Bombardier to supply signaling to London Underground
The contract is valued at approximately $577 million. Bombardier will equip 192 miles of track line (25 miles in tunnels), 113 stations, 191 trainsets, 49 engineering trains and six heritage trains by 2018, using its communication-based train control technology, CITYFLO 650.
Bombardier Transportation has been awarded the major contract for the Sub Surface Railway (SSR) automatic train control (ATC) signaling upgrade for London Underground in the U.K. The contract, valued at approximately $577 million, is a part of London Underground's SSR Upgrade Programme (SUP).
Bombardier will provide the proven CITYFLO 650 ATC system, its innovative communication-based train control (CBTC) technology, similar to that running successfully on the Metro de Madrid in Spain.
The full scope of the contract is for the signaling renewal and provision of an ATC system for the four sub-surface lines (Metropolitan, District, Circle, Hammersmith & City) of the London Underground network. Carrying 1.3 million passengers a day, the lines comprise 40 percent of the network and carry 25 percent of the total ridership.
Bombardier will equip the 192 miles of track line (25 miles in tunnels), 113 stations, 191 trainsets, 49 engineering trains and six heritage trains by 2018, followed by a two-year warranty period. The main project office will be in London, with Bombardier sites in Bangkok, Helsinki, Madrid, Pittsburgh, Plymouth, Derby and Reading providing much of the product supply and associated engineering works. Bombardier will equip the existing and new SSR vehicles in line with the new contract.
CITYFLO 650 is a highly proven Bombardier ATC solution operating successfully around the world on 13 lines in North America, Europe and Asia. It is a moving block, CBTC system utilizing modern radio-based wide area networks to communicate between the control center and the train.
In addition to the possibility of being installed without interruption to service and adhering to tight timelines, CITYFLO 650 can provide interoperability with legacy train control systems and can be adapted to accommodate country requirements. This advanced solution leads to improved safety, higher capacity and reliability, shorter headways between trains and reduced maintenance costs.
More Rail

Amtrak Finalizes Pre-Development Agreement for Penn Station Overhaul
The agreement advances plans for a $7 billion to $8 billion transformation of New York's busiest transit hub, with construction expected to begin by the end of 2027.
Read More →
New York MTA Leverages Zoning Program to Advance Station Accessibility
Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.
Read More →
Virginia's $28.5B Transportation Plan Targets Transit and Rail
Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.
Read More →
DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades
Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.
Read More →
D Line Expansion Fuels Growth Across LA Metro's Rail System
Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.
Read More →
Southern California's Metrolink Debuts Contactless Fare Payment Pilot
Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.
Read More →
California's BART Approves FY27 Budget While Maintaining Service Levels
The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.
Read More →
Penn Station Transformation Advances with Design Unveiling
The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.
Read More →
Second Avenue Subway Phase 2 Advances into Major Construction Stage
New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.
Read More →
The Invisible Infrastructure of Passenger Flow
What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.
Read More →