Caltrain Continues to Successfully Test Electric Trains

The testing will allow the agency to ramp up the testing of the new fleet as the launch of electrified service this fall grows closer.

Caltrain Continues to Successfully Test Electric Trains

Each of Caltrain's 23 electric trainsets must complete 1,000 miles of testing before it is allowed to carry passengers.

Photo: Caltrain

3 min to read


San Carlos, Calif.’s Caltrain met another milestone in the electrification of its system, as it successfully tested electric trains and overhead wires between Redwood City and Mountain View for the first time. 

The testing will allow the agency to ramp up the testing of the new fleet as the launch of electrified service this fall grows closer.

Ad Loading...

Live run tests started at five miles per hour, to ensure the overhead wire and train are properly connected. Once the connection was successfully established, the train increased speed to the corridor’s 79 mile per hour maximum limit.

Twenty-five such test runs were successfully completed over the course of last weekend.

Moving Electrification Along

Each of the 23 electric trainsets must complete 1,000 miles of testing before it is allowed to carry passengers.

Initial tests were conducted between Santa Clara and College Park Stations on the Santa Clara Drill Track, but Caltrain has steadily been expanding the available testing area from San Jose to Mountain View.

With this live run, testing can now take place from San Jose to Redwood City, further accelerating the process and keeping the launch of service on schedule for fall 2024.

Ad Loading...

“Another test completed marks another step toward a reliable, fast and frequent service for our riders,” said Caltrain Executive Director Michelle Bouchard. “I cannot wait for everyone to get to experience the modernized, zero-emission fleet of Caltrain’s future for themselves this fall.”

Benefits of Electric Trains

Electric trains are quieter than Caltrain’s current diesel fleet, so the public is advised to pay close attention when crossing the tracks and to always wait for the gate to fully rise before crossing.

Caltrain’s historic Electrification Project is the first undertaking in North America in a generation in which diesel trains and their infrastructure components are transitioned to an electrified system.

Electrification means faster and more frequent service, including doubling the frequency on weekends. The passenger experience will be greatly improved as well with the new trains featuring Wi-Fi, power outlets at every seat, onboard displays with digital trip information, and increased storage capacities.  

Electrification will also help meet ambitious regional and state climate action goals by lowering greenhouse gas emissions, improving air quality, and relieving traffic congestion.

Ad Loading...

Additionally, electrified service will advance equity along the corridor by reducing noise and air pollution while increasing access for priority equity communities. It will also set the framework for California’s future high-speed rail network that will run on the Caltrain corridor.

The proposed electrification service plan includes 70 weekday peak hour trains, an increase from the current 66.

Eleven stations would see four train arrivals hourly per direction, up from seven stations currently. Midday trains would cover 44 stations per hour, up from 34 today and weekend service will arrive every half hour, rather than hourly.

More Rail

Railby StaffFebruary 2, 2026

Chicago Region Transit Ridership Grows in 2025

The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.

Read More →
Managementby StaffJanuary 29, 2026

Valley Metro Sees Strong Ridership Growth in 2025

The agency ranked top five among mid-sized U.S. transit systems, defined as agencies with 15 million to 50 million annual trips.

Read More →
Busby StaffJanuary 29, 2026

Subway Customer Satisfaction Reaches Record High, New York MTA Says

The subway system saw increases across all key metrics, with 62% of subway riders reporting they feel satisfied with the system overall.

Read More →
Ad Loading...
Managementby StaffJanuary 27, 2026

Keolis Retains Virginia Railway Express Contract

The new contract for Keolis and VRE will commence in July 2026, with the potential to expand to 15 years.

Read More →
Busby StaffJanuary 27, 2026

California's OCTA Advances 2026 Initiatives Centered on Balance and Sustainability

The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.

Read More →
Railby Staff and News ReportsJanuary 26, 2026

People Movement: Virginia's DRPT Names New Director and More

In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
Ad Loading...
ManagementJanuary 23, 2026

Seattle Sound Transit Sets Launch Date for Crosslake Connection

This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.

Read More →
A blue and white graphic with a map of the proposed study area for the Sepulveda Transit Corridor and text reading "LA Metro Approves Underground Rail for Sepulveda Transit Corridor."
RailJanuary 23, 2026

LA Metro Approves Underground Rail for Sepulveda Transit Corridor

The agency’s selection aims to slash travel times from the San Fernando Valley to the Westside to under 20 minutes.

Read More →
TechnologyJanuary 21, 2026

Florida's Tri-Rail Taps Siemens Mobility for Modern Locomotive Procurement

Expected to enter service in 2029, these locomotives support the agency’s commitment to offer reliable and efficient rail transportation across South Florida.

Read More →
Ad Loading...
Rendering of an Austin Light Rail station.
RailJanuary 20, 2026

Austin Transit Partnership Advances Federal Funding Process for Light Rail Project

See how the agency’s transit project completed a Final Environmental Impact Statement within the federal two-year guideline.

Read More →