MTA Announces Phase One Milestone of Park Avenue Viaduct Replacement Project

New York's MTA celebrates major progress on the Park Avenue Viaduct project, rebuilding vital rail infrastructure to improve reliability and safety.

Aerial view of a Metro-North train passing through the gantry system.

Crews use an innovative gantry system to install new prefabricated bridge units over Park Avenue, replacing 128 sections of the Metro-North Viaduct without disrupting service.

Photo: MTA/Trent Reeves

3 min to read


The Metropolitan Transportation Authority reached a major milestone with the completion of bridge replacement work on Phase 1 of the Park Avenue Viaduct Replacement Project. Through 128 bridge installations, the project replaced 8,240 track feet of the aging 132-year-old structure without disrupting Metro-North service.

According to an agency release, "strong" project management and an "innovative" construction approach have pushed the project as a whole $93 million under budget and 51 months ahead of schedule.

Ad Loading...

"[The] milestone demonstrates the transformative work we can get done in New York when we invest in transit," Governor Kathy Hochul said. "The Park Avenue viaduct is a lifeline for hundreds of thousands of Metro-North riders, and now, riders will benefit from a more reliable ride for decades to come."

MTA Upgrades 1890s Park Avenue Viaduct

The Park Avenue Viaduct is the elevated structure in East Harlem that carries four Metro-North tracks and approximately 98% of Metro-North trains daily. Without it, Metro-North would not be able to provide service to Manhattan for riders from the Bronx, Westchester, Putnam, and Dutchess counties, or the state of Connecticut.

It was constructed in the 1890s, and significant portions of it require comprehensive reconstruction after well over a century of heavy use.

"Completing work on an elevated structure that dates back to the Gilded Age ahead of schedule and under budget shows what's possible when we modernize our infrastructure and put riders first," Hochul said.

Image of crews working with the gantry system to replace parts of the Park Avenue Viaduct.

Crews work along Park Avenue in East Harlem as part of the MTA’s multi-phase effort to modernize the Metro-North Viaduct.

Photo: MTA/Trent Reeves

Phase 1 commenced in October 2023 to replace the full substructure and superstructure from East 115th Street to East 123rd Street along Park Avenue, as well as to install new track, power, communications, and signal systems across the new section.

Ad Loading...

Using an innovative gantry system erected over the Viaduct and spanning Park Avenue, the project was able to replace whole sections of the existing concrete and steel bridge deck with new prefabricated bridge units. Over 19 weekends since June 2024, the project replaced 128 individual sections of track — without disrupting Metro-North service on the other side of the structure.

Construction Approach Propels Harlem Viaduct Project Forward

Project contractor Halmar International proposed this approach during an extensive Design-Build procurement process following industry engagement. Phase 1 of the project is 21 months ahead of its initial schedule. This efficiency enabled the project to proceed simultaneously with Phase 2, from East 127th Street to the mid-block between East 131st Street and East 132nd Street, which commenced in May 2024.

Proceeding with Phase 2 on an accelerated timeline resulted in additional time savings, totaling 51 months compared to the initial baseline. As reported, the project is $93 million under its initial budget.

"Our 2025-2029 Capital Plan is all about bringing infrastructure into the 21st century, and we look forward to bringing the same innovative and cost-saving approach that has succeeded here to projects all over the system," MTA Chair and CEO Janno Lieber said.

While the entire structure for Phase 1 is now complete, additional work on the systems and track level will continue through the winter, with Phase 1 expected to reach substantial completion in April 2026. Progress on Phase 2 will continue apace, with substantial completion for that phase expected in September 2027.

Ad Loading...

Additionally, as part of the project, MTA Arts & Design commissioned a permanent art installation over 116 St and along Park Avenue. Harlem Melodic Moments, by Jorge Luis Rodríguez, depicts the music of Harlem and El Barrio on each façade through a visual rhythm of concentric interlocking rings. Large-scale medallions outlined in gold showcase performers of Salsa, Bolero, Latin Jazz, Jazz, Blues, Gospel, Be-Bop, Hip-Hop, Rap, and other danceable fusion genres.

"This replacement project strengthens the backbone of Metro-North's operations, which carries over 98% of all mainline trains. Ensuring the structural integrity and safety of the viaduct is critical to keep running safe and reliable service to and from Grand Central Terminal," Metro-North Railroad President Justin Vonashek said.

More Management

Erin Hockman
Managementby StaffMay 4, 2026

Iowa's DART Taps New CEO

Erin Hockman will officially assume the role on May 7, as current CEO Amanda Wanke departs to take a leadership position with Metro Transit in the Twin Cities.

Read More →
Caltrain trains on tracks
Railby StaffMay 1, 2026

Caltrain Survey Shows Record-High Rider Approval

The survey showed that commute trips still make up the majority of ridership, with most riders boarding 2 to 3 days a week, reflecting hybrid work schedules. Two-thirds of Caltrain riders have access to a car, while 37% of Caltrain riders are considered low-income.

Read More →
A VIA bus
Busby StaffMay 1, 2026

San Antonio's VIA Launches Next Round of Bus Improvements

The changes are designed to reduce overall travel time, shorten wait times, and get customers to their destinations more quickly.

Read More →
Ad Loading...
A graphic of a map showing a "Snapshot of Systemwide Vulnerabilities (projected)."
Managementby News/Media ReleaseMay 1, 2026

MBTA Unveils First Systemwide Climate Resilience Roadmap

The plan outlines strategies to protect transit infrastructure from extreme weather, prioritize critical investments, and improve system reliability as climate risks intensify.

Read More →

People Movement: DART Names Interim Chief, Clean Energy Taps New President/CEO

In this edition, we cover recent appointments and announcements at MCTS, Voith, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
A person working on a bus
ManagementMay 1, 2026

Data-Driven Maintenance: Focusing Effort Where It Matters Most

Advances in data and analytics are giving transit agencies new opportunities to refine maintenance practices, improve efficiency and make more informed decisions about asset performance.

Read More →
Ad Loading...
transit tracker connectpoint
Sponsoredby Alex RomanMay 1, 2026

Connectpoint Expands Digital Signage Strategy with LED Push

Connectpoint is enhancing its digital signage strategy by integrating LED technology into its services.

Read More →
frontrunner bus
SponsoredMay 1, 2026

ADA Compliant Transit: Easier, More Dignified Travel for Every Passenger

Today’s riders—and the communities you serve—expect more from public transit. While ADA compliance is required, leading transit agencies know that true accessibility also means delivering dignity, efficiency, and a better rider experience. This whitepaper reveals why forward thinking agencies nationwide choose the Low Floor Frontrunner as their first choice for ADA compliant vehicles—setting a new standard with passenger first design, faster boarding, improved safety, and unmatched operational performance.

Read More →
A expanse of highway in Colorado with text reading "FMCSA Tightens Clearinghouse Verification to Strengthen Driver Records."
Managementby StaffApril 30, 2026

FMCSA Tightens Clearinghouse Verification to Strengthen Driver Records

New ID requirements for employers and service providers aim to improve data accuracy and oversight for motorcoach and commercial drivers.

Read More →
Ad Loading...
A snowy bridge construction staging zone.
Managementby StaffApril 30, 2026

USDOT Reboots Key Bridge Contract, Expands Infrastructure Funding Nationwide

Maryland to rebid major bridge contract as the Build America Bureau commits $20 million to accelerate project planning and public-private partnerships across 17 states.

Read More →