Boston's MBTA Provides Update on South Coast Rail Project

The project, which spans across six stations, will start running test trains June 17. When complete, the project will restore rail service between Boston and the South Coast for the first time in over 70 years.

June 14, 2024
Boston's MBTA Provides Update on South Coast Rail Project

MBTA's timeline adjustment to spring 2025 for passengers allows for more resources and attention to make South Coast Rail reliable on the first day of service and beyond.

Photo: Canva

4 min to read


Boston’s Massachusetts Bay Transportation Authority (MBTA) provided an update on the progress of the South Coast Rail project, including a new milestone reached that brings the project closer to completion.

The project, which spans across six stations, will start running test trains June 17. When complete, the project will restore rail service between Boston and the South Coast for the first time in over 70 years.

Ad Loading...

Update from MBTA’s GM/CEO

The MBTA and its GM/CEO Phillip Eng hosted two public meetings to update residents on the South Coast Rail project.

“The MBTA is deeply committed to delivering the South Coast Rail project while upholding the highest standards of quality and safety before launching passenger service,” said Eng. “We recognize this project is especially important for the Fall River, New Bedford, and Taunton communities, and the surrounding region. Through testing and quality control measures, we are dedicated to providing the public with a reliable and dependable railroad system they can count on.”

After a review of the project, Eng determined new project leadership was needed to ensure the success and safety of the project.

The timeline adjustment to spring 2025 for passengers allows for more resources and attention to make South Coast Rail reliable on the first day of service and beyond.

Nationally, these projects are highly specialized and complex, requiring specific expertise, with the system testing phase being one of the most challenging aspects to ensure seamless integration of all components.

Ad Loading...

Construction and Equipment

Four locomotives have undergone a comprehensive overhaul and are now prepared to provide the necessary pulling power to operate the trains efficiently.

Additionally, 16 modern bi-level coaches have been specifically acquired to serve passengers on South Coast Rail. Bi-level coaches offer increased passenger capacity with comfortable seating arrangements on two levels, ideal for commuter routes.

Four stations are now complete and two stations are nearing completion.

MBTA’s South Coast Project

Following the successful completion of Automatic Train Control (ATC) testing and the transfer of dispatch to Keolis, the South Coast Rail project will progress to Positive Train Control (PTC) system testing. This federally mandated testing will begin in August and continue through January.

Once all components — stations, layover facilities, tracks, ATC, and the PTC system — are built, tested, and approved, the project will move to the final phase of “New Start” implementation with the Federal Railroad Administration (FRA). This phase involves certifying train operators, final inspections, and running demonstration services without passengers.

Ad Loading...

The timeline for this final stage depends on the FRA’s review and requirements. The intensive, multi-phased process designed specifically for first-time rail activation projects to achieve compliance with Federal regulations governing the movements of passenger trains over new territory ensures railroad operators meet the prescribed regulatory standards prior to the commencement of new commuter rail service.

The “New Start” process is comprised of many key components, including the requirement to implement a System Safety Program, a rigorous qualification program for personnel who will be engaged in the operations of the railroad, adherence to industry design and construction standards, and a comprehensive safety certification process all completed and approved prior to the start of passenger service.

Additionally, a robust Quality Assurance and Quality Control program will be implemented to ensure operations run smoothly.

As the South Coast Rail project advances through the “New Start” process, the MBTA will continue to prioritize safety and quality in the development of this new rail system, working diligently to meet the regulatory requirements set forth by the FRA.

The successful completion of the “New Start” process is a critical step in bringing the South Coast Rail project to fruition and providing improved transportation options for the communities of the South Coast region.

Ad Loading...

The testing phase will involve a comprehensive array of safety measures, including track testing, signaling system testing, integration testing, and safety inspections. During this time, residents may notice increased train activity along the South Coast Rail corridor.

The MBTA trains will not carry passengers and are being operated solely for testing and training purposes. They will reach speeds of up to 79 miles per hour, up from the current 30 miles per hour limit for freight trains. This certification was completed through a rigorous safety process put in place by the MBTA and approved by the FRA.

With the track safety certification in place, the focus has shifted to testing the signal system. Initial testing was conducted at slow speeds of 25 miles per hour, and the results have been successful.

The next phase involves testing the railroad crossings, ensuring that the gates function properly within the guidelines set by federal regulators. These tests will be conducted at multiple speeds, in both directions, and on all routes.

More Rail

Two Metra locomotives on rail tracks.
Railby StaffApril 10, 2026

Metra Reaches New 10-Year Agreement with BNSF

The announcement highlights the long-standing partnership between the Class I railroad and the commuter rail system, dating back to Metra's creation in 1983.

Read More →
Ribbon cutting at Siemens' new North Carolina facility.
Railby StaffApril 9, 2026

Siemens Opens North Carolina Railcar Manufacturing Facility

Site construction is complete, production is underway, and the first locally built passenger coaches are on track for delivery in Summer 2026.

Read More →
Two MBTA railcars in station.
Railby StaffApril 9, 2026

MBTA Completes Key Red Line Signal Upgrade Weeks Early

Crews completed a significant portion of the testing required before commissioning the new, digital signaling system, which will bring important upgrades that strengthen Red Line service reliability for riders and provide Red Line Operations the ability to route trains more quickly, turn trains around faster, and recover from unplanned disruptions more efficiently, said MBTA officials. 

Read More →
Ad Loading...
A Metra train on the rails
Railby StaffApril 8, 2026

Metra Reveals 2026 Construction Program

In addition to new projects, progress continues on a multiyear effort to upgrade track, electrical, and signal systems on the Metra Electric Line to accommodate the expansion of service on the South Shore Line.

Read More →
Governor Moore speaking at Maryland light rail station
Managementby StaffApril 7, 2026

Governor Advances Transit-Oriented Development in Baltimore

The Maryland Transit Administration is advancing the nearly $1.4 billion Light Rail Modernization Program, which modernizes the Baltimore Central Light Rail Line from Hunt Valley to BWI Thurgood Marshall Airport with new, low-floor vehicles and upgrades to all light rail stations, systems, and maintenance facilities.

Read More →
A fleet of Caltrain electrified trains on tracks
Railby StaffApril 3, 2026

Funding Gap Could Force Caltrain to Slash Service, Close Stations

The Peninsula Corridor Joint Powers Board recently met for a budget workshop, during which staff outlined the significant service reductions Caltrain could be forced to make without new external funding. 

Read More →
Ad Loading...
SEPTA's Exo railcars
Railby StaffApril 2, 2026

SEPTA Purchases Montreal Coach Cars to Bolster Regional Rail Fleet

Funding for the purchase of the railcars comes from the nearly $220 million in additional capital dollars Gov. Josh Shapiro allocated in November 2025 to support urgent safety upgrades and infrastructure improvements.

Read More →
The South Shore Line with Passengers
Railby StaffApril 1, 2026

South Shore Line Extension Debuts, Boosting Rail Access in Northwest Indiana

The $945 million project connects four new stations and expands regional mobility.

Read More →
A rendering of a California High-Speed Rail vehicle
Railby StaffApril 1, 2026

High-Speed Rail May Boost Brain Health, New Study Finds

Research ties rail access to lower depression, better cognition and improved air quality.

Read More →
Ad Loading...
An MBTA commuter rail at a station.
Railby StaffMarch 31, 2026

Massachusetts Announces Summer Savings for Commuter Rail Riders

With major events and increased travel expected across the state this summer, the Administration is focused on making sure people have a reliable, affordable alternative to driving so we can reduce congestion, support daily commuters, and keep Massachusetts moving.

Read More →