Sound Transit completes downtown light rail service

The return follows the conclusion of Connect 2020, an 11-week period of major service impacts while construction crews connected the existing system in downtown Seattle to East Link.

by Staff
March 23, 2020
Sound Transit completes downtown light rail service

With light rail ridership down nearly 70% as the region battles the spread of the novel coronavirus, trains will continue to run every 14 minutes under temporary service reductions announced last week.

WSP

2 min to read


With the project’s completion, riders through Downtown Seattle will no longer need to transfer at Pioneer Square, and restrictions on bicycles will end. WSP

Link light rail will return to two-track service in downtown Seattle stations beginning Monday. The return follows the conclusion of Connect 2020, an 11-week period of major light rail service impacts while construction crews connected the existing light rail system in downtown Seattle to East Link in preparation for the 2023 extension of service to Mercer Island, Bellevue, and Redmond.

Ad Loading...

With the project’s completion, riders through Downtown Seattle will no longer need to transfer at Pioneer Square, and restrictions on bicycles will end.

With light rail ridership down nearly 70% as the region battles the spread of the novel coronavirus, trains will continue to run every 14 minutes under temporary service reductions announced last week. Because of these reductions, which also affect Sounder and some ST Express routes, as well as King County Metro Transit services, resources such as Google maps, One Bus Away, and other apps and websites may not have accurate schedule information for all trips.

Sound Transit is committed to serving the public and will continue to meet the needs of transit-dependent riders as well as services for low-income, minority, and limited-English-proficiency populations. It remains critical for riders to continue observing the precautions that health authorities are emphasizing to help control the spread of the virus.

“We want to thank our riders for their patience during Connect 2020, and for the safety measures they are observing as they ride transit during this challenging time,” said Sound Transit CEO Peter Rogoff. “We are committed to continue to keep our services moving for those who need them, including health care workers and others who are working to keep our communities functioning.”

With the end of the Connect 2020 disruption, the existing tunnel is now configured for East Link in preparation for 2023, when light rail expands to 10 new East King County stations. Before then, three new stations — U District, Roosevelt, and Northgate — will begin service in 2021, boosting ridership and increasing the importance of completing this work now.

More Rail

A New York MTA subway car with an open gangway
Railby Staff and News ReportsSeptember 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →
A San Diego MTS Copper Line vehicle
Railby Staff and News ReportsSeptember 15, 2026

San Diego MTS Breaks Monthly Trolley Ridership Record

Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.

Read More →
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Railby Alex RomanSeptember 14, 2026

Report Examines NJ TRANSIT Reliability, Funding Challenges

The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.

Read More →
Ad Loading...
A CapMetro commuter rail train provided by Stadler
Railby Staff and News ReportsSeptember 11, 2026

Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement

Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.

Read More →
Rendering of an Alstom train in a VIA Rail Station
Technologyby Alex RomanSeptember 10, 2026

Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More

In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.

Read More →
The CATS Gold Line in service with the city skyline in the background.
Railby Staff and News ReportsSeptember 3, 2026

CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips

With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Amtrak Sunnyside Groundbreaking
Railby Staff and News ReportsSeptember 2, 2026

Amtrak Begins Major Construction at New York’s Sunnyside Yard

The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.

Read More →
O'Hare Flyer Rendering
Railby Staff and News ReportsAugust 27, 2026

Chicago Leaders Unveil Plans for O’Hare Airport Express Train

The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.

Read More →
Ad Loading...
An OCTA coastal rail line train.
Railby Staff and News ReportsAugust 27, 2026

OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor

The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.

Read More →