DART Green Line rail project heading into final stretch
Bolstered by the receipt of $78.4 million in ARRA funds, the Green Line rail project is headed for on-time and on-budget arrival at four new stations on Sept.14, 2009.

Congresswoman Eddie Bernice Johnson speaks at a press conference at the future Fair Park Station as DART Board Chairman Randall Chrisman and DART President/Executive Director Gary Thomas look on.
[IMAGE]DART-station-2-full.jpg[/IMAGE]Bolstered by the receipt of $78.4 million in funds from the American Recovery and Reinvestment Act (ARRA), the Dallas Area Rapid Transit (DART) Green Line rail project of is headed for on-time and on-budget arrival at four new stations on September 14, 2009.
The first section of the $1.8 billion Green Line will extend from Pearl Station on the east side of Downtown Dallas to Deep Ellum Station, Baylor University Medical Center Station, Fair Park Station (at the intersection of Parry and Exposition) and the MLK Station, adjacent to the J. B. Jackson Jr. Transit Center on the east site of Fair Park. It restores rail service to a neighborhood that 50 years ago was home to up to four rail lines. Daily service to Victory Station will also begin September 14.
The remaining 25 miles of the Green Line, scheduled to open in December 2010, will extend southeast to Pleasant Grove and northwest from Victory Station to the Dallas Market Center, the Southwestern Medical District, Love Field Airport and downtown Farmers Branch, and Carrollton. Construction of the Green Line, the longest light rail project under construction in North America, has produced more than 2,200 construction jobs.
Major funding for the Green Line comes from a $700-million Full Funding Grant Agreement (FFGA) from the Federal Transit Administration. The FFGA was first awarded in July 2006 at the start of Green Line construction. The funds awarded under the ARRA are part of DART’s FFGA.
Construction is also under way on the first nine miles of a new Orange Line that will branch from the Green Line in northwest Dallas to serve the city of Irving in 2011. The line will be extended to DFW International Airport by 2013. DART also is building a five-mile extension of the Blue Line from Garland to Rowlett that will open in 2012.
These lines are earning national attention as well. The Orange Line is among the first projects slated to receive funds – more than $61 million – under the ARRA. Altogether, the Green, Orange and Blue line projects are expected to add 60,000 weekday passenger trips, nearly doubling ridership on the DART Rail System.
More Rail

Biz Briefs: STV teams with Amtrak, Motorcoach Operators Boost Fleet and Land Contracts, and More
From manufacturers and suppliers to transit agencies and motorcoach operators, these updates offer a snapshot of the projects, partnerships and business moves driving the industry forward.
Read More →
Metra Celebrates 100 Years of Electric Rail, Looks to the Future
The event was also a celebration of recent reforms to public transportation in the Chicago area, changes that could be as transformative in the future as the major civic achievement a century ago, said officials.
Read More →
LA Metro Marks Banner Year, Sets Ambitious Goals for New Fiscal Year
Incoming LA Metro Board Chair and Los Angeles Mayor Karen Bass joined outgoing Board Chair Fernando Dutra and LA Metro CEO Stephanie Wiggins to review accomplishments from fiscal year 2026, which included the opening of new rail extensions, advancement of major transit projects, expanded safety programs, and new rider amenities.
Read More →
DART Taps Nathaniel P. Ford Sr. as Next President/CEO
Since 2012, Ford has served as the CEO of the Jacksonville Transportation Authority
Read More →
California High-Speed Rail Authority Signs MOU to Advance High Desert Corridor
The agreement deepens collaboration between the California High-Speed Rail Authority and the High Desert Corridor Joint Powers Agency, supporting design integration, cost savings, and faster delivery of a key Southern California rail link.
Read More →
Building the Next Generation of Transit Technology
In this edition of METROspectives, Luminator CEO Magnus Friberg discusses the company's transformation, the growing role of AI and software, and what's next for transit technology.
Read More →How Data, Strategy, and Community Engagement Are Reshaping Transit
In this edition of METROspectives, strada360 CEO Steve Lassey discusses how transit agencies can better align planning with operations, leverage data to improve decision-making, and build public trust as they prepare for the future of mobility.
Read More →
TTC Launches Camera Pilot to Curb Illegal Passing of Streetcars
During the pilot, the cameras will measure how often illegal streetcar passing occurs and test the technology's reliability for future automated enforcement.
Read More →
NJ TRANSIT Secures Capital Funding, Adopts FY2027 Budget
The budgets continue investments in infrastructure and equipment to maintain the system in a state of good repair and enhance the overall customer experience.
Read More →
Biz Briefs: Masabi Teams with St. Louis Metro and More
In METRO's latest installment, we take a look at recent news from Transdev, Hitachi, and more partnerships making headlines across the transportation sector.
Read More →