Valley Metro accelerates light rail extension by 7 years
Will re-launch the 3.2-mile Northwest extension. The project has received approval to accelerate the completion year from 2023 to 2016. Final design is under way; construction will begin in early 2013.
Valley Metro’s (Metro) construction of light rail is back on the move in Phoenix, with the re-launch of the Northwest extension along 19th Ave. from the current end-of-line north 3.2 miles to Dunlap Avenue. The project has received approval to accelerate the completion year from 2023 to 2016. Final design is under way; construction will begin in early 2013.
Phoenix Mayor Greg Stanton says many in the city have been looking forward to the project beginning again. “Speaking on behalf of the residents and passengers, I know there is much anticipation to add light rail service to the highly-used bus service along this route. This project is an investment in the community I believe in and will prove to be a great benefit with its completion.”
The Northwest extension was initially set to open this year; however, in 2009, the economic downturn and decline in local sales tax revenue forced the project on hold. With its postponement, the project was pushed out to a 2023 completion year. The positive strides in the economy, expected boost from the building of this extension and local willpower have helped to advance it by seven years.
This project is one of six high-capacity/light rail extensions being planned for or in active construction in the metro Phoenix region. It will extend rail service farther north into Phoenix, capturing new riders, serving high-density neighborhoods and getting closer to the Interstate 17 freeway and its employment centers.
“It’s an exciting time as we further expand into Phoenix, providing our customers with greater access to transit and choice in how they travel,” said Valley Metro CEO Steve Banta. “It is another step in building a multi-modal Total Transit Network that supports regional growth, mobility and quality of life.”
Metro is in process of re-energizing contracts with the Northwest extension designer, AECOM, and contractor, Sundt/Stacy Witbeck. AECOM will work through the spring to update and complete design; Sundt/Stacy Witbeck will break ground with utility relocation at the first of the year.
More Rail

New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Read More →
San Diego MTS Breaks Monthly Trolley Ridership Record
Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.
Read More →
Report Examines NJ TRANSIT Reliability, Funding Challenges
The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.
Read More →
Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement
Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.
Read More →
Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More
In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.
Read More →
CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips
With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.
Read More →
Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations
Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.
Read More →
Amtrak Begins Major Construction at New York’s Sunnyside Yard
The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.
Read More →
Chicago Leaders Unveil Plans for O’Hare Airport Express Train
The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.
Read More →
OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor
The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.
Read More →