The Federal Transit Administration approved the Los Angeles County Metropolitan Transportation Authority’s (Metro) request to be reimbursed for early work activities for Section Three of the Purple Line Extension Project between Century City and the Westwood/VA Hospital.
The approval also clears the way for Metro to take advantage of highly competitive tunnel contract bids, which have come in lower than expected and would save the project an estimated $130 million. These tunneling bids were at risk to expire on Oct. 3, 2018. Additionally, the FTA’s approval avoids the need to rebid the tunnel contract, saving an additional $200 million in projected escalation costs and nearly two years of project delay.
Ad Loading...
The “Letter of No Prejudice” (LONP) permits the agency to incur costs on a project using non-federal resources with the understanding that the costs incurred after the letter’s approval may be reimbursable to Metro if the project is chosen for federal funding later. The LONP will take effect upon FTA’s final review of technical refinements to the project, which are being finalized by Metro. Metro will then issue a Notice to Proceed to the contractor, Frontier-Kemper/Tutor Perini Joint Venture, which has agreed to extend its bid price to Dec. 3, 2018 to accommodate FTA’s final environmental review.
FTA’s actions mark an important step in the path to ultimately secure a Full Funding Grant Agreement for the Purple Line Extension Section Three. In August, Section Three was cleared to enter the engineering phase of the FTA Capital Investment Grants Program. Two earlier subway extension sections have already received federal funding. Metro is now seeking a $1.3-billion grant for Section Three through the FTA’s New Starts Program and anticipates a grant agreement will be forthcoming in early 2019.
Overall, Metro’s revised Letter of No Prejudice, submitted to the FTA on August 30, reduced the agency’s ask from $786 million for early work activities to $492 million based on favorable tunneling contract bids and other project efficiencies.
The Purple Line Extension’s first two sections are under construction between Wilshire/Western and Century City. When all three sections are complete, the subway extension will travel approximately nine miles underground between Koreatown and Westwood. Major construction of the first section between Koreatown and Beverly Hills began in 2015.
“Thanks to L.A. County taxpayers, we already have the local dollars we need to pay the lion’s share of this regionally significant mega-project,” said Metro CEO Phillip A. Washington. “Working closely with the FTA, we can leverage our significant local investment with the precious resources of the federal government to deliver one of the most competitive and beneficial public transit projects in America today.”
Ad Loading...
Construction of the second section between Beverly Hills and Century City started in 2017. Section Three, scheduled to begin construction in 2019, will complete the subway to Westwood. The entire line is on track to open by 2026, in time for the 2028 L.A. Olympic and Paralympic Games in Los Angeles.
Operation Lifesaver awarded $220,200 in grants to 12 states to support rail safety campaigns focused on grade crossing awareness and trespass prevention.
The survey showed that commute trips still make up the majority of ridership, with most riders boarding 2 to 3 days a week, reflecting hybrid work schedules. Two-thirds of Caltrain riders have access to a car, while 37% of Caltrain riders are considered low-income.
Advances in data and analytics are giving transit agencies new opportunities to refine maintenance practices, improve efficiency and make more informed decisions about asset performance.
In this Consultant Roundtable, Carmen C. Cham shares insights on how agencies can create spaces that are intuitive, connected and built for long-term impact.
The Red Line Extension Project will provide the Far South Side of Chicago with rapid rail transit for the first time by extending the Red Line by 5.5 miles from 95th Street to 130th Street, including the construction of four new Red Line stations at 103rd, 111th, Michigan, and 130th streets.
The Siemens CBTC System, Trainguard MT, in compliance with New York Subway Interoperability Interface Specifications, enables trains to run as close as 90 seconds apart, using next-generation signaling and continuous communication to keep operations moving seamlessly.
While recognizing regional economic constraints and continuing to improve service, the budget increases the jurisdictional subsidy to less than 1.8%, significantly below the inflation rate and the 3% regional target, said agency officials.
With more than 59,400,000 boardings since the service’s debut, the A Line’s utilization surpassed that of all other RTD rail services in 2025, the agency reported.
The plan outlines funding for transit operations, capital projects, and freight and passenger rail initiatives, as state officials seek public input on priorities shaping mobility and infrastructure across the Commonwealth.