METRO Magazine Logo
MenuMENU
SearchSEARCH

FTA to reimburse L.A. Metro for early work on Purple Line extension

The approval also clears the way for Metro to take advantage of highly competitive tunnel contract bids, which have come in lower than expected.

September 24, 2018
FTA to reimburse L.A. Metro for early work on Purple Line extension

 

3 min to read


The Federal Transit Administration approved the Los Angeles County Metropolitan Transportation Authority’s (Metro) request to be reimbursed for early work activities for Section Three of the Purple Line Extension Project between Century City and the Westwood/VA Hospital.

The approval also clears the way for Metro to take advantage of highly competitive tunnel contract bids, which have come in lower than expected and would save the project an estimated $130 million. These tunneling bids were at risk to expire on Oct. 3, 2018. Additionally, the FTA’s approval avoids the need to rebid the tunnel contract, saving an additional $200 million in projected escalation costs and nearly two years of project delay.

Ad Loading...

The “Letter of No Prejudice” (LONP) permits the agency to incur costs on a project using non-federal resources with the understanding that the costs incurred after the letter’s approval may be reimbursable to Metro if the project is chosen for federal funding later. The LONP will take effect upon FTA’s final review of technical refinements to the project, which are being finalized by Metro. Metro will then issue a Notice to Proceed to the contractor, Frontier-Kemper/Tutor Perini Joint Venture, which has agreed to extend its bid price to Dec. 3, 2018 to accommodate FTA’s final environmental review.

FTA’s actions mark an important step in the path to ultimately secure a Full Funding Grant Agreement for the Purple Line Extension Section Three. In August, Section Three was cleared to enter the engineering phase of the FTA Capital Investment Grants Program. Two earlier subway extension sections have already received federal funding. Metro is now seeking a $1.3-billion grant for Section Three through the FTA’s New Starts Program and anticipates a grant agreement will be forthcoming in early 2019.

Overall, Metro’s revised Letter of No Prejudice, submitted to the FTA on August 30, reduced the agency’s ask from $786 million for early work activities to $492 million based on favorable tunneling contract bids and other project efficiencies.

The Purple Line Extension’s first two sections are under construction between Wilshire/Western and Century City. When all three sections are complete, the subway extension will travel approximately nine miles underground between Koreatown and Westwood. Major construction of the first section between Koreatown and Beverly Hills began in 2015.

“Thanks to L.A. County taxpayers, we already have the local dollars we need to pay the lion’s share of this regionally significant mega-project,” said Metro CEO Phillip A. Washington. “Working closely with the FTA, we can leverage our significant local investment with the precious resources of the federal government to deliver one of the most competitive and beneficial public transit projects in America today.”

Ad Loading...

Construction of the second section between Beverly Hills and Century City started in 2017. Section Three, scheduled to begin construction in 2019, will complete the subway to Westwood. The entire line is on track to open by 2026, in time for the 2028 L.A. Olympic and Paralympic Games in Los Angeles.

More Rail

A picture of a San Diego MTS railcar and bus at a transit station.
Managementby StaffApril 17, 2026

San Diego Transit Agencies Propose Fare Hike to Close Budget Gaps

The agencies, San Diego MTS and NCTD - San Diego Railroad, which share a fare system (PRONTO), proposed the changes to help address their respective financial sustainability strategies.

Read More →
An overhead rendering of the Austin Transit Partnership rail system.
Railby StaffApril 16, 2026

Austin Transit Partnership Names Contractor for Light Rail Operations Facility

The ATP board’s approval of the KAP team enables ATP to begin pre-construction activities, including advancing design, initiating permitting, and preparing the site for future construction.

Read More →
A Coach USA Van Hool CX 45 delivered by ABC Companies.
Busby StaffApril 15, 2026

ABC Delivers Van Hools to Coach USA and More in Biz Briefs

In METRO's latest installment, we take a look at the latest news from suppliers including Moovit, CAF, and more.

Read More →
Ad Loading...
A photo of an Amtrak train with a logo
Technologyby StaffApril 15, 2026

Amtrak Advances Plan for New Long-Distance Fleet

The railroad has issued a formal request for proposals to manufacturers for more than 800 new passenger railcars that will serve 14 long-distance routes nationwide.

Read More →
A headshot of Inez Evans Benson
Busby Alex RomanApril 15, 2026

Inez Evans Benson on Rethinking Transit Through Customer Experience

The WSP leader discusses why agencies must look beyond satisfaction metrics and take a more holistic, community-driven approach to service.

Read More →
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Technologyby StaffApril 14, 2026

Alstom Delivers First Multilevel III NJ TRANSIT Commuter Railcar

The delivery marks the first car in a 374‑vehicle order and begins the arrival of a new generation of higher‑capacity, more reliable, and more comfortable trains for one of the country’s busiest commuter rail systems.

Read More →
Ad Loading...
A BART train on the tracks.
Railby StaffApril 13, 2026

San Francisco's BART Breaks Multiple Records for Post-Pandemic Ridership in March

BART recorded 5,403,140 exits in March, making it the highest monthly ridership since the pandemic and surpassing the previous high set in October 2025 (5,346,890 exits).

Read More →
Ribbon cutting photo celebrating SEPTA's new Ardmore Station
Railby StaffApril 13, 2026

Philadelphia's SEPTA Celebrates New Ardmore Station

The station was rebuilt as part of SEPTA’s Station Accessibility Program, making it fully ADA accessible with new elevators, ramps, and high-level platforms.

Read More →
Two Metra locomotives on rail tracks.
Railby StaffApril 10, 2026

Metra Reaches New 10-Year Agreement with BNSF

The announcement highlights the long-standing partnership between the Class I railroad and the commuter rail system, dating back to Metra's creation in 1983.

Read More →
Ad Loading...
Ribbon cutting at Siemens' new North Carolina facility.
Railby StaffApril 9, 2026

Siemens Opens North Carolina Railcar Manufacturing Facility

Site construction is complete, production is underway, and the first locally built passenger coaches are on track for delivery in Summer 2026.

Read More →