Sound Transit completes $1.9B Seattle rail tunnel link
There are now twin tunnels running 3.1 miles between downtown Seattle and the University of Washington. The contractor team, JCM U-Link Joint Venture, mined two tunnels about a mile long between the site of the future Capitol Hill Station and downtown Seattle. The project is about halfway complete and scheduled to open in 2016.
Sound Transit contractors have connected the University Link light rail tunnels with the Downtown Seattle Transit Tunnel (DSTT). The tunnel boring machine, nicknamed "Brenda," recently completed its one-mile trip on the second tunnel between Capitol Hill and downtown.
The tunnel-boring machine removal of a headwall between the mining operations and the DSTT means there are now twin tunnels running 3.1 miles between downtown Seattle and the University of Washington. The contractor team, JCM U-Link Joint Venture, mined two tunnels about a mile long between the site of the future Capitol Hill Station and downtown Seattle. A separate contractor completed the twin tunnels between UW and Capitol Hill in early April.
The contractors will now focus on completing 21 cross passages between the twin tunnels by early 2013.
Overall, the $1.9 billion project is about halfway complete and scheduled to open in 2016. Between now and then contractors have to finish stations at UW and Capitol Hill, install communications and power systems and test the new line.
The expansion with stations in the heart of Capitol Hill and the University of Washington will provide unparalleled speed and reliability through Seattle's most dense neighborhoods. A trip from Husky Stadium to Westlake will take six minutes and is expected to add 70,000 riders to the system by 2030.
The corridor includes three major universities/colleges — the University of Washington (UW), Seattle University and Seattle Central Community College (SCCC) — with a combined enrollment of more than 50,000 students.
More Rail

New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Read More →
San Diego MTS Breaks Monthly Trolley Ridership Record
Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.
Read More →
Report Examines NJ TRANSIT Reliability, Funding Challenges
The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.
Read More →
Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement
Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.
Read More →
Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More
In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.
Read More →
CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips
With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.
Read More →
Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations
Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.
Read More →
Amtrak Begins Major Construction at New York’s Sunnyside Yard
The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.
Read More →
Chicago Leaders Unveil Plans for O’Hare Airport Express Train
The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.
Read More →
OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor
The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.
Read More →