrak will be updating the bridge’s mechanical and electrical equipment, which was corroded by Hurricane Sandy.

  • Track 19 at New York Penn Station – Amtrak will replace three turnouts and conduct total ballasted track and wood tie track replacement.

While Amtrak has maintained and repaired this aging infrastructure, some of which dates to the 1970s, full replacement is now required. During the summer of 2017, Amtrak kicked off its Infrastructure Renewal at New York Penn Station, and continued it in early 2018. The Infrastructure Renewal program is one element of Amtrak’s plan to modernize stations, infrastructure, and equipment on the Northeast Corridor.

More Rail

A New York MTA subway car with an open gangway
Railby Staff and News ReportsSeptember 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →
A San Diego MTS Copper Line vehicle
Railby Staff and News ReportsSeptember 15, 2026

San Diego MTS Breaks Monthly Trolley Ridership Record

Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.

Read More →
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Railby Alex RomanSeptember 14, 2026

Report Examines NJ TRANSIT Reliability, Funding Challenges

The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.

Read More →
Ad Loading...
A CapMetro commuter rail train provided by Stadler
Railby Staff and News ReportsSeptember 11, 2026

Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement

Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.

Read More →
Rendering of an Alstom train in a VIA Rail Station
Technologyby Alex RomanSeptember 10, 2026

Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More

In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.

Read More →
The CATS Gold Line in service with the city skyline in the background.
Railby Staff and News ReportsSeptember 3, 2026

CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips

With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Amtrak Sunnyside Groundbreaking
Railby Staff and News ReportsSeptember 2, 2026

Amtrak Begins Major Construction at New York’s Sunnyside Yard

The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.

Read More →
O'Hare Flyer Rendering
Railby Staff and News ReportsAugust 27, 2026

Chicago Leaders Unveil Plans for O’Hare Airport Express Train

The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.

Read More →
Ad Loading...
An OCTA coastal rail line train.
Railby Staff and News ReportsAugust 27, 2026

OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor

The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.

Read More →