Since March 7, 2007, nearly 1,000 employees working 24 hours a day, five days a week, have completed more than 2,400 controlled blasts — all without affecting the nearby operations of MTA Metro-North Railroad or the New York City Subway.
Sandhogs working on the New York Metropolitan Transportation Authority’s (MTA) East Side Access megaproject have concluded major blasting under Grand Central Terminal, where they are building two enormous caverns 160 feet below street level that will house eight tracks for Long Island Rail Road (LIRR) trains.
Since March 7, 2007, nearly 1,000 employees working 24 hours a day, five days a week, have completed more than 2,400 controlled blasts — all without affecting the nearby operations of MTA Metro-North Railroad or the New York City Subway.
Ad Loading...
Approximately 857,000 cubic yards of rocky muck were excavated and removed, enough to cover the entirety of Central Park one foot deep.
“This is a very significant milestone for the East Side Access project,” said Dr. Michael Horodniceanu, president, MTA capital construction. “The caverns are essentially now fully excavated. Much work remains to be done to build the platforms and tracks and finish what is currently raw, cave-like space. But we now have a fully built shell in which all future work will take place.”
Each blast was overseen by an FDNY-licensed blaster. To conduct a blast, teams of sandhogs drill hundreds of holes measuring 1½ inches in diameter into the mica-inflected granite schist that forms the bedrock of Midtown Manhattan. Together, the holes are loaded with 200 pounds to 500 pounds of an explosive powder known as Emulex. After the sandhogs clear into a safe area, the Blaster-in-Charge issues a warning — “fire in the hole!” — and triggers the blast.
The contractors, a joint venture of Dragados USA Inc., and Judlau Contracting Inc., are continuing to perform miscellaneous concrete work until their contract is complete in June. They expect that they may need to make additional small blasts that will trim out pieces of rock in the cavern.
In addition to the blasting, the caverns under Grand Central have been excavated in part by two monstrous 200-ton tunnel boring machines that operated from September 2007 until June 2011, chewing through a total of more than 32,000 linear feet of Manhattan bedrock from 63rd Street to 37th Street.
Operation Lifesaver awarded $220,200 in grants to 12 states to support rail safety campaigns focused on grade crossing awareness and trespass prevention.
The survey showed that commute trips still make up the majority of ridership, with most riders boarding 2 to 3 days a week, reflecting hybrid work schedules. Two-thirds of Caltrain riders have access to a car, while 37% of Caltrain riders are considered low-income.
Advances in data and analytics are giving transit agencies new opportunities to refine maintenance practices, improve efficiency and make more informed decisions about asset performance.
In this Consultant Roundtable, Carmen C. Cham shares insights on how agencies can create spaces that are intuitive, connected and built for long-term impact.
The Red Line Extension Project will provide the Far South Side of Chicago with rapid rail transit for the first time by extending the Red Line by 5.5 miles from 95th Street to 130th Street, including the construction of four new Red Line stations at 103rd, 111th, Michigan, and 130th streets.
The Siemens CBTC System, Trainguard MT, in compliance with New York Subway Interoperability Interface Specifications, enables trains to run as close as 90 seconds apart, using next-generation signaling and continuous communication to keep operations moving seamlessly.
While recognizing regional economic constraints and continuing to improve service, the budget increases the jurisdictional subsidy to less than 1.8%, significantly below the inflation rate and the 3% regional target, said agency officials.
With more than 59,400,000 boardings since the service’s debut, the A Line’s utilization surpassed that of all other RTD rail services in 2025, the agency reported.
The plan outlines funding for transit operations, capital projects, and freight and passenger rail initiatives, as state officials seek public input on priorities shaping mobility and infrastructure across the Commonwealth.