N.Y. Fulton St. Transit Center continues progress

The $1.4 billion project is more than 60% complete, and will improve travel for nearly 300,000 commuters, residents and visitors.

April 12, 2012
N.Y. Fulton St. Transit Center continues progress

The installation of the parasols at the top of the Transit Center oculus (shown), which will be used to direct sunlight down to the lowest levels of the Transit Center, has been completed. All photos courtesy MTAPhotos. MTAPhotos.

2 min to read


The installation of the parasols at the top of the Transit Center oculus (shown), which will be used to direct sunlight down to the lowest levels of the Transit Center, has been completed. All photos courtesy MTAPhotos. MTAPhotos.

New York's Metropolitan Transportation Authority's construction of the new Fulton Street Transit Center that will improve travel for nearly 300,000 commuters, residents and visitors to Lower Manhattan and better link 10 subway lines to PATH service and the World Trade Center site.

The Transit Center is more than 60% complete and on track for its scheduled June 2014 completion. The $1.4 billion project will feature 70,000 square feet of shops, restaurants and office space, as well as offer street-level ADA accessible entrances and include restoration of the historic Corbin Building, an 1888 landmark.

According to MTA officials, construction at the Transit Center building continues to progress well. The curtain wall of the building is being installed, with some of the steel mullions already in place and exterior glass delivery beginning this month. The installation of the parasols at the top of the Transit Center oculus, which will be used to direct sunlight down to the lowest levels of the Transit Center, has been completed.

Across the street from the Transit Center Building, the new Dey Street Entrance is nearing completion as finishes such as floor and wall tile work, stair treads and electrical work are installed. The Dey Street Entrance should open to the public later this summer.

Underground at the 4/5 Fulton Street Station the structural work at the northern end of the platform has been completed, strengthening a structure that was first opened to the public over 100 years ago as one of New York City’s first subway stations.

The Corbin Building, which is over 120 years old and is being restored and rehabilitated as part of the Fulton Street Transit Center project, is in the process of getting a central HVAC system installed for the first time in that building’s history.

The Fulton Street A/C Station mezzanine continues to receive new finishes, including floor tile and blue-tinted glass tiles on the mezzanine walls. Other components of the Transit Center have already been completed and opened for customer use, including the rehabilitated 2/3 Fulton Street Station, new 4/5 Fulton Street Station southern entrances, a new entrance at 135 William Street, as well as both platforms and a underpass at the R Cortlandt Street Station.

More Rail

A photo of rail tracks in Ottawa, Canada

Building a National Framework for Transit Safety and Consistency

On a recent episode of METROspectives, METRO Magazine’s Executive Editor Alex Roman sat down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the CSA Group, to explore a bold initiative aimed at addressing those challenges: the development of a National Code for Transit and Passenger Rail Systems in Canada.

Read More →
Stairs in a New York rail station with text reading "USDOT Invests $686 Million to Modernize Aging Rail Stations."
Railby StaffMarch 2, 2026

FTA Invests $686M to Modernize Aging Rail Stations

Competitive FTA grants will support accessibility upgrades, family-friendly improvements, and cost-efficient capital projects at some of the nation’s oldest and busiest transit hubs.

Read More →
A purple MBTA train at a Mansfield Station platform.
Railby StaffFebruary 27, 2026

MBTA Updates Rail Modernization Plan to Expand Reliability and Accessibility

The strategy outlines near- and long-term upgrades to ease congestion, support housing growth, and advance statewide climate goals.

Read More →
Ad Loading...
LA Metro underground station with vehicle
Railby StaffFebruary 27, 2026

LA Metro Sets D Line Subway Extension Launch Date

The 3.92-mile addition will soon take riders west beyond its current Wilshire and Western station in Koreatown, continuing under Wilshire Boulevard through neighborhoods and communities including Hancock Park, Windsor Square, the Fairfax District, and Carthay Circle into Beverly Hills.

Read More →
MBTA railcars
Railby StaffFebruary 26, 2026

Boston's MBTA Marks Progress in Regional Rail Modernization

The procurement advances the agency's broader efforts to modernize its rail fleet and position Regional Rail for long-term improvement.

Read More →
An Amtrak Acela
Railby StaffFebruary 26, 2026

Amtrak Sets New Course for Long-Distance Fleet Renewal

Under the plan, all long-distance routes will transition to a universal single-level fleet, replacing today’s mix of bi-level and single-level equipment.

Read More →
Ad Loading...
A TriMet MAX Light Rail vehicle overhead shot
Railby StaffFebruary 24, 2026

STV Finalizes Design for First Phase of TriMet MAX Blue Line Substation Upgrades

The milestone is a significant step toward modernizing the MAX Blue Line’s power infrastructure, one of the oldest components of the region’s light rail system.

Read More →
HDR rendering of LA to Coachella Valley Rail Project
Railby StaffFebruary 20, 2026

HDR Selected to Advance LA–Coachella Valley Rail Corridor Project

The firm will lead the Tier 2 environmental review program for the Coachella Valley Rail Corridor, including the conceptual and preliminary engineering needed to develop project-level environmental clearance.

Read More →
Rendering of Austin Transit Partnership's light rail line.
Railby StaffFebruary 19, 2026

Contractor Chosen to Help Build Austin Light Rail

The ATP board’s approval of ARC enables ATP to begin pre-construction activities and advance final design for Austin Light Rail under the first phase of what will be a multibillion-dollar contract.

Read More →
Ad Loading...
The Gold Line Logo
Railby StaffFebruary 18, 2026

LA Metro A Line Claremont Extension Study Projects $1.1B in Economic Output

Additionally, construction activity is estimated to generate more than $154 million in tax revenue, including more than $20 million for Los Angeles County.

Read More →