METRO Magazine Logo
MenuMENU
SearchSEARCH

California's SacRT Enters Final Light Rail Testing Phase

During this phase of testing, the new low-floor trains will simulate real-world scenarios, actively pulling into stations, deploying ramps, opening and closing doors, and proceeding to the next station.

December 8, 2023
California's SacRT Enters Final Light Rail Testing Phase

The burn-in testing is expected to take approximately two weeks per train. The thorough process allows SacRT staff to identify and address any issues before the trains are approved for passenger service.

Photo: SacRT

2 min to read


The California Sacramento Regional Transit District (SacRT) announced a significant milestone in the Light Rail Modernization Project as its new low-floor trains entered the final testing phase, bringing the region one step closer to an enhanced and more accessible public transit system.

SacRT began the “burn-in” testing phase on December 7. Testing is being conducted systemwide on the Blue, Green, and Gold Lines from 8 p.m. to 4 a.m., Monday through Friday. The schedule is designed to minimize any impact on regular light rail service.

Ad Loading...

Phased Testing of Light Rail

During this phase of testing, the new low-floor trains will simulate real-world scenarios, actively pulling into stations, deploying ramps, opening and closing doors, and proceeding to the next station. To distinguish these trains from regular service trains, prominent “Test Train” decals are on doors and windows to prevent customers from accidentally boarding.

The burn-in testing is expected to take approximately two weeks per train. The thorough process allows SacRT staff to identify and address any issues before the trains are approved for passenger service.

The testing process is projected to continue through spring 2024 for the first 20 low-floor trains in anticipation of starting passenger service with the new trains on the Gold Line in summer 2024.

SacRT’s New Low-Floor Light Rail Trains

The new low-floor vehicles will provide easier access at every doorway, a spacious seating design, and large windows for better light and views. They feature improved accessibility with wider aisles. 

The new low-floor vehicles will increase overall operational flexibility by providing more access to passengers with disabilities.

Ad Loading...

SacRT is modernizing the light rail system to make future travel easier, safer, and more convenient for riders. The project includes the purchasing of new low-floor trains, reconfiguring station platforms to accommodate the new trains and adding a passing track to allow for 15-minute light rail service at all Folsom area stations.

More Rail

A New York MTA subway car with an open gangway
Railby Staff and News ReportsSeptember 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →
A San Diego MTS Copper Line vehicle
Railby Staff and News ReportsSeptember 15, 2026

San Diego MTS Breaks Monthly Trolley Ridership Record

Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.

Read More →
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Railby Alex RomanSeptember 14, 2026

Report Examines NJ TRANSIT Reliability, Funding Challenges

The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.

Read More →
Ad Loading...
A CapMetro commuter rail train provided by Stadler
Railby Staff and News ReportsSeptember 11, 2026

Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement

Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.

Read More →
Rendering of an Alstom train in a VIA Rail Station
Technologyby Alex RomanSeptember 10, 2026

Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More

In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.

Read More →
The CATS Gold Line in service with the city skyline in the background.
Railby Staff and News ReportsSeptember 3, 2026

CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips

With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Amtrak Sunnyside Groundbreaking
Railby Staff and News ReportsSeptember 2, 2026

Amtrak Begins Major Construction at New York’s Sunnyside Yard

The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.

Read More →
O'Hare Flyer Rendering
Railby Staff and News ReportsAugust 27, 2026

Chicago Leaders Unveil Plans for O’Hare Airport Express Train

The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.

Read More →
Ad Loading...
An OCTA coastal rail line train.
Railby Staff and News ReportsAugust 27, 2026

OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor

The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.

Read More →