Construction at Roosevelt Station is about 70 percent complete. Crews are focused on finishing the station entrances, or headhouses, seen here on the left.
Sound Transit
2 min to read
Construction at Roosevelt Station is about 70 percent complete. Crews are focused on finishing the station entrances, or headhouses, seen here on the left.
Sound Transit
Sound Transit's Northgate Link Extension reached 70% completion, as project construction moves ahead to start service in 2021. The project is a major component of Sound Transit's regional commitment to complete 116 new miles of voter-approved light rail, the largest rail service expansion in the country.
Progress on Northgate Link construction includes track installation, which is nearing 50% completion. In addition, construction at each of the three stations on the extension has reached a significant milestone. The Northgate Station is approximately 70% complete, and the Roosevelt Station is nearing 70% completion. The University District Station is approximately 50% complete.
Ad Loading...
When finished, the 4.3-mile regional light rail extension will offer riders traffic-free travel between Northgate and downtown Seattle in 14 minutes. Trains traveling in 3.5-mile twin tunnels north to and from the University of Washington Station at Husky Stadium will stop at underground stations in the U District and Roosevelt neighborhoods, exit the tunnels at First Avenue Northeast and Northeast 95th and transition to a 0.8-mile elevated guideway to reach the station.
Sound Transit is simultaneously working to extend light rail north, south, east, and west, opening new stations every few years to form a 116-mile regional system by 2041. Northgate Link will be followed in 2023 by the opening of service to Mercer Island, Bellevue and Redmond's Overlake community.
Additional extensions to Shoreline, Mountlake Terrace, Lynnwood, Kent/Des Moines, Federal Way and downtown Redmond are planned in 2024. Further light rail extensions are scheduled to reach West Seattle, Fife and Tacoma in 2030; Ballard in 2035; Paine Field and Everett in 2036; and South Kirkland and Issaquah in 2041.
The agency is also working on further investments including but not limited to expansions of Sounder South service and bus rapid transit service in 2024 along the north, east and south sides of Lake Washington.
In this episode of METROspectives, METRO’s Executive Editor Alex Roman sits down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the Canadian Standards Association (CSA Group).
In this edition, we cover recent appointments and announcements at HDR, NCTD, STV, and more, showcasing the individuals helping to shape the future of transportation.
The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.
The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.
In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.
This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.