Caltrain, Partners Complete Successful Energization, Testing of Full 51-Mile Corridor

The milestone achievement in the Caltrain Electrification Project signifies major progress in expanding the agency’s ability to test electric trains at full speed along the corridor and prepare for electrified revenue service in September 2024.

Caltrain, Partners Complete Successful Energization, Testing of Full 51-Mile Corridor

Caltrain, PG&E, and Balfour Beatty’s work to complete the energization was substantial, needing to be safely conducted while maintaining rail service to more than 20,000 customers every weekday who depended on the existing infrastructure.

Photo: Caltrain

3 min to read


San Carlos, Calif.’s Caltrain, with its partners Pacific Gas and Electric Company (PG&E) and Balfour Beatty, energized and tested the full 51-mile Caltrain-owned corridor between San Francisco and San Jose.

The milestone achievement in the Caltrain Electrification Project signifies major progress in expanding agency’s ability to test electric trains at full speed along the corridor and prepare for electrified revenue service in September 2024. 

Ad Loading...

“The completion of the Overhead Catenary System allows us to test electric trains along our entire corridor,” said Caltrain Executive Director Michelle Bouchard. “This is a momentous step in the Caltrain Electrification project as we approach the launch of electrified service in fall 2024.”

Electrifying Caltrain

Caltrain has built two main traction power substations, one in San Jose and the other in South San Francisco.

Together, with one switch station and seven parallel stations along the corridor, power substations provide, distribute, and regulate electricity to the overhead wires, which will power Caltrain’s new high-performance electric trains.

Caltrain, PG&E, and Balfour Beatty’s work to complete the energization was substantial, needing to be safely conducted while maintaining rail service to more than 20,000 customers every weekday who depended on the existing infrastructure.

PG&E infrastructure upgrades include: 

Ad Loading...
  • Constructing two, double-circuit 115 kV transmission connections from the East Grand Substation in South San Francisco and the FMC Substation in San Jose to Caltrain traction power stations in those communities.

  • Rebuilding the East Grand and FMC substations that enabled PG&E to support Caltrain’s request for redundant transmission feeds.

  • Upgrading three PG&E and two third-party remote end substations.

Public Outreach, Better Service

As crews continue to test electric trains along the corridor, Caltrain is embarking on a public outreach campaign to educate passengers, residents, and businesses about best safety practices along the corridor.

The agency has sent out mailers, hosted community meetings and embarked on social media campaigns to remind everyone that all overhead wires on Caltrain property should be assumed to be energized now.

Caltrain’s historic Electrification Project is the first undertaking in North America in a generation in which diesel trains and their infrastructure components are transitioned to an electrified system.

Electrification means faster and more frequent service, including doubling the frequency on weekends. The passenger experience will be greatly improved as well with the new trains featuring Wi-Fi, power outlets at every seat, onboard displays with digital trip information, and increased storage capacities.  

Ad Loading...

Electrification will also help meet ambitious regional and state climate action goals by lowering greenhouse gas emissions, improving air quality, and relieving traffic congestion.

Additionally, electrified service will advance equity as well as sustainability along the corridor by reducing noise and air pollution while increasing access for priority equity communities. It will also set the framework for California’s future high-speed rail network that will run on the Caltrain corridor.

Caltrain recently began offering four new fare promotions, offering discounts for families, groups, youth, and hybrid workers.

More Rail

Railby StaffFebruary 2, 2026

Chicago Region Transit Ridership Grows in 2025

The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.

Read More →
Managementby StaffJanuary 29, 2026

Valley Metro Sees Strong Ridership Growth in 2025

The agency ranked top five among mid-sized U.S. transit systems, defined as agencies with 15 million to 50 million annual trips.

Read More →
Busby StaffJanuary 29, 2026

Subway Customer Satisfaction Reaches Record High, New York MTA Says

The subway system saw increases across all key metrics, with 62% of subway riders reporting they feel satisfied with the system overall.

Read More →
Ad Loading...
Managementby StaffJanuary 27, 2026

Keolis Retains Virginia Railway Express Contract

The new contract for Keolis and VRE will commence in July 2026, with the potential to expand to 15 years.

Read More →
Busby StaffJanuary 27, 2026

California's OCTA Advances 2026 Initiatives Centered on Balance and Sustainability

The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.

Read More →
Railby Staff and News ReportsJanuary 26, 2026

People Movement: Virginia's DRPT Names New Director and More

In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
Ad Loading...
ManagementJanuary 23, 2026

Seattle Sound Transit Sets Launch Date for Crosslake Connection

This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.

Read More →
A blue and white graphic with a map of the proposed study area for the Sepulveda Transit Corridor and text reading "LA Metro Approves Underground Rail for Sepulveda Transit Corridor."
RailJanuary 23, 2026

LA Metro Approves Underground Rail for Sepulveda Transit Corridor

The agency’s selection aims to slash travel times from the San Fernando Valley to the Westside to under 20 minutes.

Read More →
TechnologyJanuary 21, 2026

Florida's Tri-Rail Taps Siemens Mobility for Modern Locomotive Procurement

Expected to enter service in 2029, these locomotives support the agency’s commitment to offer reliable and efficient rail transportation across South Florida.

Read More →
Ad Loading...
Rendering of an Austin Light Rail station.
RailJanuary 20, 2026

Austin Transit Partnership Advances Federal Funding Process for Light Rail Project

See how the agency’s transit project completed a Final Environmental Impact Statement within the federal two-year guideline.

Read More →