METRO Magazine Logo
MenuMENU
SearchSEARCH

Tips for Design and Layout of a First-Class Bus Maintenance Facility

No site is perfect, but every proposal should be viewed from all angles. Key considerations: cost of acquisition, room for expansion, topography, environmental factors — and your future neighbors.

by Michael T. Lee, Gannett Fleming Inc.
April 1, 2003
Tips for Design and Layout of a  First-Class Bus 
Maintenance Facility

 

7 min to read


In a perfect world, you’d want to build a new bus maintenance facility on a site that’s level, rectangular and centrally located within the service region. In addition, you’d like it be free of environmental contamination and large enough to accommodate all present needs and any future expansion. But that’s not all. You’d also like to have adequate existing utility services and, of course, no neighbors to lodge complaints about traffic, noise and congestion. Certainly you’ve heard of NIMBY (Not in My Back Yard!). Where can you find such a site? No, don’t start looking. It probably doesn’t exist, not even in Kansas. Often the available sites are limited based on considerations other than the most obvious ones. Limiting site selection factors include local political agendas, real estate and redevelopment interests, zoning regulations, availability and affordability of suitable land. In large urban areas, many of the available sites generally are one of two types. The first type is one that currently has a transit facility. These sites can generally be adapted for re-use without going through the full environmental impact statement (EIS) process, which can take a considerable amount of time and money. These sites generally will require an environmental assessment along with some environmental clean-up, usually for petroleum hydrocarbons. The challenge of using such a site is that it often requires staged construction to erect a new building, renovate an existing structure, or both. Such a site may also require the temporary relocation of the bus operations. All of these things will add to the capital and operating costs of the project. The second type of site generally available is one that has one or more significant undesirable features. Such features can include a high initial purchase cost, a remote location from the service area, significant environmental contamination (including petroleum hydrocarbons, heavy metals, asbestos and pesticides), large elevation differences, the presence of wetlands restricting development or adverse subsurface geological conditions. The best approach to selecting a site is to weigh the capital and operating costs of all available site options before deciding on the best way to proceed. Laying out the site Before a site can be laid out, the functional requirements must be defined. The most important factor is the existing bus fleet size and the potential for an expanded fleet size. Included in this thought process should be consideration of what might be needed if the future fleet is to include articulated buses, alternatively fueled buses and paratransit vehicles. Basic elements to be included in the planning process include assessing the spatial area requirements for general bus maintenance, fare removal, fueling, exterior washing, interior cleaning and bus storage. Additional space will be required for administrative and operating staff offices, training rooms, lunch rooms, locker rooms and associated toilet facilities. Space will be needed for parts storage, body and paint shops, tire shops and heavy repair areas. On-site parking will be required for vehicles for employees and vendors who will park on the site. Accommodations should be provided for such items as landscaping, site security, storm water management facilities and, potentially, water treatment facilities. Overall site layout considerations for daily operations need to include queuing space for buses during the mid-day and evening pull-in, bus circulation and storage space prior to maintenance and servicing and circulation area for buses to move to and from storage on the site. Entrance and exit locations to and from the site to adjacent streets are also very important in the consideration of the overall site layout. Care must be taken to separate the automobile circulation and parking areas from that of the buses. Pedestrian circulation from the automobile parking areas to the office, maintenance and bus storage area needs to be analyzed to maximize pedestrian safety. The overall site layout needs to be well considered to maximize the operational efficiency. The site should be planned and laid out to allow as much counterclockwise bus flow as possible, as left turns are easier to make than right turns. Provisions should be made for snow removal operations and snow storage for properties in the northern areas of the United States. The overall site layout should avoid any wetlands or hazardous materials areas as this will add potentially significant capital costs to the project. Placing the buildings The placement of the buildings on the site will be determined by the overall operations to be accommodated. Buildings, either separate or combined, will be required for the bus maintenance facility (which generally includes the administrative and operations areas), the bus storage building (in cold climate areas) and the service facility building for fare removal, fueling, washing and cleaning. There needs to be sufficient queuing for buses into and out of all of the buildings. Bus, truck, automobile and pedestrian circulation on site and between buildings should be separated as much as possible for safety purposes. Each building should be sized to handle present and future operational requirements. An important additional consideration for siting of the buildings is the potential expansion of the buildings. The buildings should be located as close to existing utilities as possible to minimize utility infrastructure costs. The building should also be placed on the site in a manner that provides for adequate access to all four sides of each building structure for local fire fighting apparatus. Do’s for site selection When considering the construction of a new bus maintenance facility, consider the following when selecting a site:

  • Include all stakeholders in the process, especially local politicians and authority staff members.

  • Determine the capital funding source in advance.

  • Consider existing service routes, proposed routes and access to main thoroughfares.

  • Assess adequate and controlled access from the site to at least one major artery.

  • Plan for the future now; consider sites large enough for expansion.

  • Select a site that is large enough so that all bus operations can be done at ground level.

  • Verify adequate utility services are available adjacent to the site.

  • Perform an environmental soil sampling and testing program to identify potential remediation costs and to determine potential building foundation costs.

  • Consider the traffic load that the facility will place on existing streets and roads.

  • Investigate applicable building and zoning codes.

  • Investigate whether stormwater retention will be required.

  • Verify that local ordinances allow for adequate fuel storage. Don’ts for site selection Consider the following things to avoid when choosing a facility site:

  • Don’t choose a site that requires excessive deadhead mileage of bus fleet to revenue routes.

  • Don’t select a site with unknown environmental or geotechnical conditions.

  • Avoid sites with wetlands.

  • Avoid the selection of a site that is within the 100-year flood plain.

  • Avoid sites with severe elevation changes.

  • Don’t wait to contact local building officials and fire marshals about the project.

  • Avoid sites that do not have adequate existing utility services — especially sewer and water.

  • Don’t assume that the facility will be welcomed into any neighborhood.

  • Don’t delay the discussion on whether alternative-fuel vehicles should be considered during the design.

  • Avoid storing buses outside in climates where the temperature falls below 35 degrees.

  • Don’t assume anything — plan ahead for all possibilities to avoid surprises later. Do’s for facility layout Once a site is selected, consider the following when laying out the facility:

  • Separate bus, automobile, truck and pedestrian traffic.

  • Provide sufficient queue space for buses during afternoon pull-in and morning pull-out functions.

  • Lay out the bus circulation for counterclockwise bus movement.

  • Allow for adequate turning radii of buses.

  • Provide for a secondary access to and from the site.

  • Locate buildings on the site to allow for growth.

  • Provide adequate access around buildings for local fire fighting apparatus.

  • Locate fueling tanks in an area that can be easily accessed by fuel trucks.

  • Plan for access of various delivery vehicles. Keep this separate from other vehicular traffic.

  • Provide a separate parking area for trucks that deliver parts and tires.

  • Minimize walking distances from automobile parking areas to work areas.

  • Determine whether the local sewer district will require effluent pretreatment.

  • Buffer the site from adjacent properties to avoid potential noise and light pollution.

  • Include adequate building maintenance and support facilities space in the facility footprint.

  • Choose low-maintenance building materials.

  • Program site and building security into the design.

  • Include the principles of sustainable green design and energy conservation.

  • Design the facility to score as high as possible on the LEED(TM) Green Building Rating System.

  • Include at least one LEED(TM) certified professional on the design team.

  • Seek qualified professional assistance — there is no substitute for experience!

Topics:Management
Subscribe to Our Newsletter

More Management

A Parsons & Sons bus
Motorcoachby Staff and News ReportsFebruary 12, 2026

Parsons & Sons Named METRO’s 2026 Motorcoach Operator of the Year

METRO Executive Editor Alex Roman presented the award to the operation’s President/CEO Scott Parsons at the United Motorcoach Association’s EXPO in Birmingham, Alabama.

Read More →
The ONE Transit Board wearing newly branded hats.
Managementby StaffFebruary 12, 2026

Central Oklahoma RTA Approves New Name, Branding

The brand strategy was developed based on input from RTA board members, staff, and stakeholders, along with secondary research conducted over a months-long process.

Read More →
Fans riding VTA for Super Bowl LX.
Managementby StaffFebruary 10, 2026

VTA Delivers Record Super Bowl LX Ridership

In close coordination with regional partners including Caltrain and BART, the agency ensured convenient interagency connections and seamless transfers for game-day passengers.

Read More →
Ad Loading...
A BART railcar
ManagementFebruary 9, 2026

BART Details Contingency Plans Without Funding

Because rail has high fixed costs and low marginal savings, it is impossible to close the projected FY27 $376M deficit with service cuts and fare increases alone, said agency officials.

Read More →
A picture of C-TRAN's electric bus.
Managementby StaffFebruary 6, 2026

C-TRAN Sees Fourth Consecutive Year of Ridership Growth

The total ridership includes all fixed-route bus service, C-VAN paratransit service, The Current, Vanpool, and special event service. Almost all individual routes saw year-over-year increases from 2024 to 2025.

Read More →
A woman pushes a man in a wheelchair on a rail platform.
Managementby Elora HaynesFebruary 5, 2026

Free Rides, Civil Rights, and the Legacy of Rosa Parks in 2026

Transit agencies across the U.S. commemorated Transit Equity Day with zero fares and a renewed focus on access and equity.

Read More →
Ad Loading...
Rendering of Sound Transit's Renton Transit Center
Busby StaffFebruary 5, 2026

Seattle’s Sound Transit Breaks Ground on New Transit Center

The Renton Transit Center project will relocate and rebuild the Renton Transit Center to better serve the regional Stride S1 line, local King County Metro services, and the future RapidRide I Line.

Read More →
Photo for METROspectives episode with Ana-Maria Tomlinson
ManagementFebruary 4, 2026

Establishing Standards & Codes in Canada, with CSA’s Ana-Maria Tomlinson

In this episode of METROspectives, METRO’s Executive Editor Alex Roman sits down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the Canadian Standards Association (CSA Group).

Read More →
David Carol, Baker Alloush, and Jesse Lazarus from METRO's People Movement February 4 edition.
Managementby Staff and News ReportsFebruary 4, 2026

New Rolling Stock Strategy Lead at New York MTA and More in People Movement

In this edition, we cover recent appointments and announcements at HDR, NCTD, STV, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
Ad Loading...
Railby StaffFebruary 2, 2026

Chicago Region Transit Ridership Grows in 2025

The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.

Read More →