BART tests first airport connector vehicle

The test vehicle is the first of four that will travel along the 3.2 mile track, or guideway, between BART’s Oakland Airport/Coliseum Station and a new station next to the terminals at Oakland International Airport.

January 23, 2014
2 min to read


Test vehicles will soon travel on the Oakland Airport Connector (OAC) tracks as the Bay Area Rapid Transit District's (BART) project moves into one of the final phases before the anticipated opening for service this fall.

The first of the new test vehicles was unveiled on Tuesday at the OAC wheelhouse, the hub where 12-foot motorized wheels pull the cables that provide traction for the driverless vehicles.

“Passenger travel on the elevated guideway between Coliseum BART and the Oakland Airport Station is now less than a year away,” said BART Director Robert Raburn. “I’m heartened that the Oakland Airport Connector will boost development in Oakland and the fact that the project has already put local people to work.”



The test vehicle is the first of four that will travel along the 3.2 mile track, or guideway, between BART’s Oakland Airport/Coliseum Station and a new station next to the terminals at Oakland International Airport. The vehicles are being constructed in Oregon and shipped to the San Francisco Bay Area for final assembly on site. All are expected to be in testing this spring.

Once OAC opens to the public, trains will complete the trip in just eight minutes, 30 seconds. Total travel time, which includes walking from the BART Coliseum Station to the OAC platform and from OAC to the airport terminals, is expected to take 12 minutes to 14 minutes.

The OAC will replace the current AirBART buses, which drive through nine intersections on local streets and take 20 minutes to 25 minutes in ideal traffic conditions.

Fares for OAC have not yet been determined but are anticipated to be roughly equivalent to the $3 AirBART fare with the added advantage of allowing Clipper card holders to simply swipe their cards to pay.

The total cost of the project is $484 million and it is on time and on budget, according to BART. The project’s local hiring program is exceeding its goals, with 934 of the 1,508 on site workers being local area residents, 271 of whom are from Oakland.

More Rail

A New York MTA subway car with an open gangway
Railby Staff and News ReportsSeptember 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →
A San Diego MTS Copper Line vehicle
Railby Staff and News ReportsSeptember 15, 2026

San Diego MTS Breaks Monthly Trolley Ridership Record

Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.

Read More →
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Railby Alex RomanSeptember 14, 2026

Report Examines NJ TRANSIT Reliability, Funding Challenges

The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.

Read More →
Ad Loading...
A CapMetro commuter rail train provided by Stadler
Railby Staff and News ReportsSeptember 11, 2026

Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement

Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.

Read More →
Rendering of an Alstom train in a VIA Rail Station
Technologyby Alex RomanSeptember 10, 2026

Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More

In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.

Read More →
The CATS Gold Line in service with the city skyline in the background.
Railby Staff and News ReportsSeptember 3, 2026

CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips

With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Amtrak Sunnyside Groundbreaking
Railby Staff and News ReportsSeptember 2, 2026

Amtrak Begins Major Construction at New York’s Sunnyside Yard

The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.

Read More →
O'Hare Flyer Rendering
Railby Staff and News ReportsAugust 27, 2026

Chicago Leaders Unveil Plans for O’Hare Airport Express Train

The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.

Read More →
Ad Loading...
An OCTA coastal rail line train.
Railby Staff and News ReportsAugust 27, 2026

OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor

The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.

Read More →