LIRR double-track project close to complete

The project utilizes Design-Build construction and a specialized New Track Construction machine that lays rail more than 10 times faster than the MTA has ever done before, saving more than $7 million in construction costs.

January 17, 2018
LIRR double-track project close to complete

The new Double Track will enable the LIRR to provide more frequent off-peak service to the Ronkonkoma Branch in both directions, with off-peak service going from one train every hour to one train every 30 minutes in both directions.

MTA

4 min to read


The new Double Track will enable the LIRR to provide more frequent off-peak service to the Ronkonkoma Branch in both directions, with off-peak service going from one train every hour to one train every 30 minutes in both directions. MTA

New York Gov. Andrew M. Cuomo announced the Long Island Rail Road (LIRR) Double Track reached a major milestone and the final five miles of rail being laid this month. The project utilizes Design-Build construction and a specialized New Track Construction machine that lays rail more than 10 times faster than the MTA has ever done before, saving more than $7 million in construction costs and allowing for an expected project completion of August 2018 — 16 months ahead of schedule. Once complete, the Double Track, extending from Farmingdale to Ronkonkoma, will dramatically reduce delays on the LIRR and enable more off-peak service in both directions by adding nearly 13 miles of parallel track.

While touring the Double Track, Gov. Cuomo also announced 24 LIRR projects totaling $1 billion — including the $121 million Hicksville Station Transformation and the new Wyandanch Station — will be completed in 2018. Twenty-one additional LIRR projects will break ground this year, including the $2 billion LIRR Expansion Project that will add a third track to 9.8 miles along the congested Main Line of the LIRR between Floral Park and Hicksville. Together, these projects significantly advance the Governor's $6.6 billion transformation and modernization of the Long Island commuter rail and $100 billion Infrastructure and Development Plan for New York.

Ad Loading...

"By pairing design-build contracting with the use of innovative track-laying equipment, we are building a more robust infrastructure faster and at less expense to New Yorkers,” said Gov. Cuomo. “This project, along with the 23 other commuter line projects we will complete this year, will ensure LIRR remains the backbone of the region's economy."

Double Track

The $387.2 million Double Track project, which is bringing a second track to single-track territory, has provided hundreds of construction jobs and, upon completion, will improve service and reliability on the LIRR's Ronkonkoma Branch, while spurring economic activity, and improving LIRR service to Long Island MacArthur Airport. Over the past 25 years, ridership on the Ronkonkoma Branch has doubled — growing in popularity since the line was electrified in 1988.

With just one track along most of the 18-mile route between Farmingdale and Ronkonkoma, the LIRR can operate only a limited number of trains and lacks operational flexibility in the event of a disruption. If one train becomes disabled, all other trains — coming from both east and west — have no way around the problem.

The new Double Track will enable the LIRR to provide more frequent off-peak service to the Ronkonkoma Branch in both directions, with off-peak service going from one train every hour to one train every 30 minutes in both directions. The project will reduce delays associated with service disruptions for the 48,000 weekday riders on the Ronkonkoma Line by giving the railroad flexibility to go around obstacles that it cannot currently in single-track territory.

Ad Loading...

The project has taken place over two phases. Phase One used the New Track Construction machine to lay the first 3.5 miles of new track between Central Islip and Ronkonkoma, and was completed in August 2016. Phase Two includes laying the rest of the track between Farmingdale and Central Islip. Over the next several months, crews will continue construction that includes stone ballast, tamping, surfacing, and installation of the third rail and new signal system.

New Track Construction Machine

The Double Track project marks the MTA's first-ever use of the New Track Construction machine, which is capable of laying one mile of track per day — more than ten times faster than the 500 feet of track per day that the MTA manually laid previously. By speeding up this process, the MTA is significantly improving productivity, increasing safety and reducing the potential of construction disruption to local communities.

The machine is pulled from the front end by a bulldozer along the route of the new track. It automatically handles the flow of materials, negating the use of overhead cranes for track construction. The machine's ability to bring in supplies by rail negates the need for trucking supplies in. The MTA plans to use the machine in future projects in response to the Governor's challenge to increase efficiency in its projects.

More Rail

Railby StaffFebruary 2, 2026

Chicago Region Transit Ridership Grows in 2025

The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.

Read More →
Managementby StaffJanuary 29, 2026

Valley Metro Sees Strong Ridership Growth in 2025

The agency ranked top five among mid-sized U.S. transit systems, defined as agencies with 15 million to 50 million annual trips.

Read More →
Busby StaffJanuary 29, 2026

Subway Customer Satisfaction Reaches Record High, New York MTA Says

The subway system saw increases across all key metrics, with 62% of subway riders reporting they feel satisfied with the system overall.

Read More →
Ad Loading...
Managementby StaffJanuary 27, 2026

Keolis Retains Virginia Railway Express Contract

The new contract for Keolis and VRE will commence in July 2026, with the potential to expand to 15 years.

Read More →
Busby StaffJanuary 27, 2026

California's OCTA Advances 2026 Initiatives Centered on Balance and Sustainability

The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.

Read More →
Railby Staff and News ReportsJanuary 26, 2026

People Movement: Virginia's DRPT Names New Director and More

In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
Ad Loading...
ManagementJanuary 23, 2026

Seattle Sound Transit Sets Launch Date for Crosslake Connection

This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.

Read More →
A blue and white graphic with a map of the proposed study area for the Sepulveda Transit Corridor and text reading "LA Metro Approves Underground Rail for Sepulveda Transit Corridor."
RailJanuary 23, 2026

LA Metro Approves Underground Rail for Sepulveda Transit Corridor

The agency’s selection aims to slash travel times from the San Fernando Valley to the Westside to under 20 minutes.

Read More →
TechnologyJanuary 21, 2026

Florida's Tri-Rail Taps Siemens Mobility for Modern Locomotive Procurement

Expected to enter service in 2029, these locomotives support the agency’s commitment to offer reliable and efficient rail transportation across South Florida.

Read More →
Ad Loading...
Rendering of an Austin Light Rail station.
RailJanuary 20, 2026

Austin Transit Partnership Advances Federal Funding Process for Light Rail Project

See how the agency’s transit project completed a Final Environmental Impact Statement within the federal two-year guideline.

Read More →