MTA Announces Phase One Milestone of Park Avenue Viaduct Replacement Project

New York's MTA celebrates major progress on the Park Avenue Viaduct project, rebuilding vital rail infrastructure to improve reliability and safety.

Aerial view of a Metro-North train passing through the gantry system.

Crews use an innovative gantry system to install new prefabricated bridge units over Park Avenue, replacing 128 sections of the Metro-North Viaduct without disrupting service.

Photo: MTA/Trent Reeves

3 min to read


The Metropolitan Transportation Authority reached a major milestone with the completion of bridge replacement work on Phase 1 of the Park Avenue Viaduct Replacement Project. Through 128 bridge installations, the project replaced 8,240 track feet of the aging 132-year-old structure without disrupting Metro-North service.

According to an agency release, "strong" project management and an "innovative" construction approach have pushed the project as a whole $93 million under budget and 51 months ahead of schedule.

Ad Loading...

"[The] milestone demonstrates the transformative work we can get done in New York when we invest in transit," Governor Kathy Hochul said. "The Park Avenue viaduct is a lifeline for hundreds of thousands of Metro-North riders, and now, riders will benefit from a more reliable ride for decades to come."

MTA Upgrades 1890s Park Avenue Viaduct

The Park Avenue Viaduct is the elevated structure in East Harlem that carries four Metro-North tracks and approximately 98% of Metro-North trains daily. Without it, Metro-North would not be able to provide service to Manhattan for riders from the Bronx, Westchester, Putnam, and Dutchess counties, or the state of Connecticut.

It was constructed in the 1890s, and significant portions of it require comprehensive reconstruction after well over a century of heavy use.

"Completing work on an elevated structure that dates back to the Gilded Age ahead of schedule and under budget shows what's possible when we modernize our infrastructure and put riders first," Hochul said.

Image of crews working with the gantry system to replace parts of the Park Avenue Viaduct.

Crews work along Park Avenue in East Harlem as part of the MTA’s multi-phase effort to modernize the Metro-North Viaduct.

Photo: MTA/Trent Reeves

Phase 1 commenced in October 2023 to replace the full substructure and superstructure from East 115th Street to East 123rd Street along Park Avenue, as well as to install new track, power, communications, and signal systems across the new section.

Ad Loading...

Using an innovative gantry system erected over the Viaduct and spanning Park Avenue, the project was able to replace whole sections of the existing concrete and steel bridge deck with new prefabricated bridge units. Over 19 weekends since June 2024, the project replaced 128 individual sections of track — without disrupting Metro-North service on the other side of the structure.

Construction Approach Propels Harlem Viaduct Project Forward

Project contractor Halmar International proposed this approach during an extensive Design-Build procurement process following industry engagement. Phase 1 of the project is 21 months ahead of its initial schedule. This efficiency enabled the project to proceed simultaneously with Phase 2, from East 127th Street to the mid-block between East 131st Street and East 132nd Street, which commenced in May 2024.

Proceeding with Phase 2 on an accelerated timeline resulted in additional time savings, totaling 51 months compared to the initial baseline. As reported, the project is $93 million under its initial budget.

"Our 2025-2029 Capital Plan is all about bringing infrastructure into the 21st century, and we look forward to bringing the same innovative and cost-saving approach that has succeeded here to projects all over the system," MTA Chair and CEO Janno Lieber said.

While the entire structure for Phase 1 is now complete, additional work on the systems and track level will continue through the winter, with Phase 1 expected to reach substantial completion in April 2026. Progress on Phase 2 will continue apace, with substantial completion for that phase expected in September 2027.

Ad Loading...

Additionally, as part of the project, MTA Arts & Design commissioned a permanent art installation over 116 St and along Park Avenue. Harlem Melodic Moments, by Jorge Luis Rodríguez, depicts the music of Harlem and El Barrio on each façade through a visual rhythm of concentric interlocking rings. Large-scale medallions outlined in gold showcase performers of Salsa, Bolero, Latin Jazz, Jazz, Blues, Gospel, Be-Bop, Hip-Hop, Rap, and other danceable fusion genres.

"This replacement project strengthens the backbone of Metro-North's operations, which carries over 98% of all mainline trains. Ensuring the structural integrity and safety of the viaduct is critical to keep running safe and reliable service to and from Grand Central Terminal," Metro-North Railroad President Justin Vonashek said.

More Management

A red, white, and blue graphic with the APTA logo and text reading "APTA Nominates 2026-2027 Chair & Vice Chair."
Managementby Staff and News ReportsSeptember 10, 2026

APTA 2026 Nominating Committee Selects Leadership Slate, Names Chair and Vice Chair Nominees

Leadership changes will help shape the association’s priorities and its representation of the transportation industry during the 2026–2027 term.

Read More →
DART's light rail station at 8th and Corinth
Security and Safetyby Alex RomanSeptember 10, 2026

DART Launches Major Security, Fare Enforcement Initiative

The 90-day demonstration will deploy coordinated security teams at five light rail stations while testing controlled access and gathering data to guide future investments.

Read More →
STraffic White Paper Cover Learn about delivering 1300 gates at 91 stations while managing fare evasion. Explore the large scale deployment, solution customization and real-world results that affect the region. Prepare for deployment in your region now.
SponsoredSeptember 9, 2026

Advancing Fare Collection Through Technology and Innovation

Learn about delivering 1300 gates at 91 stations while managing fare evasion. Explore the large scale deployment, solution customization and real-world results that affect the region. Prepare for deployment in your region now.

Read More →
Ad Loading...
A TransLink train goes by a large FIFA World Cup soccer ball structure.
Managementby Elora HaynesSeptember 8, 2026

Game Day in Motion: Moving Millions During the 2026 World Cup

Between packed transit stations and team motorcoaches, see how agencies and operators across North America tackled the transportation demands of the 2026 FIFA World Cup.

Read More →
A blue and white graphic with text reading "Surface Transportation Averts Shutdown, Leaves Transit Funding Gap."
Managementby Elora HaynesSeptember 4, 2026

Surface Transportation Extension Averts Shutdown, Leaves Transit Funding Gap

The stopgap keeps federal transportation programs moving, but missing advance funding could complicate the transit and rail projects agencies are planning next.

Read More →
Bus Tech Talk: Transit Tech Training...What's Changed?
Busby Alex RomanSeptember 4, 2026

Bus Tech Talk: Keeping Transit Technicians Ahead of the Technology Curve

LA Metro’s Obed Mejia discusses technician training, evolving maintenance technology, fleet replacement, and strategies for getting the most out of today’s transit fleets.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Holly Arnold
Managementby Alex RomanSeptember 2, 2026

People Movement: Holly Arnold Joins Transdev and More

In this edition, we also cover recent appointments and announcements at Pace, CamTran, MCI, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
A Chicago rail and rail car in the city.
Managementby Staff and News ReportsSeptember 1, 2026

NITA Launches New Era of Regional Transit in Chicago

The new authority replaces the RTA and brings CTA, Metra, and Pace under a strengthened regional framework for funding, planning, fares, safety, and service coordination.

Read More →
Ad Loading...
Canada-Qatar match fans underneath a TransLink SkyTrain overpass.
Managementby Elora HaynesSeptember 1, 2026

How World Cup Mobility Put Transit and Motorcoaches to the Test

Behind the seamless trips were months of planning, multimodal partnerships, and lessons agencies and operators can carry into the next mega-event.

Read More →