Officials: MBTA Orange Line Work 82% Complete
Crews have worked tirelessly to finish tie replacement work between the Dana Bridge and Community College station with current tie replacement work taking place at the North Station portal, which began on September 9.

As of this week’s reporting, 82% of the planned work on the MBTA's Orange Line has been completed.
MBTA
Boston’s MBTA GM Steve Poftak announced 82% of the work taking place along the Orange Line is complete and track work taking place between Dana Bridge and North Station will allow for the removal of three more slow zones, which will bring the total number of slow zones removed to five.
Work taking place in this area includes track and tie replacement, rail installation, track alignment, and tamping. Crews have worked tirelessly to finish tie replacement work between the Dana Bridge and Community College station with current tie replacement work taking place at the North Station portal, which began on September 9. Tie replacement work involves crews operating hi-rail heavy equipment to remove old ties and install new ties. The critical tie replacement will remove three of the six slow zones that the T aims to address during the shutdown. Crews have already completed work to remove slow zones at Jackson Square and between Downtown Crossing and State. Finishing this important work and removing these slow zones allows for faster, more reliable service for Orange Line riders.
MBTA is letting Orange Line riders know that, when Orange Line trains begin running again on Monday, September 19, slow zones will continue to be in place temporarily for about one week where the work was performed. In the rail industry, after new track and ballast installation, and due to the amount of track area disturbed during work, it is a given that slow zones need to temporarily remain in place. This is because it takes time for the new track and ballast to “settle” as trains repeatedly run over these areas.
Additionally, 64 new Orange Line cars are now available when service resumes, supporting riders during peak commuting periods. This is up from 30 cars when the Orange Line shutdown first started. This is also over a full complement of new Orange Line cars ready to serve riders.
As of this week’s reporting, 82% of the planned work has been completed.
Overall, teams have completed approximately 65% of rail replacement and 90% of track replacement. The full depth track replacement includes the ballast, ties, and rail.
About 99% of the special track work is complete. The special track renewal work includes replacing things like crossover areas.
About 99% of Cologne eggs and rail fastener work is finished near Tufts Medical Center station. Cologne eggs are the fasteners that allow crews to directly affix rail to the concrete pads, which are also utilized on certain parts of the Orange Line. The MBTA is in the process of installing the final five new eggs with 395 fully complete.
There has also been excellent progress on the ongoing signal testing at Oak Grove and Malden Center stations with about 84% of these signal upgrades complete.
More Rail

Trinity Metro Breaks Ground on $270M TEXRail Extension
The 2.1-mile extension will connect Fort Worth’s Medical District and Near Southside to downtown, surrounding communities, and Dallas-Fort Worth International Airport.
Read More →
Bringing Austin’s First Light Rail System to Life
Austin Transit Partnership CEO Greg Canally discusses the city's nearly 10-mile light rail project, its collaborative approach to project delivery, the importance of community engagement, and the milestones ahead as construction approaches in 2027.
Read More →
Metra Draft Plan Outlines Costs, Service Improvements for Regional Rail
The Systemwide Network Plan identifies infrastructure needs and potential investments to expand all-day, bidirectional rail service across the Chicago region.
Read More →
Amtrak Completes First Street Tunnel Upgrades, Restores Service
The nine-day construction project included replacing aging track infrastructure and modernizing switch systems near Washington Union Station.
Read More →
FRA Announces $2.3B for Passenger, Freight Rail Projects Nationwide
The CRISI Grant Program funding will support rail infrastructure improvements, safety upgrades, and projects aimed at improving freight and passenger rail service across 45 states and Washington, D.C.
Read More →
Caltrain’s Electrification Drives a New Era of Ridership Growth
The railroad’s shift to electric service has brought more frequent trains, stronger customer satisfaction, and increased ridership, earning it APTA’s Outstanding Public Transportation System award.
Read More →
FTA Advances $164M Broward County Commuter Rail Project
The proposed 10.5-mile commuter rail extension would connect Fort Lauderdale and Aventura, expanding passenger rail options in South Florida.
Read More →
New York MTA Launches Historic $1.9B Signal, Track Modernization Project
Funded in part by congestion pricing revenue, the project will replace nearly century-old signals along the A and C lines in Brooklyn and Queens.
Read More →
LA Metro Breaks Ground on East San Fernando Valley Light Rail Project
The 6.7-mile line will add 11 stations along Van Nuys Boulevard, expand access to jobs and regional transit connections, and support Metro’s broader efforts to improve mobility as rail ridership grows.
Read More →
CSA Group Releases Climate Resilience Standard for Transit, Passenger Rail
Developed with support from the Standards Council of Canada, CSA D700 guides assessing climate-related risks and planning adaptation measures for transit and passenger rail systems.
Read More →