BART Silicon Valley Berryessa Extension begins revenue service

The milestone marks the culmination of the first phase of the BART Silicon Valley Extension Program that is expanding BART service into Santa Clara County.

by Staff
June 12, 2020
BART Silicon Valley Berryessa Extension begins revenue service

The $2.3 billion, 10-mile Berryessa Extension, which broke ground in April 2012, begins south of BART's Warm Springs Station in Fremont, proceeds through Milpitas, and ends in the Berryessa area of north San José.

Credit:

VTA

3 min to read


The Santa Clara Valley Transportation Authority (VTA) and Bay Area Rapid Transit District (BART) is opening the Berryessa Extension for revenue service. The milestone marks the culmination of the first phase of the BART Silicon Valley Extension Program that is expanding BART service into Santa Clara County, bringing frequent and reliable regional rail service to more than 1.7 million residents.

The $2.3 billion, 10-mile Berryessa Extension, which broke ground in April 2012, begins south of BART's Warm Springs Station in Fremont, proceeds through Milpitas, and ends in the Berryessa area of north San José. VTA funded, designed, oversaw construction, and will own the infrastructure and BART will operate the extension. The design-build project was built under the Skanska, Shimmick and Herzog (SSH) joint venture. Lockwood, Andrews & Newnam Inc. (LAN), a national planning, engineering, and program management firm, served as the lead designer under the SSH joint venture contract.

Ad Loading...

“Bringing BART service to Santa Clara County leads us into an era for Silicon Valley where we are forging new pathways for mobility,” said VTA GM/CEO Nuria Fernandez. “With this new addition to our public transit network, we look forward to many years of improved connectivity throughout our region.”

Commuters traveling on I-880 and I-680, two congested corridors that connect residential areas in Alameda, Contra Costa, and San Joaquin Counties to high-technology and other employment centers in Silicon Valley, can now use the Berryessa Extension as an alternative. By taking cars of these congested corridors, the project will help eliminate 3,500 tons of greenhouse gases every year.

Transit-oriented development opportunities have flourished around the stations. To date, near the Milpitas Station, almost 7,000 housing units, more than 10,000 square feet of office space, and over 186,000 square feet of retail space have been occupied, entitled or under construction. Similarly, adjacent to the Berryessa Station, more than 3,300 residential units have been developed to date, with plans to increase the capacity to 5,100. Plans are also underway for a high-rise hotel with up to 175 rooms.

With the opening of the two new stations, BART will have a total of 50 stations and 131 miles of track serving five Bay Area counties. The project also provides numerous intermodal options, including connections to VTA light rail and buses, Caltrain, Altamont Commuter Express, Capitol Corridor and Amtrak, Mineta San Jose International Airport, and high-speed rail.

The project improves access to employment, educational, medical, entertainment, and retail centers near the two stations. These include the Great Mall of the Bay Area, connections to employment centers such as Google, eBay and Cisco Systems, Levi’s Stadium, Berryessa Flea Market in San Jose, San Jose State University, Stanford University, and Santa Clara University.

Ad Loading...

The second phase of the BART Silicon Valley Extension, which is currently in the design stage, will extend BART service six miles from the Berryessa Transit Center into downtown San José and terminating in Santa Clara. Four stations are planned for the second phase: 28th Street/Little Portugal, Downtown San Jose, Diridon, and Santa Clara. The second phase is expected to be completed in 2030.

More Rail

A wide shot of Alstom's Multilevel III commter railcar for NJ TRANSIT
Rail•by Alex Roman•November 13, 2026

NJ TRANSIT Approves $65.6M for Hudson-Bergen Light Rail Improvements

The funding marks the first phase of a planned $250 million investment over five years to modernize stations, overhaul vehicles, and improve system reliability and passenger safety.

Read More →
STraffic's John Moon
Technology•by Alex Roman•November 12, 2026

STraffic Expands North American Presence with Fare Collection Technology

John Moon, Associate Director, Product Strategy at STraffic, discusses the company's growth in North America, its efforts to reduce fare evasion, and more.

Read More →
An aerial shot of the Denver region
Management•by Alex Roman•November 12, 2026

Study: Denver RTD Generates $2.1 Billion in Annual Economic Activity

An economic impact study finds the agency supports approximately 17,500 jobs, delivers $1.6 billion in annual community and mobility benefits, and generates $2.42 in economic value for every dollar invested.

Read More →
Ad Loading...
METRO Magazine leadership update graphic featuring a portrait of Mark Aesch, identified as administrator of the Federal Transit Administration (FTA), alongside the U.S. Department of Transportation and FTA logos on a blue gradient background.
Management•by Alex Roman•November 12, 2026

Mark Aesch Nominated to Lead Federal Transit Administration

The former Rochester transit chief and TransPro founder, who has also contributed to METRO Magazine, brings decades of industry experience and a focus on performance, accountability, and financial sustainability to the nomination.

Read More →
Transit Reaches 200 Agency Partnerships, Expands Rider Experience Tools
Technology•by Alex Roman•November 6, 2026

Transit Expands Agency Partnerships, Reaching 200 Official App Partners

COO Jake Sion discusses Transit’s growth, the success of its Transit Royale program, and how technology is helping agencies improve the rider experience.

Read More →
A rendering of Trinity Metro's future station at the Medical Center
Rail•by Alex Roman•October 30, 2026

Trinity Metro Breaks Ground on $270M TEXRail Extension

The 2.1-mile extension will connect Fort Worth’s Medical District and Near Southside to downtown, surrounding communities, and Dallas-Fort Worth International Airport.

Read More →
Ad Loading...
Austin Light Rail rendering from UT perspective
Rail•by Alex Roman•October 30, 2026

Bringing Austin’s First Light Rail System to Life

Austin Transit Partnership CEO Greg Canally discusses the city's nearly 10-mile light rail project, its collaborative approach to project delivery, the importance of community engagement, and the milestones ahead as construction approaches in 2027.

Read More →
Two Metra locomotives on rail tracks.
Rail•by Alex Roman•October 29, 2026

Metra Draft Plan Outlines Costs, Service Improvements for Regional Rail

The Systemwide Network Plan identifies infrastructure needs and potential investments to expand all-day, bidirectional rail service across the Chicago region.

Read More →
METRO Magazine graphic featuring railroad tracks and switches inside a dark tunnel with the headline “Amtrak Completes First Street Tunnel Upgrades, Restores Service.”
Rail•by Elora Haynes•October 29, 2026

Amtrak Completes First Street Tunnel Upgrades, Restores Service

The nine-day construction project included replacing aging track infrastructure and modernizing switch systems near Washington Union Station.

Read More →
Ad Loading...
FRA Invests $2.3B in Rail Projects Nationwide
Rail•by Alex Roman•October 28, 2026

FRA Announces $2.3B for Passenger, Freight Rail Projects Nationwide

The CRISI Grant Program funding will support rail infrastructure improvements, safety upgrades, and projects aimed at improving freight and passenger rail service across 45 states and Washington, D.C.

Read More →