MBTA double-track project gets go-ahead to proceed to next phase
The work will improve reliability and support future network growth by adding double-track segments to the Franklin Line.


The MBTA's Fiscal and Management Control Board approved a $30 million contract for second phase work and third phase preliminary design work of the Franklin Line Double Track Project, which will improve reliability and support future network growth by adding double-track segments to the Franklin Line. The contract was awarded to the MBTA's commuter rail operator Keolis Commuter Services.
While the Franklin Line is one of the highest ridership lines on the Commuter Rail, the line is also utilized by freight trains on the same tracks with a short track segment west of Walpole Station used for passing: trains pull into this short section of track and pause for trains traveling in the opposite direction to pass by. When the Franklin Double Track Project is complete, the second track being added will extend this track segment, allowing for passing trains to travel without stopping, improving the reliability of service schedules, and supporting future Franklin Line network growth.
Phase 1
Keolis Commuter Services and the MBTA's Railroad Operations team partnered to manage Phase 1 of the project, which aimed to add about four additional miles of double track between Walpole and Norfolk Stations. Keolis was awarded the Phase 1 contract in February 2019, which included the design, procurement, construction, and commissioning of two new signal interlockings; the delivery of all subgrade preparation work, tree removal, major drainage improvements, bank stabilization, and new retaining walls; and replacement of a road bridge that included the removal of the existing bridge, requalification of abutments, the procurement of a new bridge structure, and installing and building the new deck. The work also included the plating of 11,000 ties, the demolition of rock ledges, and adding 150,000 tons of ballast. Phase 1 track construction is anticipated to be complete this month with all Phase 1 work on target to be completed in December 2019. The new track is anticipated to be commissioned in spring 2020 after the MBTA's Positive Train Control program completes its activities on the Franklin Line.
Phase 2
Following the completion of Phase 1 work, Phase 2 work will commence, which includes the addition of another 3.5 miles of double track west from Norfolk Station to Frank Street, which is just east of Franklin Station. The addition of this 3.5-mile segment improves the resilience of the Line and decreases the time between trains from about 45 minutes to about 35 minutes. Phase 2 work, which is anticipated to be complete in December 2020, includes subgrade preparation; drainage improvement work; two interlockings, signal houses, signal gantries, and retaining walls; and new track infrastructure.
Phase 3
In parallel with Phase 2 construction taking place, preliminary design work will begin for Phase 3, which is focused on the four-mile section of track between Walpole and Norwood Central Stations. Upon the completion of the design and construction as part of Phase 3, a double-track line will have ultimately been created along the entire line between South Station in Boston and Franklin Station, improving resiliency on both the Franklin and Fairmount Lines and creating the opportunity to potentially schedule Franklin Line express service.
More Rail

Trinity Metro Breaks Ground on $270M TEXRail Extension
The 2.1-mile extension will connect Fort Worth’s Medical District and Near Southside to downtown, surrounding communities, and Dallas-Fort Worth International Airport.
Read More →
Bringing Austin’s First Light Rail System to Life
Austin Transit Partnership CEO Greg Canally discusses the city's nearly 10-mile light rail project, its collaborative approach to project delivery, the importance of community engagement, and the milestones ahead as construction approaches in 2027.
Read More →
Metra Draft Plan Outlines Costs, Service Improvements for Regional Rail
The Systemwide Network Plan identifies infrastructure needs and potential investments to expand all-day, bidirectional rail service across the Chicago region.
Read More →
Amtrak Completes First Street Tunnel Upgrades, Restores Service
The nine-day construction project included replacing aging track infrastructure and modernizing switch systems near Washington Union Station.
Read More →
FRA Announces $2.3B for Passenger, Freight Rail Projects Nationwide
The CRISI Grant Program funding will support rail infrastructure improvements, safety upgrades, and projects aimed at improving freight and passenger rail service across 45 states and Washington, D.C.
Read More →
Caltrain’s Electrification Drives a New Era of Ridership Growth
The railroad’s shift to electric service has brought more frequent trains, stronger customer satisfaction, and increased ridership, earning it APTA’s Outstanding Public Transportation System award.
Read More →
FTA Advances $164M Broward County Commuter Rail Project
The proposed 10.5-mile commuter rail extension would connect Fort Lauderdale and Aventura, expanding passenger rail options in South Florida.
Read More →
New York MTA Launches Historic $1.9B Signal, Track Modernization Project
Funded in part by congestion pricing revenue, the project will replace nearly century-old signals along the A and C lines in Brooklyn and Queens.
Read More →
LA Metro Breaks Ground on East San Fernando Valley Light Rail Project
The 6.7-mile line will add 11 stations along Van Nuys Boulevard, expand access to jobs and regional transit connections, and support Metro’s broader efforts to improve mobility as rail ridership grows.
Read More →
CSA Group Releases Climate Resilience Standard for Transit, Passenger Rail
Developed with support from the Standards Council of Canada, CSA D700 guides assessing climate-related risks and planning adaptation measures for transit and passenger rail systems.
Read More →