Amtrak Pushes Ahead on Trio of East Coast Rail Yard Projects

Combined with two similar projects already under construction in Philadelphia and Seattle, and another in planning for Rensselaer/Albany, New York, these collective investments will support Amtrak’s continued record ridership growth and help deliver a new era of passenger rail in America.

August 19, 2025
Amtrak Pushes Ahead on Trio of East Coast Rail Yard Projects

Combined with two similar projects already under construction in Philadelphia and Seattle, and another in planning for Rensselaer/Albany, New York, these collective investments will support Amtrak’s continued record ridership growth and help deliver a new era of passenger rail in America.

3 min to read


Amtrak awarded design-build contracts and has begun preconstruction activities for three rail yard modernization projects on the Northeast Corridor (NEC), which will help improve service reliability and enable more efficient, world-class train maintenance, according to the rail line.

“These investments are key to introducing our new Airo trains on the Northeast Corridor beginning in 2027,” said Roger Harris, president at Amtrak. “With ridership and revenue at all-time highs, we’re making great strides to meet this growing demand with new, state-of-the-art trains that will improve service reliability and the overall customer experience.”

Ad Loading...

Investing in Amtrak

Combined with two similar projects already under construction in Philadelphia and Seattle, and another in planning for Rensselaer/Albany, New York, these collective investments will support Amtrak’s continued record ridership growth and help deliver a new era of passenger rail in America.

While not visible to guests on their Amtrak journey, these upgrades are necessary to support new Airo trains arriving on more than a dozen routes over the coming years, said Amtrak officials. 

Each train will be operated as a single “trainset,” rather than individual railcars. The new rail yard facilities will help create a consistent maintenance system that improves efficiencies and reduces turnaround times during repairs or inspections, while also improving safety and overall working conditions for employees.

A Scalamandre-Citnalta Joint Venture will design and construct new maintenance, inspection, and servicing facilities — as well as other related upgrades.

Planned Work

Boston (Southampton Yard)

An SPS New England-Railroad Construction Company (RCC) Joint Venture will design and construct a new maintenance facility and renovate existing facilities to support Northeast Regional, Acela, and Long Distance trains that operate out of this yard, connecting with cities such as Chicago, New York, Philadelphia, Baltimore, Washington DC, and Richmond.

Improvements Include:

Ad Loading...
  • Construction of a new two-track Maintenance & Inspection facility.

  • Renovation of the existing two-track regional Service and Inspection facility into a two-track Service & Cleaning facility.

Work will be conducted in phases, with full project completion expected in 2029.

New York City (Sunnyside Yard)

A Scalamandre-Citnalta Joint Venture will design and construct new maintenance, inspection, and servicing facilities — as well as other related upgrades — to support Northeast Regional, Acela, Long Distance, and commuter trains that operate out of this yard, connecting with cities such as Albany, Boston, Chicago, Philadelphia, Baltimore, Washington DC, Richmond, Raleigh, Charlotte, Miami, and New Orleans.

Improvements Include:

  • Construction of a new two-track Maintenance & Inspection facility.

  • Construction of six new Service and Cleaning tracks with canopy coverage.

  • Consolidation of commissary, employee workspace, material storage, and parking into a single location within the yard, including an efficient modular office compound.

  • Bringing 11 existing service platforms to a state of good repair (required to clean/prepare trains for passenger service and store trainsets when not in operation).

  • Other infrastructure upgrades to accommodate this work, including reconfiguration of two major interlockings and tracks connecting the yard to the NEC.

Ad Loading...

Work will be conducted in phases, with full project completion expected in 2030.

Washington, DC (Ivy City Yard)

A Clark-Herzog Joint Venture will design, construct, and renovate new and existing maintenance and servicing facilities to support Northeast Regional (including the state-supported Amtrak Virginia service), Acela, Long Distance and commuter trains that operate out of this yard, connecting with cities such as Boston, New York, Philadelphia, Baltimore, Richmond, Charlotte, Savannah, Miami, New Orleans, and Chicago.

Improvements Include:

  • Construction of three new exterior Service & Cleaning tracks with canopy coverage.

  • Renovation of two existing two-track maintenance facilities to include a new drop table.

  • Replacement of the existing water main infrastructure within and around the yard, which provides flexibility to serve multiple trainsets across the various facilities.

Work will be conducted in phases, with full project completion expected in 2030.

More Rail

Railby StaffFebruary 2, 2026

Chicago Region Transit Ridership Grows in 2025

The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.

Read More →
Managementby StaffJanuary 29, 2026

Valley Metro Sees Strong Ridership Growth in 2025

The agency ranked top five among mid-sized U.S. transit systems, defined as agencies with 15 million to 50 million annual trips.

Read More →
Busby StaffJanuary 29, 2026

Subway Customer Satisfaction Reaches Record High, New York MTA Says

The subway system saw increases across all key metrics, with 62% of subway riders reporting they feel satisfied with the system overall.

Read More →
Ad Loading...
Managementby StaffJanuary 27, 2026

Keolis Retains Virginia Railway Express Contract

The new contract for Keolis and VRE will commence in July 2026, with the potential to expand to 15 years.

Read More →
Busby StaffJanuary 27, 2026

California's OCTA Advances 2026 Initiatives Centered on Balance and Sustainability

The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.

Read More →
Railby Staff and News ReportsJanuary 26, 2026

People Movement: Virginia's DRPT Names New Director and More

In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
Ad Loading...
ManagementJanuary 23, 2026

Seattle Sound Transit Sets Launch Date for Crosslake Connection

This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.

Read More →
A blue and white graphic with a map of the proposed study area for the Sepulveda Transit Corridor and text reading "LA Metro Approves Underground Rail for Sepulveda Transit Corridor."
RailJanuary 23, 2026

LA Metro Approves Underground Rail for Sepulveda Transit Corridor

The agency’s selection aims to slash travel times from the San Fernando Valley to the Westside to under 20 minutes.

Read More →
TechnologyJanuary 21, 2026

Florida's Tri-Rail Taps Siemens Mobility for Modern Locomotive Procurement

Expected to enter service in 2029, these locomotives support the agency’s commitment to offer reliable and efficient rail transportation across South Florida.

Read More →
Ad Loading...
Rendering of an Austin Light Rail station.
RailJanuary 20, 2026

Austin Transit Partnership Advances Federal Funding Process for Light Rail Project

See how the agency’s transit project completed a Final Environmental Impact Statement within the federal two-year guideline.

Read More →