The MBTA's Fiscal and Management Control Board approved a $30 million contract for second phase work and third phase preliminary design work of the Franklin Line Double Track Project, which will improve reliability and support future network growth by adding double-track segments to the Franklin Line. The contract was awarded to the MBTA's commuter rail operator Keolis Commuter Services.
While the Franklin Line is one of the highest ridership lines on the Commuter Rail, the line is also utilized by freight trains on the same tracks with a short track segment west of Walpole Station used for passing: trains pull into this short section of track and pause for trains traveling in the opposite direction to pass by. When the Franklin Double Track Project is complete, the second track being added will extend this track segment, allowing for passing trains to travel without stopping, improving the reliability of service schedules, and supporting future Franklin Line network growth.
Ad Loading...
Phase 1
Keolis Commuter Services and the MBTA's Railroad Operations team partnered to manage Phase 1 of the project, which aimed to add about four additional miles of double track between Walpole and Norfolk Stations. Keolis was awarded the Phase 1 contract in February 2019, which included the design, procurement, construction, and commissioning of two new signal interlockings; the delivery of all subgrade preparation work, tree removal, major drainage improvements, bank stabilization, and new retaining walls; and replacement of a road bridge that included the removal of the existing bridge, requalification of abutments, the procurement of a new bridge structure, and installing and building the new deck. The work also included the plating of 11,000 ties, the demolition of rock ledges, and adding 150,000 tons of ballast. Phase 1 track construction is anticipated to be complete this month with all Phase 1 work on target to be completed in December 2019. The new track is anticipated to be commissioned in spring 2020 after the MBTA's Positive Train Control program completes its activities on the Franklin Line.
Phase 2
Following the completion of Phase 1 work, Phase 2 work will commence, which includes the addition of another 3.5 miles of double track west from Norfolk Station to Frank Street, which is just east of Franklin Station. The addition of this 3.5-mile segment improves the resilience of the Line and decreases the time between trains from about 45 minutes to about 35 minutes. Phase 2 work, which is anticipated to be complete in December 2020, includes subgrade preparation; drainage improvement work; two interlockings, signal houses, signal gantries, and retaining walls; and new track infrastructure.
Phase 3
Ad Loading...
In parallel with Phase 2 construction taking place, preliminary design work will begin for Phase 3, which is focused on the four-mile section of track between Walpole and Norwood Central Stations. Upon the completion of the design and construction as part of Phase 3, a double-track line will have ultimately been created along the entire line between South Station in Boston and Franklin Station, improving resiliency on both the Franklin and Fairmount Lines and creating the opportunity to potentially schedule Franklin Line express service.
Operation Lifesaver awarded $220,200 in grants to 12 states to support rail safety campaigns focused on grade crossing awareness and trespass prevention.
The survey showed that commute trips still make up the majority of ridership, with most riders boarding 2 to 3 days a week, reflecting hybrid work schedules. Two-thirds of Caltrain riders have access to a car, while 37% of Caltrain riders are considered low-income.
Advances in data and analytics are giving transit agencies new opportunities to refine maintenance practices, improve efficiency and make more informed decisions about asset performance.
In this Consultant Roundtable, Carmen C. Cham shares insights on how agencies can create spaces that are intuitive, connected and built for long-term impact.
The Red Line Extension Project will provide the Far South Side of Chicago with rapid rail transit for the first time by extending the Red Line by 5.5 miles from 95th Street to 130th Street, including the construction of four new Red Line stations at 103rd, 111th, Michigan, and 130th streets.
The Siemens CBTC System, Trainguard MT, in compliance with New York Subway Interoperability Interface Specifications, enables trains to run as close as 90 seconds apart, using next-generation signaling and continuous communication to keep operations moving seamlessly.
While recognizing regional economic constraints and continuing to improve service, the budget increases the jurisdictional subsidy to less than 1.8%, significantly below the inflation rate and the 3% regional target, said agency officials.
With more than 59,400,000 boardings since the service’s debut, the A Line’s utilization surpassed that of all other RTD rail services in 2025, the agency reported.
The plan outlines funding for transit operations, capital projects, and freight and passenger rail initiatives, as state officials seek public input on priorities shaping mobility and infrastructure across the Commonwealth.