LA Metro Completes 5 Years of Tunneling on D Line Subway Extension

The major construction milestone was accomplished safely in one of the densest and most geologically challenging urban corridors in the L.A. region and nation.

April 3, 2024
LA Metro Completes 5 Years of Tunneling on D Line Subway Extension

Contractors utilized the latest Tunnel Boring Machine technology to excavate approximately 40 to 60 feet per day to help complete tunneling for the project.

Photo: LA Metro

2 min to read


The Los Angeles County Metropolitan Transportation Authority (Metro) completed tunneling for the D Line Subway Extension Project, which will connect downtown L.A. with West L.A.

The major construction milestone was accomplished safely in one of the densest and most geologically challenging urban corridors in the L.A. region and nation.

Ad Loading...

D Line Tunnel Boring

With the completion of tunneling, Metro will continue to work with its two contractors as a part of a joint venture with Skanska-Traylor-Shea and Tutor-Perini/O&G to complete seven new underground stations in Section 1 between Wilshire/Western and Wilshire/La Cienega, Section 2 between Wilshire/La Cienega and Century City, and Section 3 between Century City and Westwood.

Contractors utilized the latest Tunnel Boring Machine (TBM) technology to excavate approximately 40 to 60 feet per day to help complete tunneling for the project. The 400 foot-long, 21 foot-diameter earth digging machines utilized closed face, pressurized TBM technology that minimizes ground settlement during excavation.

The machines also lined the tunnel itself with precast concrete segments that were bolted together to form secure rings making them water- and gas-tight, preventing water and gas-related risks. The same TBM technology was successfully employed on Metro’s 2009 Eastside Extension Project.

The 400 foot-long, 21 foot-diameter earth digging machines utilized closed face, pressurized TBM technology that minimizes ground settlement during excavation.

Photo: LA Metro

Making It to The Historic Milestone

During its five years of tunneling, Metro faced and successfully overcame many technical challenges like gassy ground, tar sands, and abandoned oil wells. Near the La Brea Tarpits, for example, Metro’s advanced TBMs made their way through tar sands, and used horizontal directional drillings to probe the earth so contractors could identify and remove potential objects before any TBM damage occurred.

Metro also safely used the same methods to identify and avoid unmapped and abandoned oil wells underneath Beverly Hills High School.

Ad Loading...

"The end of tunneling work on this project is a triumph of engineering, planning and execution. Our construction team undertook a painstaking process that helped us keep everyone in these communities safe and deliver a better project for the people of L.A. County," said Stephanie Wiggins, Metro CEO. "We have proven yet again our capability to safely tunnel underneath a range of different structures as well as sensitive and historic sites."

Forecasted openings are 2025 for Section 1, 2026 for Section 2, and 2027 for Section 3 of the project.

Metro secured local funding to build the project via the 2008 Measure R and 2016 Measure M voter-approved transportation sales tax measures. These local funding sources were then matched by federal funding, which ultimately amounted to approximately half of the project’s overall cost.

More Rail

Operation Lifesaver Rail Safety Education logo over railroad tracks background, representing rail safety awareness initiatives.
Railby News/Media ReleaseMay 4, 2026

Operation Lifesaver Awards Rail Safety Outreach Funds in 12 States

Operation Lifesaver awarded $220,200 in grants to 12 states to support rail safety campaigns focused on grade crossing awareness and trespass prevention.

Read More →
Caltrain trains on tracks
Railby StaffMay 1, 2026

Caltrain Survey Shows Record-High Rider Approval

The survey showed that commute trips still make up the majority of ridership, with most riders boarding 2 to 3 days a week, reflecting hybrid work schedules. Two-thirds of Caltrain riders have access to a car, while 37% of Caltrain riders are considered low-income.

Read More →
A person working on a bus
ManagementMay 1, 2026

Data-Driven Maintenance: Focusing Effort Where It Matters Most

Advances in data and analytics are giving transit agencies new opportunities to refine maintenance practices, improve efficiency and make more informed decisions about asset performance.

Read More →
Ad Loading...
Carmen C. Cham of HNTB
Managementby Alex RomanApril 29, 2026

How Transit Architecture Is Reshaping the Rider Journey

In this Consultant Roundtable, Carmen C. Cham shares insights on how agencies can create spaces that are intuitive, connected and built for long-term impact.

Read More →
A Red Line Rendering
Railby StaffApril 27, 2026

Chicago Kicks Off Historic Red Line Extension at Michigan Avenue Station Site

The Red Line Extension Project will provide the Far South Side of Chicago with rapid rail transit for the first time by extending the Red Line by 5.5 miles from 95th Street to 130th Street, including the construction of four new Red Line stations at 103rd, 111th, Michigan, and 130th streets.

Read More →
Trains at railroad crossings
Security and Safetyby StaffApril 27, 2026

USDOT Invests $1.1B to Enhance Safety Infrastructure at Railroad Crossings

Every year, more than 2,000 incidents and 300 fatalities occur at railroad crossings nationwide. 

Read More →
Ad Loading...
Siemens and LK Comstock photo for Fulton-Liberty Lines
Security and Safetyby StaffApril 27, 2026

NYC’s Fulton–Liberty Lines Get Digital Signal Upgrade from Siemens and L.K. Comstock

The Siemens CBTC System, Trainguard MT, in compliance with New York Subway Interoperability Interface Specifications, enables trains to run as close as 90 seconds apart, using next-generation signaling and continuous communication to keep operations moving seamlessly.

Read More →
WMATA 7000-series railcars at Navy Yard
Managementby StaffApril 24, 2026

WMATA Adopts FY2027 Budget, Boosts Service Without Raising Fares

While recognizing regional economic constraints and continuing to improve service, the budget increases the jurisdictional subsidy to less than 1.8%, significantly below the inflation rate and the 3% regional target, said agency officials.

Read More →
Denver RTD's A Line with passengers
Railby StaffApril 23, 2026

Denver's RTD Celebrates 10th Anniversary of the A Line

With more than 59,400,000 boardings since the service’s debut, the A Line’s utilization surpassed that of all other RTD rail services in 2025, the agency reported.

Read More →
Ad Loading...
Passengers on a public transit vehicle.
Railby StaffApril 21, 2026

Virginia DRPT Releases Draft Six-Year Program for Transit, Rail Investments

The plan outlines funding for transit operations, capital projects, and freight and passenger rail initiatives, as state officials seek public input on priorities shaping mobility and infrastructure across the Commonwealth.

Read More →