WMATA Reveals Yellow Line Reopening Date
The reopening will mark the completion of rehabilitation work on the Yellow Line tunnel and bridge between Pentagon and L'Enfant Plaza stations.

Construction crews have worked since September to mitigate water intrusion in the steel-lined tunnel and replace aging bridge bearings and expansion joints.
Photo: WMATA
The Washington Metropolitan Area Transit Authority (Metro) announced it is welcoming customers back to the Yellow Line on Sunday, May 7, 2023, beginning with the start of rail service at 7 a.m.
The reopening will mark the completion of rehabilitation work on the Yellow Line tunnel and bridge between Pentagon and L'Enfant Plaza stations, according to Metro's news release.
Following eight months of construction for safety repairs, customers will once again have a connection across the Potomac River between Virginia and DC, instead of only using the Blue Line. This will reduce travel times by as much as 15 minutes.
Initially, trains will run every eight minutes on weekdays, every 12 minutes after 9:30 p.m., and on weekends between Huntington and Mt Vernon Square. Blue+ service that has been operating between Huntington and New Carrollton will be discontinued once the Yellow Line reopens.
"I want to thank our customers for their patience while we completed this critical work to ensure safe, reliable service for decades to come," said Randy Clarke, Metro GM/CEO. "I'm also very proud and thankful to the dedicated women and men who worked to deliver this complex project on schedule and on budget."
Construction crews have worked since September to mitigate water intrusion in the steel-lined tunnel and replace aging bridge bearings and expansion joints. The work included replacing over 1,000 individual steel plates held together by more than 12,000 bolts in the tunnel and replacing 88 bearings on the bridge.
The project also upgraded the fire suppression system on the 3,000-foot bridge and removed and replaced miles of critical communications cables used by multiple regional partners.
More Rail

NJ TRANSIT Approves $65.6M for Hudson-Bergen Light Rail Improvements
The funding marks the first phase of a planned $250 million investment over five years to modernize stations, overhaul vehicles, and improve system reliability and passenger safety.
Read More →
STraffic Expands North American Presence with Fare Collection Technology
John Moon, Associate Director, Product Strategy at STraffic, discusses the company's growth in North America, its efforts to reduce fare evasion, and more.
Read More →
Study: Denver RTD Generates $2.1 Billion in Annual Economic Activity
An economic impact study finds the agency supports approximately 17,500 jobs, delivers $1.6 billion in annual community and mobility benefits, and generates $2.42 in economic value for every dollar invested.
Read More →
Mark Aesch Nominated to Lead Federal Transit Administration
The former Rochester transit chief and TransPro founder, who has also contributed to METRO Magazine, brings decades of industry experience and a focus on performance, accountability, and financial sustainability to the nomination.
Read More →
Transit Expands Agency Partnerships, Reaching 200 Official App Partners
COO Jake Sion discusses Transit’s growth, the success of its Transit Royale program, and how technology is helping agencies improve the rider experience.
Read More →
Trinity Metro Breaks Ground on $270M TEXRail Extension
The 2.1-mile extension will connect Fort Worth’s Medical District and Near Southside to downtown, surrounding communities, and Dallas-Fort Worth International Airport.
Read More →
Bringing Austin’s First Light Rail System to Life
Austin Transit Partnership CEO Greg Canally discusses the city's nearly 10-mile light rail project, its collaborative approach to project delivery, the importance of community engagement, and the milestones ahead as construction approaches in 2027.
Read More →
Metra Draft Plan Outlines Costs, Service Improvements for Regional Rail
The Systemwide Network Plan identifies infrastructure needs and potential investments to expand all-day, bidirectional rail service across the Chicago region.
Read More →
Amtrak Completes First Street Tunnel Upgrades, Restores Service
The nine-day construction project included replacing aging track infrastructure and modernizing switch systems near Washington Union Station.
Read More →
FRA Announces $2.3B for Passenger, Freight Rail Projects Nationwide
The CRISI Grant Program funding will support rail infrastructure improvements, safety upgrades, and projects aimed at improving freight and passenger rail service across 45 states and Washington, D.C.
Read More →