MARTA Reopens Renovated Airport Station
MARTA began station rehabilitation work at Airport Station in June 2022. Prior to this most recent round of construction, teams completed structural work in preparation for the new elevator installation, replaced the south vestibule and progressed electrical upgrades.

The Airport Station Project is part of MARTA’s approximately $1 billion multi-year Station Rehabilitation Program and primarily paid for with State of Good Repair Funds in the Capital budget. The total project cost is $55 million.
Photo: MARTA
The Metropolitan Atlanta Rapid Transit Authority (MARTA) Airport Station reopened after a six-week closure to renovate the concourse and platform levels.
The following work was completed during a temporary station closure from April 8 through May 19.
Installation of new terrazzo flooring in concourse.
Installation of new platform pavers.
Repair, sealing, and painting of track and concourse walls.
Preparation for installation of the new canopy.
“This was an incredibly successful project and I want to thank our customers for bearing with us while we completed this necessary work,” said MARTA GM/CEO Collie Greenwood. “Temporarily closing the station significantly reduced the overall construction time by 17 months and ensured the safety of workers and customers. A big thank you to the project and construction teams, and MTI Limo and Shuttle Services for working around the clock to get this work done and make sure customers and airport employees still had a reliable connection to the airport.”
Airport Station Construction
During the closure, MARTA provided bus shuttle service between College Park Station and Hartsfield-Jackson Atlanta International Airport 22 hours a day.
Shuttle ridership was approximately 320,000 over the 42-day period. Airport Station serves on average 11,000 customers daily.
The Airport Station Project is part of MARTA’s approximately $1 billion multi-year Station Rehabilitation Program and primarily paid for with State of Good Repair Funds in the Capital budget. The total project cost is $55 million.
MARTA began station rehabilitation work at Airport Station in June 2022. Prior to this most recent round of construction, teams completed structural work in preparation for the new elevator installation, replaced the south vestibule and progressed electrical upgrades.
Other planned improvements include replacement of ceilings and lighting, a new RideStore, full rehabilitation of the existing elevator, a public art installation, replacement of all signage, and full renovation of employee spaces.
Steps to Complete, Real-Time Info
Additional service impacts may follow as the project reaches its conclusion, including nightly closures and another temporary closure at the end of construction to install the new canopy.
MARTA has also upgraded digital sign content at Airport Station and at all 38 rail stations systemwide to display more service information, including real-time train arrivals and scheduled train arrivals up to 30 minutes out.
Real-time arrivals will be denoted with an icon and update every ten seconds. Scheduled arrivals will account for single tracking and special rail service.
Other digital sign upgrades planned for this year include repairs to nonfunctioning station screens, adding live bus departures and cancellations to the screens, and enhancement to MARTA’s website.
More Rail

New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Read More →
San Diego MTS Breaks Monthly Trolley Ridership Record
Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.
Read More →
Report Examines NJ TRANSIT Reliability, Funding Challenges
The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.
Read More →
Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement
Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.
Read More →
Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More
In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.
Read More →
CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips
With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.
Read More →
Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations
Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.
Read More →
Amtrak Begins Major Construction at New York’s Sunnyside Yard
The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.
Read More →
Chicago Leaders Unveil Plans for O’Hare Airport Express Train
The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.
Read More →
OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor
The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.
Read More →