METRO Magazine Logo
MenuMENU
SearchSEARCH

Brampton, Ontario 'Züms' toward boosting ridership with BRT service

The Züm service will be completely integrated into Brampton's existing transit system. Passengers will be able to ride the buses at no extra cost and transfer quickly and easily between lines.

by Brittany-Marie Swanson, Assistant Editor
November 19, 2010
Brampton, Ontario 'Züms' toward boosting ridership with BRT service

Phase one of the project will introduce 61 new buses to Brampton's transit system. These will serve the three Züm lines opening over the course of the project's first phase, including the now operational Queen St. corridor.

3 min to read


[IMAGE]MET11news-zum-2.jpg[/IMAGE]The City of Brampton in Ontario, Canada, has seen its transit ridership grow at approximately three times the national average since 2005. For 2010, the ridership increase stands at 12 percent to date. Since the passing of the Transportation and Transit Master Plan in 2004, the city has been striving to better streamline its public transit by introducing a grid-based system and, most recently, a bus rapid transit (BRT) service called Züm (pronounced "zoom").

The first Züm line opened in September on Queen St., one of Brampton's major transit corridors, coinciding with the highest ridership of the city's public transportation in history. The remainder of the Züm service will be introduced over the project's two phases.

Ad Loading...

"Our city is growing rapidly — it's one of the fastest growing cities in Canada," said Sue Connor, director of transportation for Brampton Transit. "We've compared our ridership to the growth of the city. Up to this point, we've been gaining about 25 percent new riders, and we think that's going to increase now that this new Züm service is in place."

Phase one of the project will introduce 61 new buses to Brampton's transit system. These will serve the three Züm lines opening over the course of the project's first phase, including the now operational Queen St. corridor. In 2011, Züm will begin serving Main St.; phase one will be completed in 2012 with the addition of a Züm line on Steeles Avenue.

In 2012, when Züm begins serving Steeles Ave., the city will begin to employ 60-foot articulated vehicles.  

"After we get through the first phase, because of passenger volumes, we'll be needing 60-foot buses," Connor explained. At completion, the Züm service will include 65 articulated buses that are 60 feet in length and 41 conventional buses 40 feet in length.

"And on top of that, we have 238 buses in our conventional fleet as well," Connor adds.

Ad Loading...

The Züm service will be completely integrated into Brampton's existing transit system. Passengers will be able to ride Züm buses at no extra cost and transfer quickly and easily between lines.

"The Züm BRT lines will run in the major corridors throughout the city — east, west, north, south — and then on the major arterial roads feeding into those lines. We have conventional service, which is upgraded to a 10-minute frequency," Connor said.

Brampton's entire transit system has also been updated to include real-time information for passengers. GPS in each bus helps the city to track any delays and make service adjustments accordingly.  

Each Züm bus is equipped with a security camera, LED headlights and a visual and audible stop announcement system. The interiors have been branded with the Züm logo and according to third-party testing, the buses have the lowest interior noise ever recorded.

The New Flyer-manufactured Züm vehicle is a hybrid-diesel and "the first bus in North America to have an electronic instrumental panel," Connor says. Brampton is the first city in North America to employ this vehicle model, which has "10 percent less weight than a normal, conventional bus on the market right now." Connor said the city is expecting an 8 to 10 percent drop in fuel consumption due to the vehicle's efficiency boosting features.

Ad Loading...

The $285 million Züm project will include the construction of transit infrastructure at major intersections for BRT use that will include queue jump lanes, bus bays, station stops and major technology upgrades. A Züm route on Bovaird — part of phase two - is due to be completed in 2014.

"The buses get really positive feedback," Connor continued. "Our challenge now is convincing people to move out of cars, out of that congestion and get on our buses. We're doing that by selling the control, the comfort and the convenience that the Züm service provides."

 

Subscribe to Our Newsletter

More Bus

Community Transit's Bluebell bus celebrating the agency's 50-year milestone.
Busby StaffMay 15, 2026

Washington's Community Transit Celebrates 50-Year Milestone

The milestone highlights both the agency’s history and its evolving role in meeting the region’s growing mobility needs.

Read More →
The groundbreaking event for St. Cloud, Minnesota's Metro Bus facility.
Busby StaffMay 13, 2026

Minnesota's Metro Bus Breaks Ground on New Transit Facility

The new facility will augment the current Metro Bus Transit Center and overall system as part of new routes and service improvements known as Metro Bus Forward.

Read More →
An NJ TRANSIT bus.
Managementby StaffMay 13, 2026

NJ TRANSIT to Expand Cleanliness, Safety, and Accessibility Under New Action Plan

The plan includes investments in cleaner vehicles and upgraded stations, NJT LiveView to provide real-time GPS tracking of train and light rail service, enhanced safety initiatives through a new Real Time Crime Center, and the debut of a redesigned NJ TRANSIT mobile app.

Read More →
Ad Loading...
Mayor Tim Keller in front of an ABQ RIDE microtransit vehicle
New Mobilityby StaffMay 12, 2026

ABQ RIDE Forward's Next Phase Sets Target Date

ABQ RIDE Forward is the first transit system overhaul in more than 25 years. This latest phase marks 15% completion of the 16-phase rollout, which will continue over the next several years.

Read More →
METRO Biz Briefs cover photo

STV Launches Power Practice and More in Biz Briefs

In METRO's latest installment, we take a look at the latest news from SilverRide, Complete Coach Works, and more.

Read More →
Cover for Part 2 with AC Transit's Cecil Blandon
ManagementMay 8, 2026

Bus Tech Talk: Part 2 with AC Transit's Cecil Blandon

In Part 2 of a two-part conversation, AC Transit’s director of maintenance joins co-hosts Alex Roman and Mark Hollenbeck to discuss his maintenance team’s work with various types of vehicle, training, augmented reality, and more.

Read More →
Ad Loading...
Maintenance officials examining a vehicle on a lift.
Managementby Alex RomanMay 8, 2026

Avoiding Mid-Season Breakdowns: A Fleet Readiness Q&A

John Hatman, COO of Master’s Transportation, breaks down the priorities, warning signs and common mistakes fleet managers should address now to stay ahead of summer demand.

Read More →
SEPTA's advertisement for multi-rider feature.
Technologyby StaffMay 7, 2026

Philadelphia's SEPTA Introduces Multi-Rider Feature for Contactless Payments

Up until now, this feature was only available when using a SEPTA Key card.

Read More →
Rendering of the upgraded Derby-Shelton Train Station
Busby StaffMay 4, 2026

CTDOT Launches Four-Station Upgrades on Waterbury Line

Construction on all four stations is beginning now and is anticipated to be completed by spring 2028.

Read More →
Ad Loading...
East Colfax BRT
Busby StaffMay 4, 2026

Denver RTD breaks ground on Aurora segment of East Colfax BRT

The beginning of the final BRT segment advances construction across all five segments, reflecting steady progress toward shorter travel times, improved accessibility, and a more dependable connection to jobs, businesses, and community destinations.

Read More →