CHSRA Issues Forceful Rebuttal to FRA’s Proposed Funding Termination

In a 14-page letter addressed to FRA Acting Administrator Drew Feeley, Choudri defended the project’s progress and sharply criticized what he described as the FRA’s “unfounded,” “misleading,” and “disingenuous” assertions.

CHSRA Issues Forceful Rebuttal to FRA’s Proposed Funding Termination

Among the significant points of contention is the FRA’s suggestion that the authority has made “minimal progress” on the project. “The authority’s work has already reshaped the Central Valley,” Choudri wrote, citing significant achievements including:

Photo: CHSRA

3 min to read


California High-Speed Rail Authority (CHSRA) CEO Ian Choudri issued a sharp and comprehensive rebuttal to the Federal Railroad Administration’s (FRA) proposed termination of two key cooperative funding agreements. 

In a 14-page letter addressed to FRA Acting Administrator Drew Feeley, Choudri defended the project’s progress and sharply criticized what he described as the FRA’s “unfounded,” “misleading,” and “disingenuous” assertions.

Ad Loading...

“Termination of the Cooperative Agreements is unwarranted and unjustified,” Choudri stated. “FRA’s conclusions are based on an inaccurate, often outright-misleading, presentation of the evidence.”

CHSRA Disputes FRA Claims Point-by-Point

In the detailed response, Choudri methodically refutes the FRA’s primary findings, rejecting claims that the authority has made minimal construction progress or lacks a clear funding strategy. He argued that the FRA mischaracterized data, misrepresented supporting documentation, and used opaque review methodologies that do not align with the FRA’s previous assessments.

Among the significant points of contention is the FRA’s suggestion that the authority has made “minimal progress” on the project. “The authority’s work has already reshaped the Central Valley,” Choudri wrote, citing significant achievements including:

  • Completion of the 4,741-foot San Joaquin River Viaduct in Fresno.

  • Completion of the Hanford Viaduct, the longest high-speed rail structure in the Central Valley.

  • A railyard is currently under construction to support materials and logistics.

  • A total of 53 structures and 69 miles of guideway have been completed.

Choudri noted that more than 1,700 workers are engaged in daily field construction, primarily in Fresno, Kings, and Tulare counties.

Ad Loading...

“These are momentous achievements,” he said. “Combining feats of engineering, complex logistical and legal coordination, and a daily workforce in the thousands.”

Addressing the Funding Gap

The authority also challenged the FRA’s concerns regarding a projected $7 billion funding shortfall. 

Choudri pointed to Gov. Gavin Newsom’s proposal to extend the state’s Cap-and-Trade program, rebranded as Cap-and-Invest, which could provide an estimated $1 billion annually through 2045. The letter also previewed a forthcoming Request for Expressions of Interest (RFEI) from private sector partners to explore innovative cost and delivery solutions.

Choudri emphasized that the authority aggressively pursues funding and partnership opportunities, contrary to the FRA’s suggestions.

CHSRA’s response also questioned the integrity and consistency of the FRA’s review process. 

Ad Loading...

Choudri cited an October 2024 FRA monitoring report that found no major compliance issues, calling the agency’s current position a “dramatic about-face.”

“There have been no meaningful changes in the past eight months that justify FRA’s reversal,” he wrote. “Hostility to public investments in high-speed rail, and to California’s leadership, appears to be the real basis for the proposed determination.”

The letter highlighted the FRA’s attempt in 2019 to revoke funding, framing the current move as part of a longer-term pattern of federal skepticism toward California’s high-speed rail ambitions.

Project Milestones and Economic Impact

The authority also reaffirmed that environmental clearance is complete for the full Phase 1 system between downtown San Francisco and downtown Los Angeles. Electrification of the Caltrain corridor between San Francisco and San Jose has also been completed.

Currently, 171 miles of the high-speed rail corridor from Merced to Bakersfield are under active design and construction. In total, nearly 70 miles of guideway have been built, with 54 structures completed and 30 more under construction. According to the CHSRA, the project has also created over 15,300 construction jobs to date, most of which have gone to Central Valley residents.

Ad Loading...

Choudri concluded the letter with a call for collaboration rather than conflict.

“I hope that FRA and the authority can move forward to support this program, a project with a big future and great promise to better the lives of Californians and spur economic growth in the state and across the nation,” he wrote.

As the future of federal funding hangs in the balance, CHSRA said it is continuing work on its ambitious vision to connect Northern and Southern California with clean, high-speed electric rail, reaffirming its commitment to transparency, public benefit, and transformative infrastructure.

More Rail

Graphic from Amtrak promoting the B&P Tunnel Replacement and Frederick Douglass Tunnel project, featuring the Amtrak logo, project title and an illustration of a high-speed train near the West Baltimore MARC Station.
Railby News/Media ReleaseMarch 17, 2026

Amtrak Announces Community Grants for Projects Near Baltimore’s New Frederick Douglass Tunnel

Amtrak will open grant applications March 23 for community projects near the Frederick Douglass Tunnel alignment in Baltimore as part of a $50 million investment tied to the B&P Tunnel Replacement Program.

Read More →
Amtrak train with logo
Railby StaffMarch 16, 2026

Amtrak Marks Restoration of Two South Carolina Stations

The Denmark Station $2.3 million construction investment project includes a new 280-foot concrete boarding platform, built eight inches above the top of rail, for improved accessibility for passengers with disabilities and families with small children and much more.

Read More →
A view looking down the rail across the new Portal North Bridge.
Railby Staff and News ReportsMarch 13, 2026

NJ Transit, Amtrak Prepare to Open First Track on New Portal North Bridge

The new bridge will begin carrying passenger trains on March 16, replacing a 116-year-old swing bridge that has long caused delays.

Read More →
Ad Loading...
Caltrain trains on tracks
Railby StaffMarch 6, 2026

Caltrain Adopts Corridor-Wide Right-of-Way Safety Strategy

Caltrain and its partners have implemented safety improvements at specific locations in response to known risk conditions, operational needs, and available funding since the agency’s founding.

Read More →
A photo of rail tracks in Ottawa, Canada

Building a National Framework for Transit Safety and Consistency

On a recent episode of METROspectives, METRO Magazine’s Executive Editor Alex Roman sat down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the CSA Group, to explore a bold initiative aimed at addressing those challenges: the development of a National Code for Transit and Passenger Rail Systems in Canada.

Read More →
Stairs in a New York rail station with text reading "USDOT Invests $686 Million to Modernize Aging Rail Stations."
Railby StaffMarch 2, 2026

FTA Invests $686M to Modernize Aging Rail Stations

Competitive FTA grants will support accessibility upgrades, family-friendly improvements, and cost-efficient capital projects at some of the nation’s oldest and busiest transit hubs.

Read More →
Ad Loading...
A purple MBTA train at a Mansfield Station platform.
Railby StaffFebruary 27, 2026

MBTA Updates Rail Modernization Plan to Expand Reliability and Accessibility

The strategy outlines near- and long-term upgrades to ease congestion, support housing growth, and advance statewide climate goals.

Read More →
LA Metro underground station with vehicle
Railby StaffFebruary 27, 2026

LA Metro Sets D Line Subway Extension Launch Date

The 3.92-mile addition will soon take riders west beyond its current Wilshire and Western station in Koreatown, continuing under Wilshire Boulevard through neighborhoods and communities including Hancock Park, Windsor Square, the Fairfax District, and Carthay Circle into Beverly Hills.

Read More →
MBTA railcars
Railby StaffFebruary 26, 2026

Boston's MBTA Marks Progress in Regional Rail Modernization

The procurement advances the agency's broader efforts to modernize its rail fleet and position Regional Rail for long-term improvement.

Read More →
Ad Loading...
An Amtrak Acela
Railby StaffFebruary 26, 2026

Amtrak Sets New Course for Long-Distance Fleet Renewal

Under the plan, all long-distance routes will transition to a universal single-level fleet, replacing today’s mix of bi-level and single-level equipment.

Read More →