SoCal Extension Breathes New Life Into Congested Corridor

The 91/Perris Valley Line is expected to replace thousands of vehicle trips along I-215 as well as I-15 and connecting State Route 91 and SR 60.

by By Richard Quirk, AIA
September 20, 2016
SoCal Extension Breathes New Life Into Congested Corridor

Images courtesy STV Inc.

4 min to read


Images courtesy STV Inc.

For the first time in more than 20 years, Southern California’s Metrolink commuter rail launched a new line into Riverside County, providing drivers in the heavily congested corridor a long-awaited alternative.

The new 91/Perris Valley Line began regular service in June — about 15 years after it was first proposed.

Ad Loading...

The new line, which parallels Interstate 215 along a 24-mile route from Riverside to Perris, features four new commuter stations, expanding access for thousands of new Metrolink riders along the I-215 corridor. The extension expands Metrolink service across 536 miles of the region and connects to three of its existing rail lines providing access to San Bernardino, Orange County and Los Angeles. This was accomplished by linking the Burlington Northern Santa Fe (BNSF) main line and the Riverside Downtown Station to the 21-mile San Jacinto Branch Line running south to Perris through a new 1,900-foot rail segment known as the Citrus Connection.

The 91/Perris Valley Line is expected to replace thousands of vehicle trips along I-215 as well as I-15 and connecting State Route 91 and SR 60.

In announcing the new service, Metrolink board Vice Chairman and Riverside County Transportation Commission (RCTC) member Daryl R. Busch, who also serves as mayor of Perris, hailed the extension as not only a way to ease congestion in the area, but as a means to spur economic growth. “There couldn’t be a better place for new train service,” said Busch. “This is a prime area for business and economic development and Metrolink will make it an even more attractive place to create jobs and transit-friendly housing.”


Projected growth
Current ridership on the line is projected to grow to more than 4,000 daily riders. Direct service between Union Station and South Perris takes a little over two hours to make the approximately 75-mile trip. Metrolink is currently offering discounted fares to help promote the service.

Ad Loading...

STV has been a partner with the RCTC since the 91/Perris Valley Line extension was first proposed in 2001, and was contracted by the commission to perform planning, environmental studies and reports, as well as the necessary engineering and construction support since the project broke ground in late 2013.

The extension was funded through federal, state and a special sales tax in Riverside County. It was one of the first projects to win funding under the Federal Transit Administration’s Small Starts program. STV helped prepare the documents, many of which have been used as templates for other Small Starts projects throughout the country.

“This extension will make a big difference in the quality of life for residents who want an alternative to sitting in traffic, and it also lays a strong foundation for economic development along the corridor,” said Therese McMillan, the acting administrator of the FTA at the time, who now serves as chief planning officer for the Los Angeles Metropolitan Transportation Agency.

Extensive Improvements
In addition to the four stations at Riverside-Hunter Park, Moreno Valley/March Field, Downtown Perris and South Perris, the new line required extensive improvements at existing grade crossings and culverts, installation of new traffic signals, the replacement of two bridges along the SJBL along the San Jacinto River, and the construction of communication towers and landscape and sound attenuation walls.

The new line was also praised by the American Planning Association’s Inland Empire Section, which recognized it with its Hard Won Victories Award. The award was given to the RCTC for its planning efforts in demonstrating how a plan can be developed and endorsed amid varying viewpoints.

Ad Loading...

The STV team designed the rail line’s four new stations in close collaboration with RCTC and Metrolink. Stations feature 510-foot-long platforms with canopies, ADA and safety amenities, including level boarding, ticket kiosks, scheduling information and parking ranging from about 450 to 900 cars. Built with flexibility and future expansion in mind, the stations accommodate platforms up to 850 feet long as well as double-tracking and second platforms in certain areas.

Safety Standards
In addition, STV worked with the RCTC and Metrolink to uphold stringent safety standards by replacing miles of worn track, upgrading multiple grade crossings and improving the line’s signal system, including design considerations for the implementation of Positive Train Control (PTC). Work also included designing a new layover facility for locomotive maintenance and inspection areas in South Perris.

The 91/Perris Valley Line extension is Metrolink’s first new expansion project since construction of the Antelope Valley Line in 1994. Since that time, STV has served as the general engineering consultant for the rail service, performing planning, engineering design, and program and construction management for various key assignments throughout the system’s development. Metrolink currently serves more than 44,000 daily riders, with more than 75% switching from cars to transit.

Richard Quirk, AIA is senior architect/project manager with STV Inc. (www.stvinc.com)

Subscribe to Our Newsletter

More Rail

A New York MTA subway car with an open gangway
Railby Staff and News ReportsSeptember 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →
A San Diego MTS Copper Line vehicle
Railby Staff and News ReportsSeptember 15, 2026

San Diego MTS Breaks Monthly Trolley Ridership Record

Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.

Read More →
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Railby Alex RomanSeptember 14, 2026

Report Examines NJ TRANSIT Reliability, Funding Challenges

The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.

Read More →
Ad Loading...
A CapMetro commuter rail train provided by Stadler
Railby Staff and News ReportsSeptember 11, 2026

Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement

Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.

Read More →
Rendering of an Alstom train in a VIA Rail Station
Technologyby Alex RomanSeptember 10, 2026

Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More

In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.

Read More →
The CATS Gold Line in service with the city skyline in the background.
Railby Staff and News ReportsSeptember 3, 2026

CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips

With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Amtrak Sunnyside Groundbreaking
Railby Staff and News ReportsSeptember 2, 2026

Amtrak Begins Major Construction at New York’s Sunnyside Yard

The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.

Read More →
O'Hare Flyer Rendering
Railby Staff and News ReportsAugust 27, 2026

Chicago Leaders Unveil Plans for O’Hare Airport Express Train

The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.

Read More →
Ad Loading...
An OCTA coastal rail line train.
Railby Staff and News ReportsAugust 27, 2026

OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor

The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.

Read More →