Denver's RTD gets Fed approval for next phase of G Line testing

Testing will soon simulate the full daily service schedule of nearly 21 consecutive hours each day.

July 23, 2018
Denver's RTD gets Fed approval for next phase of G Line testing

The authorization given to RTD and its contractor, Denver Transit Partners (DTP), represents another significant step forward in the process to open the commuter rail line for passenger service.

Denver RTD

2 min to read


The authorization given to RTD and its contractor, Denver Transit Partners (DTP), represents another significant step forward in the process to open the commuter rail line for passenger service. Denver RTD

Denver’s Regional Transportation District (RTD) received approval from the Federal Railroad Administration (FRA) to begin the next phase of testing on the G Line. Beginning late last week, testing is ramping up and will soon simulate the full daily service schedule of nearly 21 consecutive hours each day.

The authorization given to RTD and its contractor, Denver Transit Partners (DTP), represents another significant step forward in the process to open the commuter rail line for passenger service.

Ad Loading...

Limited testing along the forthcoming 11.2-mile line between Union Station and Wheat Ridge began last fall and has been underway between on weekdays since the start of this year. That process has examined the communication signaling along the line, as well as the effectiveness of the communication technology in place at each of the G Line’s 16 at-grade railroad crossings. The gate-crossing technology is the same as that used along two additional lines originating in downtown Denver: the University of Colorado A Line to Denver International Airport, and the B Line to Westminster.

“We are pleased to have arrived at this phase in the testing schedule, and we continue to appreciate the patience of the public, businesses and leaders in the communities along the G Line as we work through all of the necessary details,” said RTD CEO/GM Dave Genova. An opening date for the G Line has not yet been announced.

As many as three trains will be running on the alignment every day, for an initial period intended to help train operators become familiar with the line. During this time frame, trains will operate every half hour starting as early as 3:30 a.m. and extending through 1 a.m. the following day. With more trains running for longer periods of time throughout the day, the RTD is urging the public to exercise caution as they move and drive through the area.

The official start to the next phase of G Line testing — simulating full passenger service — will follow this initial period. A date for the start of that phase has not been determined.

When the G Line officially opens — which also has yet to be determined — trains will run from 4 a.m. to 12:30 a.m., with 15-minute frequency between 6 a.m. and 6:30 p.m. and every 30 minutes during off-peak hours.

Ad Loading...

The line is a segment of RTD’s FasTracks program, a voter-approved transit expansion initiative to build new commuter rail and light rail, bus rapid transit service and new parking spaces; redevelop Denver Union Station; and redirect bus service to better connect the eight-county district.

 

 

More Rail

Aerial view of Caltrain's electric service.
Railby StaffJune 5, 2026

Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures

The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.

Read More →
Alstom purchasing site for Acela network manufacturing
Railby StaffJune 4, 2026

Alstom Acquires Delaware Site to Support Amtrak NextGen Acela Fleet

The company is investing more than $55 million to acquire and improve the property and will employ approximately 100 people at this site once it is operational.

Read More →
World Cup Crowds Will Test Transit Systems
ManagementJune 3, 2026

When Routine Fails: How Public Transit Must Adapt for the World Cup

The 2026 FIFA World Cup will test transit agencies’ ability to manage unpredictable travel patterns, making real-time data and operational flexibility critical to moving millions of visitors efficiently.

Read More →
Ad Loading...
A rendering of a California High-Speed Rail vehicle
Railby StaffJune 2, 2026

California Selects Team for Nation’s First True High-Speed Rail Track and Systems Contract

The board action follows completion of track installation at the 150-acre southern railhead in Kern County, which will serve as the staging and distribution hub for high-speed track and systems installation.

Read More →
Sound Transit Sounder train
Railby StaffJune 2, 2026

Seattle's Sound Transit Launches New Sounder Railcars into Service

Alstom manufactured all the cars under a $46.5 million contract and came into service in anticipation of summer crowds for soccer and baseball.

Read More →
Railby StaffJune 2, 2026

Alstom Partners With Universities to Build Rail Talent Pipeline

The partnerships include a new engineering scholarship fund at Alfred State College in Western New York and collaborations with transportation centers at the University of Pennsylvania and New York University.

Read More →
Ad Loading...
Managementby StaffJune 1, 2026

Chicago's NITA Act Moves Into Next Phase as Service Improvements Begin

Rider-focused improvements will begin rolling out across the system immediately as CTA, Metra, and Pace increase service this summer in the six-county region.

Read More →
Managementby StaffMay 29, 2026

Seattle’s Sound Transit Adopts Updated ST3 System Plan

The updated system plan incorporates cost savings across the agency, including new revenue sources and financial policies, to set the agency on a sustainable path for the future.

Read More →
An EMBARK bus going down the street.
Managementby Alex RomanMay 28, 2026

Inside Look: EMBARK Expands Fare-Free Transit Program Through New Public-Private Partnership

The OKC transit agency says sponsorship helps subsidize the Third Friday Free initiative while reducing barriers for first-time riders and boosting ridership across buses, streetcars, and river cruises.

Read More →
Ad Loading...
Managementby StaffMay 27, 2026

North Carolina's Metropolitan Transit Commission Concludes Decades of Leadership

To commemorate the occasion, current members of the MTC were presented with a custom painting of the Charlotte Transportation Center in Uptown.

Read More →