Safety Issues Cause MARTA to Sideline Atlanta Streetcar Service

The reasoning behind the decision was detailed by MARTA’s Deputy Chief Mechanical Officer Daniel Hecht during a board meeting.

Alex Roman
Alex RomanExecutive Editor
Read Alex's Posts
December 9, 2022
Safety Issues Cause MARTA to Sideline Atlanta Streetcar Service

When routine track inspections found the issues with the switch, the decision was made to place a safety hold on Nov. 29 and expedite the wheel replacement across the entire Atlanta Streetcar fleet.

Credit:

MARTA

2 min to read


The Metropolitan Atlanta Rapid Transit Authority (MARTA) is suspending Atlanta Streetcar service through the New Year due to safety concerns found during a recent inspection, thought to be caused by a wheel issue that was first identified in the first quarter of 2021.

The reasoning behind the decision was detailed by MARTA’s Deputy Chief Mechanical Officer Daniel Hecht during a board meeting. Hecht explained that regular wear and tear of the wheel profile first noticed in 2021 caused issues with the track switch, where some bolts were found to be loosened and there was damage to the concrete close to the platform.

Ad Loading...

Hecht explained that when the wheel issue was first discovered, MARTA had planned to have the wheels replaced, however, due to a worldwide wheel shortage the work was pushed into this year after its supplier, Siemens, was able to finally procure the wheels.

The original plan was to ship the vehicles out one at a time to have the wheels replaced, beginning this month. But, when routine track inspections found the issues with the switch, the decision was made to place a safety hold on Nov. 29 and expedite the wheel replacement across the entire Atlanta Streetcar fleet.

Hecht added the decision was made because of the risk associated with the continued degradation of the wheels, to protect the public and the brand name, to protect the track after the issues were identified, and to “walk the walk” that MARTA is a safety-oriented organization.

MARTA detailed the process for repairing the vehicles, which includes:

  • Unhooking the truck assemblies.

  • Lifting the Trains.

  • Shipping the trucks to Siemens facility in Sacramento, Calif., for repair.

  • Overhaul the vehicles over an eight-week timeline.

  • Ship the trucks back to MARTA.

  • Install rebuilt trucks.

Ad Loading...

In place of the streetcar service, MARTA will run cutaway vehicles, which will provide service to each of the streetcars stops on 15-minute intervals. The vehicles will eventually be wrapped to maintain brand awareness, as well as ridership. The vehicles will also be driven by the same operators who operate the streetcars to help maintain familiarity for riders who frequently utilize the service.

More Rail

A Metrolink station with two trains.
Rail•by Alex Roman•November 16, 2026

Southern California’s Metrolink Approves $508.8M Budget, Avoids Service Cuts

A $20 million state allocation allows the regional rail agency to maintain existing weekday and weekend service through fiscal year 2028, although longer-term funding challenges remain.

Read More →
A wide shot of Alstom's Multilevel III commter railcar for NJ TRANSIT
Rail•by Alex Roman•November 13, 2026

NJ TRANSIT Approves $65.6M for Hudson-Bergen Light Rail Improvements

The funding marks the first phase of a planned $250 million investment over five years to modernize stations, overhaul vehicles, and improve system reliability and passenger safety.

Read More →
STraffic's John Moon
Technology•by Alex Roman•November 12, 2026

STraffic Expands North American Presence with Fare Collection Technology

John Moon, Associate Director, Product Strategy at STraffic, discusses the company's growth in North America, its efforts to reduce fare evasion, and more.

Read More →
Ad Loading...
An aerial shot of the Denver region
Management•by Alex Roman•November 12, 2026

Study: Denver RTD Generates $2.1 Billion in Annual Economic Activity

An economic impact study finds the agency supports approximately 17,500 jobs, delivers $1.6 billion in annual community and mobility benefits, and generates $2.42 in economic value for every dollar invested.

Read More →
METRO Magazine leadership update graphic featuring a portrait of Mark Aesch, identified as administrator of the Federal Transit Administration (FTA), alongside the U.S. Department of Transportation and FTA logos on a blue gradient background.
Management•by Alex Roman•November 12, 2026

Mark Aesch Nominated to Lead Federal Transit Administration

The former Rochester transit chief and TransPro founder, who has also contributed to METRO Magazine, brings decades of industry experience and a focus on performance, accountability, and financial sustainability to the nomination.

Read More →
Transit Reaches 200 Agency Partnerships, Expands Rider Experience Tools
Technology•by Alex Roman•November 6, 2026

Transit Expands Agency Partnerships, Reaching 200 Official App Partners

COO Jake Sion discusses Transit’s growth, the success of its Transit Royale program, and how technology is helping agencies improve the rider experience.

Read More →
Ad Loading...
A rendering of Trinity Metro's future station at the Medical Center
Rail•by Alex Roman•October 30, 2026

Trinity Metro Breaks Ground on $270M TEXRail Extension

The 2.1-mile extension will connect Fort Worth’s Medical District and Near Southside to downtown, surrounding communities, and Dallas-Fort Worth International Airport.

Read More →
Austin Light Rail rendering from UT perspective
Rail•by Alex Roman•October 30, 2026

Bringing Austin’s First Light Rail System to Life

Austin Transit Partnership CEO Greg Canally discusses the city's nearly 10-mile light rail project, its collaborative approach to project delivery, the importance of community engagement, and the milestones ahead as construction approaches in 2027.

Read More →
Two Metra locomotives on rail tracks.
Rail•by Alex Roman•October 29, 2026

Metra Draft Plan Outlines Costs, Service Improvements for Regional Rail

The Systemwide Network Plan identifies infrastructure needs and potential investments to expand all-day, bidirectional rail service across the Chicago region.

Read More →
Ad Loading...
METRO Magazine graphic featuring railroad tracks and switches inside a dark tunnel with the headline “Amtrak Completes First Street Tunnel Upgrades, Restores Service.”
Rail•by Elora Haynes•October 29, 2026

Amtrak Completes First Street Tunnel Upgrades, Restores Service

The nine-day construction project included replacing aging track infrastructure and modernizing switch systems near Washington Union Station.

Read More →