Amtrak Completes First Street Tunnel Upgrades, Restores Service
The nine-day construction project included replacing aging track infrastructure and modernizing switch systems near Washington Union Station.

The completed improvements support passenger rail operations between Washington and Virginia, where Amtrak and commuter rail services share critical infrastructure.
Amtrak/METRO
Amtrak has completed infrastructure upgrades in the First Street Tunnel south of Washington Union Station, restoring train operations following a nine-day construction period.
The project, known as "Pause for Progress," required temporary service changes for trains traveling south of Washington, D.C., from October 16-26. The work focused on replacing aging infrastructure at A-Interlocking, a critical track and control point for Amtrak and Virginia Railway Express (VRE) trains operating between Washington and Virginia.
“This concentrated construction period allowed our teams to make significant improvements to critical infrastructure while limiting the amount of time it was out of service,” said Amtrak Executive Vice President, Strategy and Planning Jennifer Mitchell. “We’re grateful to Virginia Railway Express (VRE), Virginia Passenger Rail Authority (VPRA), and North Carolina Department of Transportation (NCDOT) for working closely with us to coordinate service during the outage, and to our customers for their patience and flexibility as we completed this important work to improve reliability for years to come.”
Infrastructure Improvements Completed
The construction project involved replacing switches and crossovers, rehabilitating the tunnel's track base, and installing electric switch systems.
During the nine-day construction period, crews completed the following improvements:
- Installed eight electric switch machines, two double-slip switches, and one crossing diamond.
- Rehabilitated 350 feet of track and tunnel base.
- Installed 550 tons of ballast.
- Replaced 1,000 feet of rail and 215 ties.
- Installed 2,500 feet of signal and electrical cable.
According to Amtrak, crews logged approximately 13,300 work hours during the project. The improvements are intended to strengthen infrastructure reliability along a rail corridor serving intercity passenger and commuter operations.
Coordinating Service During Construction
Amtrak coordinated with VRE, VPRA, and NCDOT to accommodate service changes during construction. CSX, Norfolk Southern, and the Washington Metropolitan Area Transit Authority (WMATA) also supported operational adjustments.
“Amtrak and the Virginia Passenger Rail Authority worked with us to develop innovative solutions that kept passengers moving while these critical improvements were completed,” said Jason Orthner, NCDOT Rail Division director. “Those partnerships help us maintain service today while building a safer, more reliable rail network for the future.”
VRE CEO Katie Choe also emphasized the importance of coordination among the agencies involved.
“The completion of this work is an important milestone for everyone who relies on the rail network between Virginia and Washington, D.C. We appreciate the close collaboration between Amtrak, VPRA, and VRE to complete these critical upgrades,” Choe said.
Passenger Rail Service Resumes
With construction complete, Amtrak Virginia service has resumed ahead of the holiday travel season.
Amtrak Virginia operates six daily round trips connecting Washington, D.C., with Richmond, Roanoke, Norfolk, Newport News, and intermediate destinations, serving 17 stations across Virginia.
VPRA is also extending portions of the Amtrak Connection Express Bus service introduced during construction, providing additional transportation options for passengers.
The completed improvements support passenger rail operations between Washington and Virginia, where Amtrak and commuter rail services share critical infrastructure.
For additional project information, visit Amtrak's Pause for Progress page.
More Rail

FRA Announces $2.3B for Passenger, Freight Rail Projects Nationwide
The CRISI Grant Program funding will support rail infrastructure improvements, safety upgrades, and projects aimed at improving freight and passenger rail service across 45 states and Washington, D.C.
Read More →
Caltrain’s Electrification Drives a New Era of Ridership Growth
The railroad’s shift to electric service has brought more frequent trains, stronger customer satisfaction, and increased ridership, earning it APTA’s Outstanding Public Transportation System award.
Read More →
FTA Advances $164M Broward County Commuter Rail Project
The proposed 10.5-mile commuter rail extension would connect Fort Lauderdale and Aventura, expanding passenger rail options in South Florida.
Read More →
New York MTA Launches Historic $1.9B Signal, Track Modernization Project
Funded in part by congestion pricing revenue, the project will replace nearly century-old signals along the A and C lines in Brooklyn and Queens.
Read More →
LA Metro Breaks Ground on East San Fernando Valley Light Rail Project
The 6.7-mile line will add 11 stations along Van Nuys Boulevard, expand access to jobs and regional transit connections, and support Metro’s broader efforts to improve mobility as rail ridership grows.
Read More →
CSA Group Releases Climate Resilience Standard for Transit, Passenger Rail
Developed with support from the Standards Council of Canada, CSA D700 guides assessing climate-related risks and planning adaptation measures for transit and passenger rail systems.
Read More →
LA Metro September Ridership Climbs 3.9%, Led by Rail Growth
The agency recorded more than 27.2 million boardings, with rail ridership increasing 12.4% year over year and the D Line posting the largest gains.
Read More →
First Full MetroLink Rail Expansion Completed in 20 Years with $192M Airport Project
The project links two St. Louis-area airports by light rail while adding roadway and bike trail connections to improve regional access and mobility.
Read More →
Utilimarc Launches SmartReplace to Optimize Fleet Replacement Decisions
AI-powered SmartReplace helps fleets prioritize vehicle replacements, model budget scenarios, and build more defensible long-term strategies.
Read More →
Scenes from APTA TRANSform & EXPO 2026
Transit leaders, manufacturers, and industry professionals gathered in Chicago to explore new technologies, share ideas, and discuss the future of public transportation.
Read More →